Confirms Remote Shutdown Testing Agreements Reached W/Nrc During 880204 Telcon.Revs,Clarifications & Supplemental Info to Remote Shutdown Demonstration Description Encl
ML20196B822
Person / Time
Site: Rancho Seco
Issue date: 02/08/1988
From: Andognini G
SACRAMENTO MUNICIPAL UTILITY DISTRICT
To: Miraglia F
Office of Nuclear Reactor Regulation
References
GCA-88-061, GCA-88-61, NUDOCS 8802120157
Download: ML20196B822 (2)


Text

..

  • hSMU= SACAAMENTo MUNICIPAL UTIUTY DISTRICT O P. O. Box 15830, Sacramento CA 95852-1830,(916) 462-3211 AN ELECTRIC SYSTEM SERVING THE HEART OF CALIFORNIA GCA 88-061 FEB 0 81988 U. S. Nuclear Regulatory Commission Attn: Frank J. Miraglia, Jr.

Associate Director for Projects Phillips Building 7920 Norfolk Avenue Bethesda, MD 20014 Docket No. 50-312 Rancho Seco Nuclear Generating Station License No. DPR-54 REMOTE SHUTDOWN CAPABILITY

Reference:

Correspondence, Andognini to Miraglia (GCA 88-029),

January 25, 1988, same subject.

Dear Mr. Miraglia:

This letter confirms the Remote Shutdown Testing agreements reached with members of your staff during a February 4,1988 telephone conference. The attachment provides revisions, clarifications and supplemental information to the remote shutdown demonstration description provided in the referenced submittal . Our understanding is that the planned remote shutdown capability demonstration, as described in the reference and in the attached supplement, is considered acceptable by your staff.

Please contact me if you have any questions. Members of your staff with questions requiring additional information or clarification may contact Mr. David Compton at (209) 333-2935, extension 4915.

Sincerely,

.fhAyxm G. Carl Andogfiini l Chief Executive Officer, 8802120157 880200 U

Attachment f" DR 60l cc: G. Kalman, NRC, Bethesda 5 0

A. D'Angelo, NRC, Rancho Seco i J. B. Martin, NRC, Walnut Creek J. Dyer, NRR, Bethesda G. Knighton, NRR, Bethesda l

RANCHO sECO NUCLEAR GENERATING STATION D 1444o Twin Cities Road, Herald, CA 96638 9799;(209) 333-2935

- - Attachment GCA 88-061 REMOTE SHUTDOWN DEMONSTRATION

1. The procedure used to perform the remote shutdown capability demonstration will be a Special Test Procedure (STP). The STP will be written in the spirit of Casualty Procedure OP-C.13a, "Plant Shutdown from Outside the Control Room". The OP-C.13a methodologies for secondary side heat removal control and RCS inventory control will be used in the STP. As described in the previous submittal, certain portions of OP-C.13a, such as remote control of Reactor Coolant Pump (RCP) seal injection, will not be demonstrated in the interest of plant and equipment safety. 'he District will submit the STP, with an accompanying description of differences from OP-C.13a, prior to test performance.
2. The cumulative primary side temperature change demonstrated during testing will .be at least 500F. This will be accomplished by a series of smaller temperature increases and decreases of approximately 200F. Each temperature change will be accomplished in a controlled manner, and will be preceded and succeeded by a stabilized temperature plateau.
3. The test will be performed with the minimum shift staffing as prescribed by Administrative Procedure AP.23, "Conduct Of The Operations Division."

Additional personnel may participate as observers.

4. The test will begin at hot shutdown following the planned 25%FP trip test. This will provide for decay heat in the core during testing, and thus more closely simulate the postulated plant conditions during a remote shutdown.