Text
-
December 2, 1988 Docket Nos.:
50-321 50-366 Mr. W. G. Hairston,it -
III Senior Vice Presider Nuclear Operations Georgia Power Company P.O. Box 1295 Birmingham, Alabama 35201 i
Dear Mr. Hairston:
SUBJECT:
NRC BULLETIN 88-03, INADEQUATE HATCH ENGAGEMENT IN HFA TYPE LAT0HING RELAYS MANUFACTURED BY GE NRC Bulletin 88-03 requested licensees to inspect their plants to ensure that all GE latching-type HFA relays installed in Class IE applications have adequate latch engagement.
Your letter of July 5, 1988 in response to the bulletin stated that the latching-type HFA relays in question are not used in safety-related systems at the Hatch plant.
Thank you for your response.
This matter is-considered closed for the Hatch plant.
Sincerely, Lawrence P. Crocker, Project Manager Project Directorate 11-3 Division of Reactor Projects - I/II Office of Nuclear Reactor Regulation cc:
See next page DISTRIBUTION:
._DOCRet Filea NRC PDR Local PDR PDII-3 Reading S. Varga 14-E-4 G. Lainas 14-H-3 D. Matthews 14-H-25 H. Rood 14-H 25 L. Crocker 14-H-25 OGC (for inform. Only) 15-B-18 E. Jordan MNBD-3302 B. Grins 9-A-2 ACRS(10)
P-315 Hatch Plant File
}
}
7hl Ok I
rocker:Is Of tthews 11/J./88 11/gT88 1$/4./88 G812050069 G81202 r
gDR ADOCK 05000321 PDC
8 o
UNITED STATES g
-[
g NUCLEAR REGULATORY COMMISSION 3
j WASHINGTON, D. C. 20555 December 2, 1988 Docket Hos.: 50-321 50-366 Mr. W. G. Hairston,"III Senior Vice Presiden*
Nuclear Operation, Georgia Power Company,
- P.O. Box 1295 Birmingham, Alabama 35201
Dear Mr. Hairston:
SUBJECT:
HRC BULLETIN 88-03, INADEQUATE HATCH ENGAGEMENT IN HFA TYPE LATCHING RELAYS MANUFACTURED BY GE NRC Bulletin 88-03 requested licensees to inspect their plants to ensure that all GE latching-type HFA relays installed in Class 1E applications have adequate latch engagement. Your letter of July 5, 1988 in' response to the bulletin stated that the latching-type HFA relays in question are not used in safety-related systems at the Hatch plant.
Thank you for your response. This matter is considered closed for the Hatch plant.
Sincerely, Lawrence P. Crocker, Project Manager Project Directorate 11-3 Division of Reactor Projects - I/II Office of Nuclear Reactor Regulation cc:
See next pege
i s
Mr. W. G. Hairston, III Edwin I. Hatch Nuclear Plant, Georgia Power Company Units Nos. I and 2 CC:
G. F. Trowbridge, Esq.
Mr. R. P. Mcdonald Shaw, Pittman, Potts and Trowbridge Executive Vice President -
2300 N Street, N. W.
Nuclear Operations Washington, D.C.
26037 Georgia Power Company P.O. Box 1295 Mr. L. T. Gucwa Birmingham, Alabama 35201 Engineering Department,.
Georgia Power Company P. O. Box 1295 Birmingham, Alabama 35201 Nuclear Safety and Compliance Manager l
Edwin I. Hatch Nuclear Plant Georgia Power Company P. O. Box 442 Baxley, Georgia 31513 Mr. Louis B. Long Southern Company Services, Inc.
P. O. Box 1295 Birmingham, Alabama 35201 Resident Inspector U.S. Nuclear Regulatory Comission Route 1, Box 725 Baxley, Georgia 31513 Regional Administ,ator, Region II U.S. Nuclear Regulatory Comission 101 Marietta Street, Suite 2900 Atlanta, Georgia 30323 Mr. Charles H. Badger Office of Planning and Budget Room 610 i
270 Washington Street, S.W.
Atlanta, Georgia 30334 Mr. J. Leonard Ledbetter, Comissioner Department of Natural Resources 270 Washington Street, N.W.
Atlanta, Georgia 30334 Chairman Appling County Comissioners County Courthouse Baxley, Gworgia 31513 i