Confirms Plans for 890104 Public Meeting at Plant Visitor Ctr to Present SALP 7 Rept for Plant.Appropriate Corporate & Plant Mgt Representation Encouraged to Attend Meeting to Ensure Mutual Understanding of NRC Issues & Findings
ML20195J537
Person / Time
Site: Quad Cities  Constellation icon.png
Issue date: 11/29/1988
From: Greenman E
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To: Reed C
COMMONWEALTH EDISON CO.
References
NUDOCS 8812020240
Download: ML20195J537 (2)


Text

. .

~

j itMog[ UMTED STATES

.. g NUCLEAR REGULATORY COMMisslON y S e4EClON lil 5 f 799 ROOScVcLT RO AD j cec ~ ctev~. itu~O,5 ..n, HOV 2 9 El Docket No. 50-254 Docket No. 50-265 Commonwealth Edison Company ATTN: Mr. Cordell Reed Senior Vice President Post Office Box 767 Chicago, IL 60600 Gentlemen:

This confirms our plans as discussed between Ms. I. Johnson of your staff and Mr. D. Jones of this office to have a meeting with you and members 'of your staff at the Quad Cities Nuclear Power Station Visitors Center on January 4,1989.

The purpose of the meeting is to present the SALP 7 report for Quad Cities.

We encourage you to have appropriate corporate and plant mar,agement representation at the meeting to ensure a mutual understanding of the issues and findings being presented by the NRC.

While this meeting is considered a presentation and discussica forcT between Commonwealth Edison Company and the NRC, the meeting will be opened to any other interested parties as observers. Those persons outside the licensee and NRC staffs should inarm the Regional Office of their intent to participate.

We hope this meeting will benefit your organization and provide you with a meaningful characterization of the overall safety performance for the Quad Cities plant.

Sincerely, hL dward G. Gr man, Dire or Division of Reactor Projects See Attached Distritution GG12020240 681129 I Q

PDR ADOCK 05000'54 S F5

, ,, . 6 o

, . Commonwealth Edison Compa::y 2 NOV 2 91980 Distribution cc: H. Bliss, Nuclear Licensing Manager R. L._Bax, Plant Manager