Forwards NRC near-term OL Criteria Developed to Resolve Question of Certification to 10CFR50.55a.Compliance to Criteria & Util 880909 Response to NRC Bulletin 88-005 Will Provide Bases for Assuring Full Compliance W/Asme Code
ML20195E197
Person / Time
Site: Shoreham File:Long Island Lighting Company icon.png
Issue date: 10/28/1988
From: Brown S
Office of Nuclear Reactor Regulation
To: Leonard J
LONG ISLAND LIGHTING CO.
References
IEB-88-005, IEB-88-5, NUDOCS 8811070289
Download: ML20195E197 (6)


Text

.

. e ,Js nuoq

,4 ,jog . UNITED STATES g g . NUCLEAR REGULATORY COMMISSION t l WASHINGTON, D C. 20656

\ ... /

+

Octcber 28, 1988 Docket No.: 50-322 Mr. John D. Leonard, Jr.

Vice President - Nuclear Operations long Island Lighting Company Shoreham Nuclear Power Station P. O. Box 618 North Country Road Wading River, New York 11792

Dear Mr. Leonard:

SUBJECT:

BULLETIN 88-05 SUPPLEMENTAL NEAR-TERM-OPERATING LICENSE (NTOL)

CRITERIA As you are aware, when the NRC issues an operating license, both the staff and the applicant are required to certify that the facility being licensed is designed and built in accordance with the regulations. Because 10 CFR 50.55a.

"Codes and Standards" includes ASME Code requirements, both certifications must consider the matter of compliance with the ASME Code.

Earlier this year the staff learned of potential ASME Code nonconformance problems for piping materials supplied by either the Piping Suppliers Inc.

or the West Jersey Manufacturing Companies. The staff's initial concerns were if any of these potential nonconforming components were installed in safety related piping systems and, if installed, would their strengths be sufficient to ensure that their safety functions would not be compromised. NRC Bulletin No. 88-05 and its two supplements address these concerns. LILCO's September 9, 1988 response to these documents provided the results of a vendor-specific component search and subsequent harn ess testing results for the suspect components installed in safety relateJ piping systems. Based on LILCO's testing, all suspect components installed in safety related piping systems exceeded the NRC/NUMARC hardness acceptance criteria.

However, the question of certification to the regulation is now the imme'"ate concern for plants to be licensed. In order to resolve this issue the caff has developed the attached NTOL criteria. These criteria are also appi', cable to the Seabrook and Shoreham plants. Compliance with these criteria coupled with LILC0's September 9, 1988 response will provide the bases for either assuring full compliance with the ASME Code requirements or finding the nonconforming components to be acceptable alternatives as allowed by 10 CFR 50.55a(a)(3).

(

8911070289 831028 '}

PDR ADOCK 03000322 Q PDC

4

,s?. l l

Should you have any questions on this matter please do' not hesitate to call me (301) 497-1444. I Sincerely,

/s/ '

Stewart W. Brown, Project Manager Project Directorate I-2.

Division of Reactor Projects I/II Office of Nuclear Reactor Regulation

Enclosure:

As stated cc w/ enclosures:

See next page

,.,MS"R;BUTION I L :wuen:nle *4:';>

NRC PDR/LPDR .

PDI-2 Reading SVarga/BBoger

  • WButler M0'Brien '

SBrown/GRivenbark i OGC i

EJordan/8 Grimes ACRS (10) t i

P 4

F I  ;-

4 I

t I

PDI-2/PM ' PDI-2/D SBrown:t WButler (0 N88 \Dl),0l88 l

[

Should you have any questions on this matter please do not hesitate to call me (301) 492-1444.

Sincerely, Stewart W. Brown, Project Manager Project Directorate I-2 Division of Reactor Projects I/II Office of Nuclear Reactor Regulation Encle:ere:

As stated cc w/ enclosures:

See next page 1

4 1

4 4

f 1,

a

Mr. John D. Leonard, Jr. Shoreham Nuclear Power Station Long Island Lighting Company (list 1) cc:

Stephen B. Latham, Esq. Gerald C. 'ruity Esq.

John F. Shea, III Esq. Ben Wiles, Esq.

Twomey, Latham & Shea Counsel to the Governor Attorneys at Law Executive Chamber Post Office Box 398 State Capitol 33 West Second Street Albany, New York 12224 Riverhead, New York 11901 Herbert H. Brown, Esq.

Alan S. Rosenthal, Esq., Chairman Lawrence Coe Lanpher, Esq..

Atomic Safety & Licensing Appeal Board Karla J. Letsche, Esq.

U.S. Nuclear Regulatory Comission Kirkpatrick & Lockhart Washington, D.C. 20555 South Lobby - 9th Floor 1800 M Street, N.W.

Washington, D.C. 20036-5891 W. Taylor Reveley, III Esq.

Hunton & Williams Dr. Monroe Schneider Post Office Box 1535 North Shore Comittee 707 East Main Street- Post Office Box 231 Richmond, Virginia 23212 Wading River, New York 11792 Howard A. Wilber Fabian G. Palomino, Esq.

Atomic Safety & Licensing Appeal Board Special Counsel to the Governor U.S. Nuclear Regulatory Comission Executive Chamber - State Capitol Washington, D.C. 20555 Albany, New York 12224 Atomic Safety & Licensing Board Panel Anthony F. Earley, Jr. , Esq.

U.S. Nuclear Regulatory Comission General Counsel Washington, D.C. 20555 Long Island Lighting Company 175 East Old County Road Atomic Safety & Licensing Appeal Board Hicksville, New York 11801 Panel U.S. Nuclear Regulatory Comission Mr. Lawrence Britt Washington, D.C. 20555 Shoreham Nuclear Power Station Post Office Box 618 Gary J. Edles Esq. Wading River, New York 11792 Atomic Safety & Lictnsing Appeal Board U.S. Nuclear Regulatory Comission Martin Bradley Ashare. Esq.

Washington, D.C. 20555 Suffolk County A'torney H. Lee Dennison Building Richard M. Kessel Veteran's Memorial Highway ,

Chairman & Executive Director Hauppauge. New York 11788 New York State Consumer Protection Board Room 1725 Resident Inspector 250 Broadway Shoreham NPS New York, New York 10007 U.S. Nuclear Regulatory Comission Post Office Box 8 Jonathan D. Feinberg, Esq. Rocky Point, New York 11778 New York State Department of Public Service Regional Administrator, Region I Three Empire State Plaza U.S. Nuclear Regulatory Comission Albany, New York 12223 475 Allendale Road King of Prussia, Pennsylvania 19aN

s .

Long Island Lighting Company Shoreham (1) i cc:

Robert Abrams Esq. Town Attorney Attorney General of the State Town of Brookhaven of New Y)rk 3232 Route 112

, ATTN: John Corwin, Esq. Medford, NY 11763 l New York State Department of Law

! Consumer Frotection Bureau State of New York 120 Broadray Department of Law 3rd Floor ATTN: Charlie Donaldson, Esq.

New York. New York 10271 120 Broadway Mr. William Steiger Plant Manager Shoreham Nuclear Power Station Post Office Box 628 Wading River, New York 11792 l

l MHB Technical Associates l 1723 Hamilton Avenue - Suite K l San Jose, California 95125 l

l Honorable Peter Cohalan Suffolk County Executive l

County Executive / Legislative Building l Veteran's Memorial Highway Hauppauge, New York 11788 Ms. Donna Ross New York State Energy Office Agency Building 2 Empire State Plaza Albany, New York 12223 Ms. Nora Bredes Shoreham Opponents Coalition 195 East Main Street Smithtown, New York 11787 Chris Nolin New York State Assembly Energy Consnittee 626 Legislative Office Building Albany, New York 12248 j

....,=.

ATTACHMENT Supplemental NRC staff criteria to demonstrate an acceptable level of quality and safety of piping materials potentially not conforming to ASPE Code requirements:

1. All installed suspect components must be identified, including all flanges, fittings and welded lugs.
2. All components not meeting SA 105 hardness requirements (BHN 187-137) shall be tested to assure that their chemistry is conforming. These components must also be evaluated for the applicable service loading conditions and the reduced material strength of the components to detennine the adequacy of design margins,
3. A statistically valid sampling plan (such as Mil-STD-1050, Table I and iia) shall be performed to determine that the chemistry of all the suspect parts conforms to SA 105 requirements. Each heat of material representing installed material should be included.

4 Credit for previously tested samples from representative heats may be taken for the sarrpling of the non-conforming components under 2) above when the number of required heats is determined under 3).