PNS-V-86-003:on 860514,offsite Power on Three of Four Transmission Lines Lost Due to phase-to-ground Faults.Caused by Straps Slung Over Lines.Sabotage Suspected.Law Enforcement Agencies Notified
ML20195C188
Person / Time
Site: Palo Verde  Arizona Public Service icon.png
Issue date: 05/15/1986
From: Norderhaug L, Schuster M
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION V)
To:
References
PNS-V-86-003, PNS-V-86-3, NUDOCS 8605300156
Download: ML20195C188 (1)


Text

a yPT TENArf KOTIFICATION OF SAFEGUARDS EVENT PNS-V-86-03 Date:May 15, 1986

Thic preliminary notification constitutes EARLY notice of events of POSSIBLE national e,ecurity or public interent significance. The information presented is as initially Tecsived without verification or evaluation and is basically all that is known by etise Legion V staff on this date.

' ~

-FACILITY: Arizona Nuclear Power Project Emergency Classification Palo Verde Units 1, 2 and 3 Notification of Unusual Event Docket Nos. 50-528, 50-529 and 50-530 Alert Wintersburg, Arizona

_ Site Area Emergency General Emergency X Not Applicable

SUBJECT:

SUSPECTED SABOTAGE: LOSS OF THREE OF FOUR OFFSITE POWER SOURCES Da May 14,1986, be83nning at approximately 8:59 PM, PDT, offsite power on 3 of 4 trcusaission lines was lost due to phase-to ground faults on each line. The power remained

= faulted through the evening until late on May 15, 1986. During the morning hours of May 15, the licensce's investigation found that a rope or strap had been slung over the transmission Ifnes causing a phase to ground fault. The licensee also found evidence that a cin11ar but unsuccessful attempt was made to knock out the 4th line..The locations of the atreps on each line was about 35 miles from the plant.

Tha transmission lines converge on the site from 4 different directions.. The grounding straps were far enough apart to require a coordinated effort by several individuals to recomplish the power loss within a few minutes. Unit 1 is currently in Mode 5 for o maintenance outage. Unit 2 is complying with the Technical Specification action statement reg:rding electrical power sources, and is holding in Mode 3 pending completion of the licznsee's investigation. Unit 3 is in the preoperational test phase.

Tha licensee has notified local law enforcement agencies and the FBI. The licensee strongly.

gumpects sabotage and intends to issue a press release.

Th2 Region was notified at approximately 8:00 AM, FDT, May 15, 1986, by the resident inspectors who are closely monitoring the if censee's investigative efforts.

Tha IAT, FBI, Headquarters Operations Center and EDO have been notified.

This information is current as of 3:00 PM, PDT, May 15, 1986.

CONTACT:

1. R. Norderhaug, FTS 463-3775 or M. D. Schuster, FTS 463-3780 8605300156 860515

-V

-003 PDR DISTRIBUTION

-H St.

MNBB Phillips E/W W111ste Air Rights Mafi:

-Chairman Pa111dino EDO NRR IE NMSS ADM:DMB

'Comm. Zech

~PA OIA RES DOT:Trans.Only

'Comm..Bernthal MPA AEOD Applicable State Comm. Roberts ELD j

Comm. Asselstine Regions :

V

[($,

}

SECY INFO NSAC

'ACRS Licensee:

CA (Reactor Licensees)

REGION V: FORM 211 y

l-PDR Resident Inspector _

(Revised-11/15/85) l-

~

--