CONTAINMENT SYSTEMS 3/4.6.4 CCMBUSTIBLE GAS CONTROL HYDROGEN ANALYZERS LIMITING CONDITION FOR OPERATION 3.6.4.1 Two independent containment hydrogen analyzers shall be OPERABLE.
APPLICABILITY:
MODES 1 and 2.
ACTION:
a.
With one containment hydrogen analyzer inoperable, restore the inoperable analyzer to OPERABLE status within 30 days or be in at least HOT STANDBY within the next 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br />, b.
With both containment hydrogen analyzers inoperable, restore at least one analyzer to OPERABLE status within 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> and comply with the requirements of ACTION a, or be in at least HOT STANDBY within the next 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br />.
SURVEILLANCE REQUIREMENTS 1,
4.6.4.1 Each hydrogen analyzer shall be demonstrated OPERABLE by the performance of a CHANNEL FUNCTIONAL TEST at least once per 31 days, and at least once per 92 days on a STAGGERED TEST BASIS by performing a CHANNEL CALIBRATION using sample gases containing:
a.
Zero volume percent hydrogen, balance nitrogen.
b.
9.5 volume percent hydrogen, balance nitrogen.
8806210483 880602 PDR ADOCK 05000392 P
DCD I
WATERFORD - UNIT 3 3/4 6-34
1 1
4 b
i i
)
ATTACIOiENT B 4
PROPOSD
' ~
mac,mm o CONTAINMENT SYSTEMS 3/4.6.4 COMBUSTIBLE GAS CONTROL HYOR0 GEN ANALYZERS LIMITING CONDITION FOR OPERATION 3.6.4.1 Two independent containment hydrogen analyzers shall be OPERABLE.
APPLICABILITY:
MODES 1 and 2.
ACTION:
With one containment hydrogen analyzer inoperable, restore the a.
inoperable analyzer to OPERABLE status within 30 days or be in at least HOT STANDBY within the next 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br />, b.
With both containment hydrogen analyzers inoperable, restore at least one analyzer to OPERABLE status within 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> and comply with the requirements of ACTION a, or be in at least HOT STANDBY within the next 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br />.
SURVEILLANCE REQUIREMENTS
- 4. 6/'4.1 ch by ogen anal er sh 11 b demons rated PERAB by he j
p forma ce of CHAN LF CTIO L TE at 1 st on per 1 da s, an at I ast nce pe 92 da s on STA ERED EST SIS b perfo ing CHAN L CA BRAT ON using ample ases ontafning:
2 Zero volume percent hydrogen, balance nitrogen.
a.
~<
b.
9.5 volume percent hydrogen, balance nitrogen.
4.6.4.1 At least once per 31 days each Hydrogen Analyzer shall be demonstrated OPERABLE by performing a CHANNEL CALIBRATION using sample gases containing a nominal:
WATERFORD - UNIT 3 3/4 6-34
- -.