High Energy Arcing Faults (HEAF) - Update Michael Cheok Office of Nuclear Regulatory Research Division of Risk Analysis June 30, 2020 1
=
Background===
- Planned 2020 testing currently on hold to address Working Group and stakeholder comments.
- Technical issues being addressed as part of NRC-EPRI Working Group 2
HEAF Program Status
- EPRI completed the industry survey and associated preliminary risk analysis.
- NRC completed a draft project plan, and preliminary insights and conclusions based on the tests completed to date.
- WG to finalize a detailed project plan to integrate industry survey, plant operating experience, realistic plant configurations, the PRA model, and test data.
- NRC will continue to keep the public and stakeholders informed via NRC website and public meetings.
3
Questions 4