tOw nECEl'IED NEC Arizona Nuclear Power Project 33 v'? 12 PM 12: 'il P O. Box 52034 e PHOENIX, ARIZONA 85072-2034 May 7, 1986 t
ANPP-36519-EEVB/LAS/DRL U. S. Nuclear Regulatory Commission Region V 1450 Maria Lane - Suite 210 Walnut Creek, CA 94596-5368 Attention:
Mr. D. F. Kirsch, Acting Director Division of Reactor Safety and Projects Palo Verde Nuclear Generating Station (PVNGS)
Unit 3 Docket No. 50/530
Subject:
Time Extension For Report - DER 86-11 A 50.55(e) Potentially Reportable Deficiency Relating to Skinner Solenoid Valves File: 86-006-216; 86-056-026; D.4.33.2
Reference:
(A) Telephone Conversation between R. C. Sorenson and D. R. Larkin on March 14, 1986 (Initial Reportability - DER 86-11)
(B) ANPP-36087, dated April 14, 1986 (Interim Report - DER 86-11)
Dear Sir:
The NRC was notified of a Potentially Reportable Deficiency in Reference (A) and an Interim Report was issued by Reference (B). At that time it was estimated that a Final Report would be available by May 16, 1986.
Due to review comments indicating the need for additional investigation and eval-uation of the transportability and root cause, it is now expected that this infor-i mation will be finalized by June 2,1986, at which time a complete report will be submitted.
4 There is no new information or change to the Interim Report at this time.
Very truly you Qq e m L,
C, C t.A A.,_
nUd E. E. Van Brunt, Jr.
8605290009Og{h8530 Executive Vice President PDR ADOCK O PDR Project Director S-EEVB/DRL/1df Idf/001/TE8611 cc: See Page Two
? 0 YS]
,e.v -,, :- r: - -
e :; y
[ OL *7
- [
DER 86 Time Extension-
'Mr.oD. F. Kirsch
- Acting Director ANPP-36519-EEVB/LAS/DRL-92.11
.May 7, 1986 Page 2 cc:
J. M.' Taylor, Director.
Office of Inspection and Enforcement U.; S.-Nuclear Regulatory Commission Washington,-D. C. 20555 A. C. Gehr (4141) 1.