Washington Public Power Supply System Box 1223 Elma, Washington 98541-1223 (206)482-4428 May 20, 1986 G03-86-298 Docket No. 50-508 Director of Nuclear Reactor Regulation Attention:
G. W. Knighton, Director PWR Project Directorate No. 7 U. S. Nuclear Regulatory Commission Washington, D. C.
20555
Subject:
NUCLEAR PROJECT N0. 3 RESPONSE TO GENERIC LETTER 83-28 SALEM ATWS EVENTS
References:
a)
Letter (G03-83-681), G. C. Sorensen to D. G. Eisenhut, same subject, dated August 23, 1983.
b)
Letter (G03-86-146),
G.
C.
Sorensen to H. R. Denton, subject "WNP-3 Revised Construction Permit Amendment Request", dated March 10, 1986.
The Supply System has received an informal NRC request to update reference a).
Specifically, additional information was requested regarding Items 3.1.3 and 3.2.3 of the subject document.
Ob a
I Y
B605270234 860520 PDR ADOCK 05000508 P
Director of Nuclear Reactor Regulation G03-86-298 Atttation:
G. W. Knighton, Director May 20, 1986 Page Two These ite.ns have to do with Post Maintenance Test Requirements in existing Technical Specifications which can be demonstrated to degrade rather than enhance safety.
Item 3.1.3 pertains to Reactor Trip System components and Item 3.2.3 pertains to all other Safety Related componer.ts.
Because of the extended construction delay at WNP-3, Operational Phase Test and Maintenance procedures have been only partially completed and Technical Specifications have not been written.
We plan to have these sufficiently complete to allow a response to Items 3.1.3 and 3.2.3 one year prior to fuel load.
The preparation of the procedures and Technical Specifications will consider the stated staff positions for Items 3.1.3 and 3.2.3.
Consistent with reference b), the NRC should use July 1998 as the earliest date for fuel load for planning purposes.
Should you have any questions or desire further clarification, the Supply System point of contact regarding this matter is Mr. D. W. Coleman, WNP-3 Project Licensing Manager, Ext. 5436.
Very truly yours, b
G. C. Sorensen, Manager Regulatory Programs,
AJM/cae cc:
Mr. J. A. Adams, NESCO Mr. R. M. Boucher, Pacific Power & Light Co.
Mr. W. L. Bryan, Washington Water Power Co.
Mr. J. Crnich, Ebasco - Elma Mr. W. J. Finnegan, Puget Sound Power & Light Co.
Mr. J. R. Lewis, BPA Mr. N. S. Reynolds, Bishop, Liberman, Cook, Purcell & Reynolds Mr. D. Smithpeter, BPA Mr. B. D. Withers, Portland General Electric Co.