Notice of Deviation from Insp on 860224-0313
ML20155D959
Person / Time
Site: Clinton Constellation icon.png
Issue date: 04/11/1986
From: Paperiello C
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To:
Shared Package
ML20155D949 List:
References
50-461-86-13, NUDOCS 8604170471
Download: ML20155D959 (1)


Text

,

NOTICE OF DEVIATION Illinois Power Company Docket No. 50-461 As a result of the inspection conducted on February 24 through March 13, 1986, and in accordance with the " General Policy for NRC Enforcement Actions,"

10 CFR Part 2, Appendix C (1985), the following deviation was identified:

In the Final Safety Analysis Report, the licensee connitted to preoperational/

acceptance test the Security battery in accordance with the Institute of Electrical and Electronics Engineers (IEEE) Standard 450-1980.

Contrary to the above, the capacity of the Security battery was not detennined during acceptance testing as required by the IEEE Standard 450-1980.

(461/86013-03)

This is a Deviation (Supplement II).

Pursuant to the provisions of 10 CFR 2.201, you are required to submit to this office within thirty days of the date of this Notice a written statement or explanation in reply, including:

(1) corrective action taken and results achieved; (2) corrective action to be taken to avoid further deviations; and (3) the date when full compliance will be achieved. Consideration may be given to extending your response time for gocd cause shown.

L} }l} -fb j'

MMa Fated /

l Carl J./ Paper 1 llo, Director Divisich of R ctor Safety h$$ hh G

'