ML20155D188

From kanterella
Jump to navigation Jump to search
Forwards List of Open Items Based on Review of Readiness Review Module 11 Re Pipe Stresses & Supports Per Insp Rept 50-425/88-19.Pipe Support & Pipe Stress Analysis Acceptable, Except for Two Items Identified in Encl
ML20155D188
Person / Time
Site: Vogtle 
Issue date: 09/22/1988
From: Grace J
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To: Hairston W
GEORGIA POWER CO.
References
NUDOCS 8810110110
Download: ML20155D188 (3)


See also: IR 05000425/1988019

Text

'

-l '

.

..

-

.

,

'

C lc6to(

'

,

s,

.

/

,

SEP 2 2 1968

Docket No. 50-425

License No. CPPR-109

Georgia Power Company

/ ATTN: Mr. W. G. Hairston, III

Senior Vice President

Nuclear Operations

P. 0. Box 4545

Atlanta, GA 30302

Gentlemen:

SUBJECT: NRC EVALUATION OF V0GTLE 2 READINESS REVIEW 0F PIPE STRESS AND

SUPPORTS MODULE N0. 11

The NRC has performed a review of the Pipe Stress and Supports for Vogtle Unit 2

covered by Readiness Review Module 11 submitted on April 19, 1988.

Based upon

NRC inspection review of those activities identified in the module, we have

determined that the Pipe Supports and Pipe Stress Analysis at Vogtle 2 are

acceptable with the exception of the two items in Enclosure 1.

This decision

is based on information presently available to the inspectors and reviewers.

Should information become available which was not considered during this review

or which conflicts with earlier information, it will be evaluated to determine

what effect it may have en the above conclusion.

Please contact us should you have any questions concerning this lctter.

Sincerely,

Hl

!

/

J. Nelson Grace

Regional Administrator

Enclosures:

1.

List of Open Items

2.

Inspection Report No. 50-425/88-19

cc w/encls:

vR. P. Mcdonald, Executive Vice

,, President, Nuclear Operations

y P. D. Rice, Vice President, Project

Director

(cc w/ercis cont'd - see page 2)

\\

8810110110 880922

I\\

PDR

ADOCK 05000425

Q

PDC

JDl

e

-

-

. , .

.

,

,

.

,

.

,

.

'

'

.

,"

SEP 03 1968

.

Georgia Power Company

2

d(cc w/encls cont'd)

C. W. Hayes, Vogtle Quality

Assurance Manager

gG. Bockhold, Jr., General Manager,

Nuclear Operations

./J. P. Kane, Manager, Nuclear Licensing

and Engineering

f.A. Bailey,ProjectLicensing

Manager

yB.W. Churchill,Esq.,Shaw,

Pittman, Potts and Trowbridge

v0. Kirkland, 111, Counsel.

Office of the Consumer's Utility

Council

v0. Feig, Georgians Against

Nuclear Energy

State of Georgia

bec w/encis:

'E. Reis, 0GC

14. Hopkins, NRR

M. Sinkule, Rll

DRS, Technical Assistant

vNRC Resident inspector

Document Control Desk

.ff

NII ,3

RJ .,(

^

)

e., y

Rll

SVias:ser

C?atterson

MSinkule

VBrohnlee [Jkeyes

M6nsI

08/;c/88

CJ/ta/88

08/4 /86

02/1 '/88

ff/.2 088 , 08/ /88

1

'l

(I

se c

,, tz

yp

Q i,

  • 1-*--

%=ss

P*'

'

g.

  • % m/ce/s3

-";f/ ,3 / s s

-

..

- ..

. ;<

.

,

'

'

-

.,

,

,

,

,

1

?

ENCLOSURE i

List of Open Items

,

Violation 50-425/88-19-01:

Failure to Follow Procedures,

Resulting in Errors in Pipe

Support

QC

and

Design

Documentation

Inspector Followup Item 50-425/88-19-02:

Potential

Problems

with

j

Spring Can Travel

.i

<

I

i

l

l

I

J

i

!

l

!

4

!

!

.

I

I

i

1

l

.i

4

. _ _ _ , . - _ . _ _ _ _ . _ _ , , ,

_

.

_ _ _ _ _ , _ . _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ . _ _ _ . _ , _ . _ . . _ . , _ _ _ . _ _ _ , ,

_

. _ . .

_.

. _ _ _ _ _ _ .

_

7 ,, .

,.

ENCLOSURE 2

.

' ' '

, , .

na seg

UNITED STATES

.'

, g

g

NUCLEAR REGULATORY COMMISSION

,,

/*

CEGION ll

..j . , I *I

101 M ARIETTA STRE ET. N W.

' * '

'e

ATLANTA,0EORGI A 30323

y %.

,/

t

  • ....

AUG 18 WS

-

Docket No. 50-425

License No. CPPR-109

Georgia Power Com)any

ATIN:

Mr. W. G. Mairston III

SeniorVice-President

Nuclear Operations

P. O. Box 4545

Atlanta, GA 30302

Gentlemen:

.

SUBJECT:

NOTICE OF VIOLATION

-

(NRC INSPECTION REPORT NO. 50-425/88-19)

'

inis refers to the Nuclear Regulatory Commission (NRC) inspection conducted

by S. J. Vlas on May 11-12 June 6-10, and July 11-14, 1988.

The inspection

included a review of activities authorized for your Vogtle facility.

At the

conclusion of the inspection, the findings were discussed with those members

of your staff identified in the enclosed inspection report.

Areas examined during the inspection are identified in the report.

Within

these areas, the inspection consisted of selective examiMtions of procedures

and representative records, interviews with personnel, and observation of

j

activities in progress.

!

The inspection findings indicate that certain activities appeared to violate

NRC requirements.

The violation

references to pertinent requirements, and

elements to be included in your r,esponse are described in the enclosed Notice

of Violation.

l

In accordance with Section 2.790 of the NRC's "Rules of Practice," Part 2,

l

Title 10, Code of Federal Regulations, a copy of this letter and its enclosures

will be placed in the NRC Public Document Room.

l

Theresponsesdirectedbythisletteranditsenclosuresarenotsubjecttothe

clearance procedures of the Office of Management and Budget as required by the

,

Paperwork Reduction Act of 1980, Pub. L. No.96-511.

.

7:4);:.we ; , ;

,

.

,

.. v

.. .

-

. :.

.

,.

,.

.

/

AUG 181988

.

Georgia Power Company

2

,

Should you have any questions concerning this lett'er, please contact us.

Sincerely,

gun

r

L. Brownlee, Chief

React r Projects Branch 3

DivisionofReactorProjects

Enclosures:

1.

Notice of Violation

2.

NRC Inspection Report

cc w/encis:

'

R. P. Mcdonald, Executive Vice

President Nuclear Operations

P. D. Rice,,Vice President,' Project

Director

C. W. Hayes, Vogtle Quality

.'

'

Assurance Mana

G. Bockhold, Jr.gerGeneral Manager,

Nuclear Operations

J. P. Kane, Manager, Nuclear Licensing

and En ineering

J.A.Baley,ProjectLicensing

Mana er

8. W.

hurchill, Esc.

Shaw

Pittman, Potts anc trowbrldge

D. Kirkland, III, Counsel,

Office of the Consumer's Utility

Council

D. Feig, Georgians Against

Nuclear Energy

__ ___.

,

> .. .

. . . . .,

.

'

-

..

,

,

,

.

?

,

'

ENCLOSURE 1

NOTICE OF VIOLATION

Georgia Power Company

Docket No. 50-425

Vogtle Unit 2

License No. CPPR-109

During the Nuclear Re

May 11-12, June 6-10, gulatory Commission (NRC) inspection conducted on

and July 11-14

1988, violations of NRC requirements

were identified.

The violation involv,ed pipe sup) ort design and construction.

In accordance with the "General Statement of Policy and Procedure for NRC

Enforcement Actions," 10 CFR Part 2, Appendix C (1988), the violation is listed

below:

.

Criterion V of Appendix B to 10 CFR Part 50, as implemented by FSAR

1

Chapter 17, Section 17.1.5 states in part: Activities affecting quality

shall be prescribed by' documented instructions, procedures, or drawings

... and shall be accom

procedures, or drawings plisited in accordance with these instructions, ,

1.

Pullman Power Products Procedure X-24, "As-Builting Piping Systems

'

and Related Components"

details requirements for as-builting and

-

.

documentation of informa, tion necessary for the performance of stress

1

'

analysis reconciliation.

Specifically Section 4.1.1, states that

"Mylars shall be revised to incorporate the as-built information,

when the actual dimension differs from the design dimension beyond

applicable measurement tolerance, but is within allowable construc-

tion tolerance."

,

Contrary to the above, the following discrepancies were fnund to be

'

properly ' redlined' and documented on a copy of the pipe support

drawing in the PPP Process Package, but were not incorporated into

the Mylars,

o

V2-1204-014-H004, the actual si:e of item 'b'.

,

V2-1204-014 H006, the dimension from the centerline W4 to the

!

c

centerline of the embeded plate.

,

'

j

o

V2-1208-005-H007, the dimension for item #4 was shown on the

!

drawing as 3 5/8", the inspectors measured in the field and the

' redline' drawing, both indicated that the dimension was 51/2".

'

V2-1208-145-H017, the pin-to pin dimension of the spring can,

o

drawing shows 12'-10 5/16", and the ' redline' and the dimension

the inspectors measured was 12'-11".

,

<

i

i

- _ _ , . _ . -

__ -

-_

_ __

._

_,_

- -

_ - ___ - -__

- _ - -

'

,,. :.

'

,.

.

.

,

, ,-

-

..

,

,

-

3

-

Georgia Power Company

2

Docket No. 50-425

Vogtle Unit 2

License No. CPPP.-109

~

,

.

o

V2-1208-145-H016, the Bill of Materials shows item #5 as 8"

wide, the inspectors measured the dimension as 8 3/4", this is

the same dimension as the ' redline' drawing,

o

Isometric 2K3-1208-146-01, Detail 2 & 3, indicate a class change

from 212/FGO

on Line 1208-145-4" to 414/FG4, on Line

1208-A20-1/2",.

The Line Designation List (LDL) shows

1208-A20-1/2" as 424/FG4.

OCN-F #7, dated 2-3-86, changed the

line to 414/FG4.

o

V2-1208-145-H017, the location of the beam attachment on the

drawing shows the 'as-built' dimension as l'-31/2", documen-

tation in the Process package and the Final Inspection Report,

both show the dimension to be l'-2 3/4".

4

Isometric 2K3-1205-006-01, from' 0CN #8, the class information

o

was not transferred correctly to the isometric. Also, not all

the information from FEDCNR-2262, was transferred to the

'as-built' isometric.

.

2.

Pullman Power Products, Procedure IX-50, "Pipe Support Field Instal-

lation and Fabrication Procedure", Section 11.1, states in part that,

a

i

"Each support shall be visually inspected for compliance with thg

support drawing and this procedure.'

Section 12.5.1, states in part

4

with this procedure.g'that, "The fie

d en ineers will as-built all supports in accordance

t

Contrary to the above, the above sections were not met in that, the

following drawings, both P&ID and pipe supports were found to have

discrepancies between the actual condition in the field and the

,

drawing; or pertinent information was missing from support drawings,

V2-1208-055 H052, shows the angle f ron, item 5, in the wrong

,

o

orientation.

4

o

V2-1208-055-H014, in the Location Plan, the vertical pipe is

shown as going in the (-)Y direction, in the field it is going

in the (+)Y direction,

,

l

'

o

V2-1208-255-H002, the drawing shows the dimension from the

centerline

of item #2 to the centerline of the pipe as

l'-4 1/4" ACT., the inspectors measured l'-2 1/4".

o

V2-1204-063 H004,

the

location of the attachment for

V2-1204-201-H002, item #a, to the embed plate, shows the

dimension from the right side of the embed plate to the

attachment as 2 3/8", the inspectors measured 3 1/16".

i

,

. , - - - - - .

,-n----

- - - - - _ _ - - . - - _ - -

- -

- - - - - - , , , - - , , , , _ _ - - _ _ - - - , _ _ , - - , . - - - - - , - - - , . _ -

.

'

..

. . :.

.

-

..

,.

,

,

-

.;

'

Georgia Power Company

3

Docket No. 50-425

l

Vogtle Unit 2

License No. CPPR-109

'

"

o

P&ID 2X4DB122, shows a line, designated as Line 006-8",

(coordinate C-5), and fust to the left of TE 0613, should be

Line 008-8".

o

V2-1205-004-H016, in the process package, the "Strut Reconcilia-

tion Report" (SRR), of 5-26-87, indicates two struts were

installed, SRR of 10-14-86, shows one strut and SRR of 5-18-88,

indicates that two struts were installed.

The piae support

drawing, (R/3), shows one strut.

There is also a d'screpancy of

the offset angles, in SRR of 10-14-86, it indicates 3 degrees,

SRR of 5-26-87, indicates 2 degrees,

o

V2-1205-006-H014, the Process Package has two different issue

tickets for the sprino can that was 'nstalled, both for the same

serial number of 8013066, they. also indicate two different

spring can sizes.

o

V2-1204-063-H007, was installed on the wrong vertical pipe.

The

support drawing had the correct location for the support.

3.

Pullman Power Products, Procedure IX-50

"Pipe Sup

Installation and Fabrication Procedure", $ection 6.6, port Field

states in part

that, "The locating dimension en the attached support in relation to

a connection point on the parent shall be documented on the attached

support (baby) drawing."

Contrary to the above, the above section was not met in that, the

following pipe support drawings, were found to not have the proper

locating dimension of the baby supports.

V2-1208-215-H003, -H004, -H005, all three drawings did not have

o

a locating dimension for the attached support (baby) in relation

to a connection point on the parent support.

This is a Severity Level V violation (Supplement II.E).

,

Pursuant to the provisions of 10 CFR 2.201, is hereby required to submit a

written statement or explanation to the Nuclear Regulatory Commission,

ATIN:

Document Control Oesk, Washington, DC 20555, with a copy to the

Regional Administrator, Region II,

and a copy to the NRC Resident Inspector,

i

within 30 days of the date of the letter transmitting this. Notice.

Th1s reply

'

should be clearly marked as a "Reply to a Notice of Violation" and should

include (for each violation):

(1) admission or denial of the violation

(2) the reason for the violation if admitted, (3) the corrective steps which

have been taken and the results achieved, (4) the corrective steps which will

be taken to avoid further violations, and (5) the date when full compliance

will be achieved.

Where good cause is shown, consideration will be given to

extending the response time. If an adequate reply is not received within the

l

,.

.

.

. _ .

_

._ . __ _

,

,

' . .

'

-

.. .;

.

,

'

Georgia Power Company

4

Oceket No. 50-425

-

Vogtle Unit 2

License No. CPPR-109

-

,

.

l

time specified in this Notice, an order may be issued to show cause why the

!

license should not be modified, suspended, or revoked or why such other action

as may be proper should not be taken.

FOR THE NUCLEAR REGULATORY COMMISSION

'

pt#

ey

/

-

V rgi UL.'8rownlee, Chief

ReactorProjectsBranch3

DivisionofReactorProjects

Dated at Atlanta, Geor i

thislgdayofgu.y

1988

j

,

'

t

!

.

!

]

'

i

I

j

i

i

1

j

-

i

I

i

1

l

1

!

1

i

i

'

1

t

i

, - - _ .

. _ _ . -

_,

,

_ _ .

. _ ___._ _..___-.

_ _ . , _ _ . _ _

,,m.7

,__, ..

.,y.,_____

, _,

___.m,,._m._____,-,-,,_,_

. _. _ _,,- -

_

_

__________________-___ -

_

, . .

, . , ' .

'.

,

,,

, * pS Eteg%,*

UNITE 3 STATES

'/

NUCLEAR REGULATORY COMMIS$lON

'

-

'

.'

REoloN la

I

j

,

101 MARIETTA STREET.N.W.

-

.

ATLANTA, otoRol A 30323

's,.....

.

Report No.:

50-425/88-19

Licensee: Georgia Power Company

.-

P. O. Box 4345

I

Atlanta, GA 30302

Docket No.:

50-425

License No.: CPPR-109

Facility Name: Vogtle 2

Inspection Conducted: May 11-12, June 6-10, and July 11-14, 1988

Inspector: b \\.dTh

8lh f Yi

5. J. ,V)as, Project Engineer

Date $1gned

Accompanying Personnel:

P. A. Balmain, Reactor Engineer, (June 6-10,1988)

S. Q. Ninh, Reactor Engin.eer, (July 11-14, 19

Approved by:

.k.

_[_ M .IT

M. V. Sinkule, Section Chief

Dat'e $1gned

l

Reactor Branch 38

l

Division of Reactor Projects

SUMMARY

Scope:

This special, announced inspection, on site, involved the areas of

safety-related supports (Unit 2), and Readiness Review Module 11

Pipe Stress and Supports (Unit 2).

Results: One violation was identified: Violation, 50-425/88-19-01, Failure to

Follow Procedures, Resulting in Errors in Pipe Support QC and Design

Documentation. See Paragraph 2.C.6),a.

Inspector Followup Item, 50-425/88-19-02, Potential Problems with

Sprir.g Can Travel.

See Paragraph 2.C.6).a.(7).

S ( 13 ? n l () d 4/

,;$ YJ (I );

L

-

-

.

va

,,

-

_ _ _ _

_____________ ______ _ _ _ _ - -

, . '

.

.

.

-

, . , -

.

..

,

..

s

/

.

REPORT DETAILS

1.

Persons Contacted

Licensee Employees

  • R. H. Pinson, Vice President - Construction
  • A. B. Gallant, Project Compliance Coordinator

"J. J. Gilmartin, Mechanical Field Operations Staff

  • E. D. Groever, Quality Assurance (QA) Site Manager - Construction

'C. W. Hayes, Quality Assurance Manager

R. W. McManus, Readiness Review (RR), Project Manager

  • W. C. Ramsey, Project Engineering Manager-
  • C, W. Rau, Mechanical Discipline Manager

-

  • C. Garrett, Operations Engineering, Oglethorpe Power Corporation

Other Organizations

R. Borgatti, Depdty Engineering Group Supervisor, Bechtel

Western Power Corporation (BWPC)

-

5. K. Gupta Deputy Engineering Group Supervisor, BWPC

P. Patel, Engineering GrNp Leader, BWPC

  • 0. W. Strohman, Project QA Engineer, BWPC
  • R. C. Summerfeld, RR Team Leader BWPC
  • P. R. Thomas, RR Team Leader, BWPC
  • M. J. Beer, Technical Assistant, V-SAMU

W. E. Faires, Principal Engineer, V-SAMU

  • M. E. Maryak, Completion Manager, V-SAMU

N. R. Pasala, Mechanical Engineering Group leader, V-SAMU

B. G. Schappell, Manager Mechanical Construction Support, V-SAMU

'O. P. Shaw, Westinghouse PQAE

  • B, Edwards, Resident Construction Manager, Pullman Power

Products (PPP)

'J. Miller. Quality Assurance Manager, PPP

R. Norton, Orafting Lead, PPP

j

T. Pacifico Engineering Manager, PPP

j

H. Smith, Quality Control (CC) Manager, PPP

K. Weis, Chief Engineer, PPP

J. Morris QC Inspector, PPP

A. Turner, QC Inspector, PPP

Other licensee employees contacted included construction craftsmen,

engineers, technicians, mechanics, and office personnel.

,

..

.-

.

' . .

-

-

.

. . '

..

/

.

.

NRC Resident Inspectors

  • R. J. Schepens, Senior Resident Inspector - Construction

' Attended exit interview

Acronyms and initialisms used throughout this report are listed in

Paragraph 4.

2.

Review of Readiness Review Module ll, Pipe Stress and Supports (Unit 2)

(50090)

A.

Scope of Review

This review consisted of an examinition of GPC's Readiness Revi'tw

Module ll, Pipe Stress and Supports.

Sections 1, 2, 3, 4, and 6,

which presented data on introduction and module organizatiosi,

organization and division of responsibilities, commi'ments, pro (ram

description, and, audits and inspections.

These did not require as

.

,

extensive a review as Section 6, which covered program assessment.

l

The evaluation of Section 6 included an examination of content.

l

review of findings and conclusions, review of a small sample of items

previously reviewed in the Readiness Review Program, and review of an

independently selected sample of documents,

both design and

construction, and a field construction inspection.

The methodology

used and an evaluation of each section are presented in the following

section.

B.

Methodology

The NRC review performed was concerned with all sections of the

report, but focused on Section 6.

The entire Module was read and

reviewed for organization and content af ter its receipt on April 13,

,

l

1988.

The Region !! inspectors conducted one on-site preliminary set-up

meeting.

This was followed up with two on-site inspections at the

Vogtle Electric Generating Plant (VEGP) Unit 2.

The first visit to the Vogtle site, made on May 11-12, 1988, was to

discuss with licensee and Readiness Review personnel, the scope and

inspection plan for the evaluation of this module. The inspector was

able to identify the systems, P&lD's, isometrics, and pipe supports,

that were to be inspected and reviewed during the acoming inspection

periods.

The

first

inspection also involved the following

activities:

Reviewing the description of the Readiness Review program and

'

o

establishing organizational responsibilities for Module 11,

o

Verifying Module 11 review boundaries,

'

,{

.,

,.

,,

,..

.

..

,

,

..

..

3

-

<

i

.

o

Inspecting ancJ reviewing an independent sample of P& ids and

piping isometrics to be used in the assessment of Section 6 of

the Module 11 report,

A sample of five P&IO's covered by thirteen piping isometrics, having

56 associated pipe supports was selected to form a basis for the

detailed assessment of the Construction Program.

The isometrics

chosen represent a diversity of pipe systems, sizes, locations, and

pipe class.

The second inspection, was made during June 6-10, 1988, involved the

following activities:

o

A detailed walkdown of the piping systems, and pipe supports

previously identified.

o

A detailed review of the construction documentation for the

items inspected in the field,

o

An assessment of the one Level !! finding reported in Section 6,

of the Module 11 report and a brief review of the 7 level III

findings.

An evaluation of the Construction Program was made by performing a

field inspection of all piping installation and pipe supports

included in the selected sample of five P&lDs, thirteen piping

isometrics and 56 pipe supports.

In addition to this field inspec-

tion, all of the Pullman Power Products (PPP) Quality Control (QC)

documents associated with the thirteen piping isometrics and 56 pipe

supports were reviewed for conformance to

specifications and

procedures, and for compliance with design drawings.

Finally,

an

assessment was

made

on

the

Level !!

finding

(2RRF-011-002), resulting from Readiness Review's Program Assessment

Section. This finding involved PPP project procedures not clearly

defining authority, responsibilities, and limits of field engineers

performing verification of construction activities versus the

authority,

responsibilities,

and

freedom of

quality

control

inspectors

to

perform

inspections

and witness

construction

activities.

The second on-site inspection was conducted during July 11-14, 1988,

included the following activities:

o

Performing a Construction Program review of findings f rom the

first inspection with the appropriate PPP personnel,

o

Accomplishing general Module 11 review activities,

o

Performing a Design Program review, for the piping and supports

inspected duritig thi first inspection on-site.

- - - - - - - - - - -

,

-

. . . -

.

.

,

,

, o, -

-

..

,

.

..

r'

4

.

General review activities included an assessment of the information

presented in Sections 1, 2, 4, and 5 of Module 11.

An evaluation of the Design Program was made by reviewing a sample of

the stress calculations for the thirteen selected piping isometrics

and their 56 associated pipe supports.

These calculations and

related design criteria, drawings, and change documentation were

reviewed for' adequacy of design control, adherence to criteria and

procedures, and design integrity.

C.

Evaluation

The evaluation of each Module section is provided below in the

section-by-section format used in the Module 11 report.

Included are

a description of the section, subject matter reviewed, basis for

acceptance, and statement of required follow-up or evaluation.

1)

Section 1 - Introduction

This section presents the scope of Module ll, outlines the

Module organization, and reports the' project status.

The

section was examined by the NRC inspectors for apropriatenoss

of scope and for background information,

a.

Boundary Definition.

Module 11 ircluded those activities

(stress analyses and pipe support design) for ASME, B&pV

Code, Section !!!, Classes 2 and 3 piping within the scope

of Bechtel West,ern power Corporation (BWPC) and Vogtle

Structural Analysis Mobile Unit (V-SAMU). The installation

of piping, Section !!!, Classes 2 and 3, and mechanical

equipment were not covered in this module. The design and

construction of piping systems in the Nuclear Steam Supply

System (NS$5), were not included this module.

Also

contained in Module 11 were stress analyses of non-safety

related piping that must meet Seismic Category 1 require-

ments for protecticn of safety-related components.

The NRC inspectors found the description of Module 11

bounW. ries to be acceptable,

b.

Project Status.

Subsection 1.3 of Module 11 presents the

project status for design and construction of small-bore

and large-bore pipe supports.

Parcentages of completion

were quoted as of September 1987.

These percentagos were

shown as 71% completion for design of small-bore and 86%

completion for design of large-bore pipe supports, and with

7% completion of the analytical stress reconcil ation

packages. On the construction side, it was shown as 56%

completion for installation of small-bore supports, and 86%

completion for installation of large-bore supports.

The NRC inspectors determined that the project status indicated

significant progress in the pipe support program.

-

__ . _ _

_

__

_

_

,

-

-

, . . . ,

.

,.'

)

-

..

,

-

]

..

..

5

g

i

i

t

l

1

2)

Section 2 - Organization and Division of Responsibility

This section describes the organizations invulved in design and

construction for Module 11.

It explains what personnel are

responsible for specific design and construction activities, and

presents Ce matrix organization used by the architect /

engineering contractor on the project.

This section was

reviewed by NRC inspectors for content and accucacy.

In the

,

process of this review, the responsibilities of the various

l

organizations and personnel within the organizations were

'

,

j

clarified. The NRC inspectors had no findings in this section.

]

3)

Section 3 - Commitments

P

This section contains listings of commitments and implementing

(

documents, which are displayed in two matrices.

The first

matrix, entitled "Commitment Matrix," identifies all of the

i

Module 11 commitments, their source doc oents subject and

l

J

{

feature.

The second matris, ' entitled "Implementation Matrix,"

!

lists the document or plant feature for each coms,1tment, as

l

discussed in the source document, and the project document in

[

]

which the commitment is implemented,

'

.

3

g

. . .

.

.

j

Ouring the review of Unit 1 Readiness Review of Module 11, it

{

was noted that two commitments contained in the FSAR were

!

3

omitted from the RR review of commitments.

This matter was

(

followed in Inspector Followup Item 50-424/86-62-01. This

(

inspector reviewed this matter during a later inspection and was

l

documented in NRC Inspection Report 50-424/86-116. This matter

was considered closed.

The inspection conducted at this time

!

was not directed toward verifying this Readiness Review section.

(

r

4)

Section 4 - Program Description

This section describes procedures, documentation, control for

!

design and as-built and reconciliation activities; equipment and

i

material; site material control; and fabrication, installation

and inspection. The section was examined by the NRC inspectors

i

i

for content and background information. Some of the background

[

was useful in the review of later sectinns in the Module,

t

especially Section 6. Program Assessment.

'

a.

Design.

Subsection 4.1 divides the description of the

design program into several categories including the pipe

!

stress and pipe suppert design process; design criteria;

design documsntation; design control and review; and design

change control.

This subsection describes the design

i

pecgram from its earliest phase of design criteria

development

to

its

final

phase of design program

!

verification.

The NRC review of this subsection revealed

l

that the information presented therein gave a descriptive

l

!

l

_

l

,;

.

.

' , ' , - ',

.

..

-

..

..

,

6

,

'

i

accounting of the design process and defined the division

of responsibility between Bechtel Western Power Corporation

and Westinghouse in pipe stress analysis activities.

It

also explained the interfaces between engineering groups

involved in the design effort.

The informaticn proved

useful for developing an understanding of the design

program, but did not lend itself to a detailed review. The

NRC inspectors identified no findings in the design program

described in this subsection.

Results from the review of

Section 6 of Module 11 were tsed to determine how

effectively the program actually functioned.

3.

Equipment and Material.

Subsection 4.2

describes

the

process for procuring safety-relating piping supports and

,

components or the materiat used to fabricate these items.

GPC serves as the pure.hasing agent, in compliance with

specifications written and controlled by BWPC, for these

items and supplies them to the contractors for instal-

lation. .No findings were identified in the procurement

.

process.

-

c.

Site Material Control.

Subsection 4.3

describes

the

responsibilities of the pipe support installers relative to

receipt, inspection, and control of ASME Boiler and

Pressure Vessel

Code mater;al

within the scope of

Module 11. This subsection details the change from Unit 1,

in that GPC has subcontracted receipt inspection of ASME

B&PV,Section III, components and materials to Pullman

Power Products (PPM

GPC is the supplier of ASME B&PV

Code items and materials to the NA-installers, PPP, GPC's

Nuclear Construction

Team,

and Nuclear

Installation

Services Company (NISCO).

Materials and equipment are

inspected when received at the job site by GPC.

After

i

satisfactory completion of this inspection, the material is

placed in storage locations maintained by GPC. The NRC did

no'. perform a detailed examination of this subsection since

the material contained a brief description and not an

assessment.

Tha NRC inspectors had no findings in th's

subsection.

d.

Fabrication, Installation, and Inspection.

Subsection 4.4

describes site fabrication, installation and inspection

l

activities for pipe supports and pipe whip restraints.

It

also references specification documents that control the

inspection of these items, such as codes, specifications,

and implementation procedures.

As indicated in this

subsection,

t-

fabrication and installation of pipe

supports was performed in accordance with Bechtel Western

Power Corporation's Specification XoAZO1, Division P1,

General Requirements, and Division PS, Pipe Support Field

Fabricat an and Installation.

It also describes the

j

, ,:

-

.

.

,;.

'; . -

.

.

..'e

. . '

7

r

,

(

.

preparation and control of the principal documents used

by PPP for site fabrication, installation and inspection

of pipe supports.

The material in this subsection is

generally descriptive and was not assessed in detail

by the NRC inspectors.

The material presented does

indicate that the basic installation program addresses

project

requirements.

. Re su t s

from the review of

.

Module 11, Section 6 were used to determine how effectively

the program actually functioned.

The NRC inspectors had.

no findings relative to the description of this program.

5)

Section 5 - Audits and Inspections

This section discusses quality assurance audits and evaluations

that have been performed by GPC, and Bechtel Western Power

Corporation, addressing pipe stress analysis and pipa supports;

and follow up of the Unit 1 findings.

It also describes

inspections and special evaluations conducted by the NRC.

This

3ection discusses findings resulting from these audits relative

to the design and construction programs.

The section also

presents three design and construction problems identified since

the completion of Unit 1, Module 11, Assessment.

The three

concerns were considered significant enough by GPC that the NRC

was informed of their potential raportability pursuant to

~

criteria of 10 CFR 50.55 (e).

The findings resulting from design program audits occurred in

the design functional areas, such as calculations, drawings,

field change requests, design documentation, and design changes.

In addition, the NRC inspectors determined that items related to

Module 11 and past NRC findings were included in the Readiness

Review Team data base for Audits and Inspections.

The NRC inspectors concluded that findings from previous audits

and inspections were considered in the Readiness Review Team's

assessments for Module 11.

The NRC inspectors had no findings

in this section.

6)

Section 6 - program Assessment

This section of the Module 11 Report describes activities

undertaken to ascertain whether construction and design

activities were adequately controlled to ensure implementation

of licensing commitments and conformance with project procedures

1

and design requirements related to pipe stress analysis and pipe

'

supports.

The section was reviewed in two phases covering

Construction Program Verification and Design Program Verifica-

tion.

The inspectors performed detailed evaluations in both

areas which are described below.

i

., __

. - _ _

_ _ . _ _ _

___ __,._ _.__

. , _ .

_ _ _ . _ _ _

_ , _ , _

_ . _ _ _ _ _

,

,.

.. .

'

>.

,1 . -

.

., .. .- .:

/ *

g

.

a.

Construction Program Verification

The Construction Program Verification performed by the

Readiness Review Team consisted of an assessment of

installed safety-related supports that had been As-built,

and associated steel. Also, the implementation of design

and construction programs with emphasis on significant

changes

in

programs,

procedures

and

org:inization

responsibilities.

The program had the objective of

determining .whether the construction control

process

functioned effectively and whether it ensured acceptable

pipe support installations.

The assessments made and conclusions reached in Readiness

Review's verification program were divided into the

following major categories:

o

Im'plementation of licensing commitments,

,

o

Followup of corrective actions which resulted from the

Unit 1 Readiness Review Program,

o

Project performance in accordance with the quality

program, procedures, and design requirements.

During the preparation by the Readiness Review Team for

con,truction walkdowns, the programs and procedures for the

installers of pipe supports for safety-related systems were

reviewed.

All programs and procedures were found to be

acceptable.

The inspectors reviewed portions of various procedures

during the evaluation of the thirteen 'sometrics and

56 pipe supports described below.

The inspectors found

that poetions of the construction procedures adequately

-

,

reflect project requirements with one exception.

The

'

inspectors determined that the PPP

Procedure

X-24,

Section 4.1 "As-Builting Piping

Systems

and

Related

,

Components", was not being properly adhered to with respect

{

to the incorporation of information ' redlined' on pipe

support drawings, by field engineers and QC personnel, onto

the mylars for the pipe supports by the draf ting group.

This is discussed in further detail in Section (1) below.

,

As discussed earlier in this report, the inspectors

selected thirteen piping isometrics with 56 associated pipe

supports to form a basis for evaluating the Construction

and Design Program Verifications.

The piping isometrics

and pipe supports examined are listed in Table 1.

The

inspectors examined the construction aspects of all 56 pipe

supports by first performing a field inspection on the pipe

isometrics and pipe supports. During this inspection, the

following information was recorded:

'

_ _ _

__

._

_ - - - - - - _

.-

  • .

.,

.. =

,, .

.

,

,

.

..

..

9

g .,

.

.

o

Pipe dimensions, component locations and orientation,

o

Support dimensions and support locations,

o

Support configuration,

o

Weld size and type,

o

Support materials,

o

NF component heat numbers,

o

Clearances between pipe and support,

o

Snubber NPT Code Data Plate information, cold set,

traceability markings on connecting hardware,

o

Spring support NPT Code Data Plate information, travel

stop installation, traceability markings on connecting

hardware.

.

The information recorded during the field inspections was

then reviewed against the Linc Designation List (LOL),

Valve List, Piping and Instrumentation Diagrams (P& ids),

pipe isometrics an' support drawings, all associated

documents in the P / QC document packages, and other

miscellaneous documents. The documents included in the PPP

QC packages were Process Sheets, MFCRBs, Authorizations to

Continue Work ( ATCWs), ors, DCN-Rs, Snubber and Strut

Checklists, Weld Process Sheets, and Weld Rod Requisition

Tickets,

knong other miscellaneous construction documents

reviewed were Requests

for Support Removal,

Liquid

Penetrant Examination Records, Material Inspection Reports,

Maintenance Work Orders, Certificates of Compliance, and

Certified Mill Test Reports.

Based on the inspection of pipe supports and associated

documentation, the inspectors found that the pipe support

installations were generally consistent with the documen-

tation and in accordance with project requiroments.

The inspectors did, however, identify several deficiencies

in the construction program, which are described as

follows:

l

(1) During the review of the as-built information gathered

)

in the field, and comparing the information to the PPP

j

Process Packages for the individual pipe supports, it

i

was noted on five occasions that all the information

i

that was

"redlined"

per

PPP

Procedure

X-24,

l

"As-Builting Piping Systems and Related Components',

i

i

l

. ' .

-

.

.,

.

.*

, , -

.

.

,

,

v

..

..

r

10

.

Section 4.1, was not properly incorporated onto the

Mylars. The following discrepancies were found to be

properly ' redlined' and documented on a copy of the

pipe support drawing in the PPP Process Package, but

were outside the tolerance of PPP Procedure X ".4,

and

not incorporated into the Mylars,

o

V2-1204-014-H004, the correct size of item

'b',

o

V2-1204-014-H006,

the

dimension

from

the

centerline W4 to the centerline of the embeded

plate.

o

V2-1208-005-H007, the dimension for item #4 was

shown on the dr& wing as 3 5/8", the inspectors

-

measured in the field and the ' redline' drawing,

both indicated that the dimension was 5 1/2".

,

,

o

V2-1208-145-H017, the pin-to pin dimension of the

spring can, drawing shows 12'-10 5/16", and the

' redline'

and the dimension the inspectors

'

measured was 12'-11".

o

V2-1208-145-H016, the Bill of Materials shows

item #5 as 8" wide, the inspectors measured the

dimension as 8 3/4", this is the same dimension

as the ' redline' drawing.

This matter of discrepancies between

' redline'

information and final pipe support drawings has been

previously identified by internal audits performed by

the licensee.

An audit, documented in an internal

Westinghouse memo, from V-SAMU As-Built Completion

Group to R. W. Braddy and M.W. Barlow, dated March 15,

i

1988, identified similar discrepancies during a two

stage audit. The conclusion was that all the supports

were found to be acceptable, but that three had a

slight reduction in margin of safety.

In a PPP memo,

f rom B.L. Edwards to C.W.

Rau, dated February 10,

1988, PPP listed actions to be taken to minimize

future occurrences.

(2) The following drawings, both pipe support and P& ids

were found to have discrepancies between the actual

condition in the field and the drawing; or pertinent

j

"

information was missing from support drawing,

o

P&ID 2X408122, shows a line, designated as Line

006-8", (coordinate C-5), and just to the lef t of

l

T' 0613, should be Line 008-8".

.

J

o

V2-1208-055-H052, shows the angle iron, item 5,

"

in the wrong orientation.

_

-

_

_

-_

_

__

_

.

__ .-

_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _

. . .

.

.

..

'!

y.,

.

,

-

..

7

, . -

11

.

o

V2-1208-055-H014,

in the Location Plan, the

vertical pipe is shown as going in the (-)Y

direction, in the field it is going in the (+)Y

direction.

o

V2-1208-215-H003,

-H004,

-H005,

all

three

drawings did not have a locating dimension for

the attached support (baby) in relation to a

connection point on the parent support.

This is

contrary to PPP Procedure X-24, "As-Builting

Piping Systems and Related Components", Section

6.6.

(3) The following pipe supports were found to have

dirensions on the dfawings that differed from the

dimensions measured in the field by the inspectors.

The dimensions are outside the tolerance of PPP

Procedure IX-50, "Pipe Support Field Installation and

Fabrication Procedure", Section 6.2.6.G.

o

V2-1208-255-H002, the drawing shows the dimension

from the centerline of item #2 to the centerline

of the pipe as l'-4 1/4" ACT. , the inspectors

measured l'-2 1/4".

o

V2-1204-063-H004, the location of the attachment

for V2-1204-201-H002, item #a, to the embed

plate, shows the dimension from the right side of

the embed plate to the attachment as 2 3/8", the

insoectors measured 3 1/16".

(4) The following drawings had discrepancies between the

information obtained in the field and the information

on the drawings.

During the review of PPP Process

packages for the three drawings, it was found that the

correct

information was noted somewhere in the

package, but was noi. incorporated onto the drawings.

(Note: the correct notation of the information was not

on the ' redline' drawings.)

o

Isometric 2K3-1208-146-01, Detail 2 & 3, indicate

a class' change from 212/FGO, on Line 1208-145-4"

to 414/FG4, on Line 1208-A20-1/2".

The Line

!

Designatien List (LOL) shows 1208-A20-1/2" as

424/FG4.

OCN-R #7, dated 2-3-86, changed the

line to 414/FG4.

o

V2-1208-145-H017,

the

location of the beam

attachment on the drawing shows the 'as-built'

dimension as

l'-3 1/2", documentation in the

Process package and the Final Inspection Report,

J

both show the dimension to be l'-2 3/4".

1

..

- - . . ,

.-,

. _ .

.'

,

.,

. ' . . . 1,

.,

.

.,

, . .

..

g-

12

.

o

Isometric 2K3-1205-006-01, from DCN #8, the class

information was not transferred correctly to the

isometric.

Also, not all the information from

FEDCNR-2262, was transferred to the 'as-built'

isometric.

(5) The following PPP Process Packages, had documentation

in the package that did not correctly reflect what was

in the field or was confusing.

o

V2-1205-004-H016, in the process package, the

' Strut Reconciliation Report" (SRR), of 5-26-87,

indicates two struts were installed, SRR of

10-14-86, Aws one strut and SD.R of 5-18-88,

indicates that two struts were installed.

The

pipe support drawing, (R/3), shows one strut.

There is also a discrepancy of the offset angles,

in SRR of 10-14-86, it indicates 3 degree , SRR

of 5-26-87, indicates 2 degrees,

o

V2-1205 006-H014, the Process Package has two

different issue tickets for the spring can that

was installed, both for the same serial number of

8G15066, they also indicate two different spring

can sizes.

J

(6) The NRC inspectors while performing the inspection in

the field noted a discrepancy with respect to pipe

1

support V2-1204-063-H007.

The support was designed

and the drawing located the support on a 4" riser, at

elevation 208'-8", and 3'-2" West of Column A3.

The

pipe support was actually installed at the correct

elevation, but on a differsnt riser, approximately

l'-11", West of Column A3.

The pipe support, at

various times was inspected no less than three times.

,

PPP has issued OR PP-18138, for disposition of this

problem.

The discrepancies, in the above six items between support

installation, design information, construction documen-

tation and QC documentation is a violation of 10 CFR 50,

Appendix B, Criterion V, and is identified as Violation

425/88-19-01 - Failure to Follnw Procedures, Resulting in

Errors in Pipe Support QC and Design Documentation.

(7) During the inspection of V2-1204-063-H005, and during

subsequent discussions with both PPP and BWPC

personnel, it was determined that the spring can

installed for this support was very close to becoming

topped out.

Therefore, it was agreed upon, that the

spring can would be monitored during hot functional

1

,

-

.-

.

.

.

? ...',

.,

.

,

.. ..

..

13

(

.

testing, and during the process of setting the spring

to its proper ' hot setting '

This item will then be

followed as Inspector Followup Item 50-425/88-19-02,

"Potential Problems with Spring Can Travel."

b.

Design Program Verification

The Design Program Verification performed by the Readiness

Review Team focused on evaluation of the pipe stress

analysis activities and design of pipe supports.

Their

assessment in part was intended to evaluate the compliance

of design change activities with engineering procedure

controls.

The RR review emphasized the evaluation of

conformance of as-built data and conformance of instal-

lation and data collection activities with quality program

requirements.

The RR group intended for the assessment samples to be

selected from the same systems evaluated for Module 4,

however,

since

the

sequencing

of

analytical

and

reconciliation work was controlled by the turnover

schedule, the assessment sample was altered and limited.

The NRC inspectors found that the RR sample coverec: all the

areas needed to evaluate the module topic, however, it was

difficult to do a complete vertical slice through their

assessment, in order to draw conclusions on the overall

program.

Therefore, the NRC inspector:, were not able to

efficiently use the RR review groups sample in their

review, and chose a completely indepe.' dent sample for

review.

Documents included in the Readiness Review Team's review

and results of the review were divided into the following

major categories:

I

o

Pipe Stress Analysis Packages,

o

Pipe Support Calculations,

o

Pipe Support Drawings,

o

Design Change and Nonconformance Documents,

The NRC inspectors examined all of the foregoing topics in

their review. The approach used by the inspectors in their

examination was directed toward evaluating the same

equipment, piping, and supports, from the beginning of

design to the completion of construction.

This was

'

accomplished by first selecting a set of thirteen piping

isometrics to form a basis for an assessment of both the

i

Design and Construction Program Verifications.

The piping

isomet rics were chosen to obtain a diversity of pipe sizes,

-

.

.

.

,

,. *: , . . . . ,

.

.. .. ..

.

14

,

.

pipe classes, locations, and systems. None of the thirteen

piping isometrics selected were included in Readiness

Review's program.

The thirteen isometrics chosen had a

total of 56 associated pipe supports.

Included in this

support sample were miscellaneous steel supports, pipe

straps, snubbers, struts, and spring supports. Of these 56

supports, only two pipe support drawings were within

Readiness Review's prcgram. The piping isometrics and pipe

supports selected for eeluation are listeo Table 1.

All

of the isometrics and pipe supports were evaluated in NRC

Regicn II's review of the Construction Program Verifica-

tion, and a portion of the design documents associated with

these isometrics were examined in the review of the Design

Program Verification. The design documents examined by NRC

inspectors are indicated in Table 1.

The NRC assessment of

design documentation is reported as follows:

,

(1) Pipe Stress Analysis Packages

-

. ..

The following calculation packages w6re examined for

completeness,

inter-discipline

'coordinatiorf,

-

conformance to design criteria and project require-

ments, consistency with drawings and installation, and

technical adequacy:

_

o

BJ-01-706, R/2

o

BG-01-717, R/1

o

BC-00-718, R/1

o

BC-00-725, R/0

Observations made relative to the stress analysis

review include:

o

The piping configuration, location of components

in the line and locations of supports. used in

the analysis was consistent with the isometric,

the installation and project tolerances, except

thst pipe support V2-1204-063-H007, was installed

on

the

wrong

pipe.

See

discussion

in

Section 2.C.6).a.(6), of this report,

o

Stress limits used were in accordance with ASME

Section III Class 2 criteria for the Class 2

piping,

o

Damping values used were in accordance with

Regulatory Guide 1.61.

j

o

Load combinations used were in accordance with

Design Criteria DC-1017 and NUREG-0484.

_ - _ - -

___

_.

._-

. _ _ - .

. _ _ -

_-

.'

<

.

.

., *:

4...

.

.

,

.. .. ..

.

15

. . .

.

.

o

Stresses for the faul.ted conditinn were within

allowances specified in ASME Code Case 1606-1.

o

The valve weights and orientations used in the

analysis were consistent with the drawings and

instellation,

The design temperature and pressure, operating

o

temperature and pressure, and pipe material were

consistent with parameters given in the Line

Designation List.

o

The seismic response spectra used in the analysis

corresponded

to

the

proper

building

and

elevation.

-

o

The calculations for thermal' anchor movements

.e

-

were correct and the movements were incorporated

'

e ~- r

in the a n a lys i ngJ,hpNf04-014-0C * 'c a l c' fa t to

in~spectors found for

.

Isometric

drawin'g+ 2M3

'

u

'

BJ-01-706, a portion of Page 7 was-'Ef6Tnf in the

-

calculation,

indicating

the

thermal

anchor

movements used in the calculation.

o

The

calculated

stresses were

within ASME

Section III Class i. allowances and deflections at

support locations were less than the allowable

for both small and large bore piping.

(2)

pipe Support Calculat_ ions

The pipe support calculation packagas listed in

Table 1,

were examined for completeness,

inter-

discipline

coordination,

conformance

to design

criteria and project requirements, consi s*.ency with

drawings and installation, and technical adequacy.

All of these pipe supports are contained in the piping

isometrics reviewed in the Construction Verification

Review, discussed in Section 2.C.6).a.

Observations made relative to these pipe support

calculations include:

o

Design loads and displacements were correctly

transferred from the pipe stress calculations to

the pipe support calculations.

I

o

A friction load was included whenever the thermal

movement at a support en:eeded 1/16 inch,

o

The structural members used in the analyses

corresponded in size and material with the

drawings and installation.

-

_

- - - _

. - - - - . -

- _

_-

__.

. - - .

.-_ _ _ _ _ - - -

_ _ _ _

- - _ _ _ _ .

,

,

.

,

,

,

l : .

4. ..

.

.

. . . . ..

.

,

16

.

o

That design assumptions were properly noted in

the calculation package.

The

inspector found

that for pipe support V2-1204-014-H006, that the

calculation for the embeded plate, that it should

have been noted that the assumptions the engineer

used, when the reduced faulted loads, used in the

calculation, were indeed compared to the upset

loads.

'

o

The calculated stresses in miscellaneous steel

were within allowances of the American Institute

of Steel Construction, and stresses in ASME

Section III Subsection NF components were within

NF allowances.

.

(3) pipe Support Orawings

The examination of pipe support drawings was performed

in conjunction with tk.e review of pipe support

calculations and the evaluation of the Construction

,

program Verification.

Therefore, all of the pipe

supports listed in Table 1 were included in the pipe

,

support drawing review.

The drawings were reviewed

for completeness, appropriate approvals, drafting

clarity, and consistency with project requirements.

The only deficiency identified in the drawing review

were those noted in the Construction Verification

Review Section 2.C.6),a of this report.

(4) Design Change and Nonconformance Documents

Based on the information presented in this report,

Mechanical Field Change Requests (MFCRs), 00N-Rs, and

Deviation Reports (DRs), were included in the many of

the 56 pipe support packages for the thirteen piping

isometrics evaluated by the NRC Region II inspectors.

These design change documents were examined by the NRC

Region II inspectors for the following attributes:

o

Proper disposition and approval,

o

Appropriate technical justification,

o

Correct incorporation into drawings.

The NRC inspectors identified no findings during the

examination of the sample design change documentation.

i

,

_ _ _ _

.

_ _ _ - _ _ -

-

- - - - - - - - - -

- - - -

'

l

.<

,

e, ' . :, 4. l. ,

.

.. .. ..

.

.

'

17

.

c.

Findings

Subsection 6.5 of the Module 11 Report presents 8 findings disclosed

by the Readiness Review Team in the Design Program Verification.

Among these findings there were no Level I,

one Level II, and

seven Level III findings.

The NRC Region II inspectors performed an

evaluation on the one Level II finding (2RRF-001-002),

o

Finding 2RRF-001-002, level II, was in reference to two PPP

procedures IX-50, and IX-65.

The concern was the lack of

clarity with respect to the appropriate responsibilities and

authority of PPP field engineers, QC inspectors, and QA

engineers.

The procedures have been revised and appropriate

training has been conducted.

.

The NRC incpectors identified no findings during the examination of

the Readiness Review Findings in the Construction and Design Program

Verification.

.

3.

Exit Interview

The inspection scope and findings were summarized on July 14, 1988,

with those persons indicated in Paragraph 1.

The inspector described

the areas inspected and discussed in detail the inspection findings.

No dissenting comments were received from the licensee.

Violation 425/88-19-01, Failure to Follow Procedures, Resulting in

Errors in Pipe Support QC and Design Documentation. See Paragraph

2.C.6).a.

Inspector Followup Item, 50-425/88-19-02, Potential Problems with

Spring Can Travel.

See Paragraph 2.C 6).a.(7).

The licensee did identify as proprietary materials various documents

for review by the inspector during this insnection, but no

i

proprietary information is contained in this report.

4.

Acronyms and Initialisms

AISC

Anerican Institute of Steel Construction

ANSI

American National Standards Institute

ASCE

American Society of Civil Engineers

ASME

American Society of Mechanical Engineers

ATCW

Authorization to Continue Work

AWS

American Welding Society

BWPC

Bechtel Western Power Company

CD

Civil Deviation Report

CMTR

Certified Materials Test Report

,

.

COC

Certificate of Compliance

DBE

Design Basis Earthquake

DC

Design Criteria (Bechtel)

DCN-R

Orawing Change Notice-Resident

P..

.,

.

  • * , . ,

-

,

y . . .. . .

18

ll

DR

Deviation Report

FSAR

Final Safety Analysis Report

GDC

General Design Criteria

GPC

Georgia Power Company

IDR

Independent Design Review

IE

Office of Inspection and Enforcement

IEB

Inspection and Enforcement Bulletin

INP0

Institute of Nuclear Power Operations

LDL

Line Designation List

NFCR

Mechanical Field Change Request

MWO

Maintenance Work Order

NDE

Non-Destructive Examination

NRC

Nuclear Regulatory Commission

NRR

Office of Nuclear Reactor Regulation

NSSS

Nuclear Steam Supply System-

OBE

Operational Basis Earthquake

P&ID

Piping and Instrumentation Diagram

PPP

Pullman Power Products

.

PQR

Procedure Qualification Record

PWR

Pipe Whip Restraint

QA

Quality Assurance

QC

Quality Control

RRF

Readiness Review Finding

RRT

Readiness Review Team

SER

Safety Evaluation Report

SRP

Safety Review Plan

SSER

Supplement Safety Evaluation Report

VEGP

Vogtle Electric Generating Plant

V-SAMU

Vogtle Structural Analysis Mobile Unit

WAC

Visual Weld Acceptance Criteria

WPS

Welding Procedure Specification

l

l

l

l

l

1

1

L

..

'

. *

-

. .

?

TABII

I .* .

..

. .

-

--

_._

,

PIPING

STRESS

-

SUPPORTS

PPP

P&lD

ISorETRICS

STRESS

ANALYSIS

LINE NUMBER

CALCtlIATION

SUPPORTS

SUPPORT QC

,

DRAWillG MfSER

Ills *ECTED BY

ANALYSIS

REVIEW D BY AND SAFETY /

PIPE

REVIEW D

INSPECTED BY DOCIAENTATION

.

'

SYSTEM and SUIll)ING

PIPING IS2ETRICS

NBC g

Pit 03Ist NIRIBER NRC RRT PIPING CIASS

SUPPORTS

NRC RE

NRC RRY REVIEW D BY NRC

_

214D8828. R/22

2E3-1204-073-01, R/4

YES 11 0

BJ-01-706 R/2 YES NO 2-1204-014-4" V2-1204-014-N007 R/2 YES NO

YES NO

YES

Safity Injecties

Q212/GGO

V2-1204-014-N00s R/3 YES YES YES NO

YES

Availirry Building

213-I204-Cl4-01, R/S

YES NO

RJ-01-706 R/2 YES NO 2-1204-014-4" V2-1204-014-N004 R/2 YES No

YES NO

YES

Q212/GGO

V2-1204-014-N005 R/2 YES NO

YES NO

YES

V2-1204-014-NO M R/2 YES No

YES NO

'ES

216D8114 R/19

2K4-1208-055-02, R/6

YES NO

SG-02-905

NO

NO 2-I?08-055-3" V2-1208-055-N044 R/2 NO

NG

YES NO

YES

Cheencel and

Q212/MGO

V2-1208-055-N045 R/2 NO

ISO

YES NO

YES

Valise Centrol

V2-1208-C55-N046 R/2 10 0

NO

YES NO

YES

Ausflicry Su61 dang

V2-1208-055-N048 R/4 NO

10 0

YES NO

TES

V2-1208-055-It049 R/2 10 0

  1. 0

YES NO

YES

V2-1208-055-N050 R/2 NO

NO

YES NO

YES

V2-1208-055-N051 R/2 NO

NO

YES NO

YES

V2-1208-055-N052 R/2 NO

NO

YES NO

YES

2X4-1208-215-01, R/5

YES NO

3G-02-905

NO

NO 2-1208-215-3" V2-1208-215-N001 R/3 NO

NO

YES NO

YES

Q212/NGO

V2-1208-215-II002 R/3 NO

NO

YES NO

YES

V2-1208-215-N003 R/2 NO

h0

YES NO

YES

V2-1208-215-N004 R/2 L

NO

YES NO

YES

V.'-1208-215-Il005 R/5 NO

NO

YES ho

YES

5

2K. I208-005-02 R/6

YES NO

3C-02-905

N0

NO 2-1208-255-3" V2-1208-255-N001 R/3 NO

NO

YES NO

YES

Q212/FGO

V2-1208-255-N002 R/2 NO

NO

YES NO

YES

V2-1208-055-N005 R/2 NO

NO

YES NO

YES

V2-1208-005-8006 R/3 NO

NO

YES NO

YES

V2-1208-005-N007 R/2 NO

NO

YES NO

YES

2E4-1204-005-01, R/6

YES NO

3G-02-905

11 0

30 2-1208-005-3" V2-1208-005-N002 !!/2 NO

h0

YES No

YES

Q212/FGO

V2-1208-005-N001 R/2 NO

31 0

YES NO

YES

22405-119. R/15

2K3-1204-063-02 R/5

YES NO

3G-01-903

NO

NO 2-1204-057-4" V2-1204-063-N003 R/2 NO

NO

YES NO

YES

Sefity Isjecties

2-1204-063-4" V2-1204-063-ilOO4 R/2 NO

10 0

YES NO

YES

Assilacry Sustdaag

2-1204-063-3" V2-1204-063-It005 R/4 NO

NO

YES NO

YES

Q212/FGO

V2-1204-063-N006 R/2 NO

NO

YES NO

YES

V2-1204-063-N007 R/3

18 0

NO

YES No

YES

V2-1204-063-N009 R/2 No

18 0

YES NO

YES

1ri-8204-063-N010 R/2 NO

No

YES PO

YES

V2-1204-063-N0l2 R/2 NO

No

YES NO

YES

V2-1204-063-N013 R/2 NO

NO

YES ho

YES

V2-1204-063-N001 R/2 NO

NO

YES No

YES

V2-I204-057-N039 R/2 NO

NO

YES len

YES

-

.

-.

-,

,

.* w

=

.

'g-

Page 2

.

. .. .... ....... -

. * < . .

.

_

--

__

_.---

.,

FIFING

,,

.-

F61D

STRESS

-.. ..

SUFFORTS

FFF

!SorETRICS

STRESS

ANALYSIS

LINE NIAGER

CALCUIATION

SUFFORTS

SUFF0WT QC

DRAWING NiseER

INSFECTED ST

AllALYSIS

REVIEM D Bf AND SAFETY /

FIPE

REVIEWD

INSFECTED BY DOCUIElfYATION

SYSYDI med EUILDINC

FIFING ISOfETRICS

SC RRT

PROSIRI NIMBER BRC RRY FIFING CIASS

SUFFORYS

lac Rg

I_E_IC

RR_Y REVIEWD RY NBC

-

.

_

2X4D8315-2. R/I6

2K3-1208-139-01, R/12

YES NO

3C-01-737, R/l YES NO 2-1208-I39-6" V2-1208-139-II016 R/3 YES NO

YES NO

YES

Chemicci med Volume

Central.

Q212/FGO

V2-1208-I)9-N0I4 R/3 YES NO

YES NO

YES

Ammilirry Seilding

V2-I208-139-N003 R/4 YES NO

YES NO

YES

V2-1200-139-It W afs yr3 leo

YES NO

YES

V2-1208-139-N0

Ls YES NO

YES NO

YES

2K3-1208-146-01. R/15

YES 31 0

E-03-903, R/I NO

NO 2-1208-145-4" V2-1208-145-li005 R/5 No

NO

YES NO

YES

2-1208-146-3" ve-I208-145-5006 R/7 EO

No

YES leo

YES

2-1208-A20-l/2*V2-1208-145-11013 R/4 NO

NO

YES 11 0

YES

Q212/FC0

V2-1200-145-N014 R/3 NO

NO

YES NO

TES

V2-1208-145-II015 R/l NO

NO

YES 11 0

YES

V2-1204-145-8016 R/l NO

NO

YES NO

YES

V2-1208-145-N017 R/3 11 0

NO

YES NO

YES

2I405122. R/20

2E3-1205-004-02, R/7

YES 11 0

E-00-718. R/I YES NO 2-1205-004-14" V2-1205-004-N015 ?/4 YES NO

YES If0

YES

Reeldoel Best

Q212/MGO

V2-1205-004-N010 R/3 YES NO

YES NO

YES

Removal Ansiliary

Seildsag

213-1205-004-01 R/13

YES NO

3C-00-718. R/l YES NO 2-1205-004-14" V2-1205-004-N016 R/3 YES NO

YES NO

YES

Q2I2/IIGO

V2-1205-004-II019 R/4 YES ho

YES 31 0

YES

V2-1205-004-N001 R/2 YES 30 0

YES NO

YES

wo

2K3-12C5-006-03, R/12

YES NO

3C-00-725, R/0 YES NO 2-1205-006-8" V2-1205-006-II009 R/4 YES leo

YES leo

YES

Q212/E0

V2-1205-006-Is001 R/5 YES NO

YES leo

YES

2K3-3205-C06-02. R/IZ

fES 11 0

BC-00-725. R/0 YES No 2-1205- W -2" V2-1205hEIC R/6 m m m M

m

Q232/E0

.

.

- - -

-

-

- - -

- - - -

-

..

..

....

t

AREA PERFORMANCE

I

CATEGORY 3

)

Licensee management attention to and involvement

in the performance of nuclear safety or safeguards

octisities are not sufficient.

The licensee's

performance does not significontly exceed that needed

1

to meet minimal regulatory requirernents.

Licensee

resources appear to be strained or not effectively

used.

NRC attention should be increased above normal

levels.

.

)

i

,

.-_ __- --_.--..

, ,

._._,.._..,.__-_,-,_,_..__,-____-_,_,,_.,.,,,.__,,_-._,.,,__,.n.___,,_.._-,_,.n_.

,_

,