Advises That Software for Procedure Generation & Maint Sys Will Be Installed & Fully Functional by 880801,in Response to Insp Repts 50-338/87-39 & 50-339/87-39
ML20155B405
Person / Time
Site: North Anna  Dominion icon.png
Issue date: 06/01/1988
From: Cruden D
VIRGINIA POWER (VIRGINIA ELECTRIC & POWER CO.)
To:
NRC OFFICE OF ADMINISTRATION & RESOURCES MANAGEMENT (ARM)
References
88-060A, 88-60A, NUDOCS 8806130174
Download: ML20155B405 (1)


Text

,

a..

VIHorxi A EI.ECTHIC AND l'OWEH COMI%NY HIcnuoNn, VIHOINI A 2 0061 June 1, 1988 D. M. C a upa w Vaca Passipant-NecLean U. S. Nuclear Regulatory Commission Serial No.

88-060A Attention: Document Control Desk NAPS /JHL Washington, D. C. 20555 Docket Nos.

50-338 50-339 License Nos. NPF-4 NPF-7 Gentlemen:

VIRGINIA ELECTRIC AND POWER COMPANY NORTH ANNA POWER STATION UNITS 1 AND 2 INSPECTION REPORT NOS. 50-338/87-39 AND 50-339/87-39 Our letter dated February 26,1988 (Serial No.88-060) provided the response to the Notice of Deviation from Inspection Report Nos. 50-338/87-39 and 50-339/87-39.

The response to the Notice of Deviation indicated that a procedure generation and maintenance system for emergency operating procedures would be installed and fully functional, by June 1, 1988, to automatically cross-reference and insert setpoints from the setpoint database into the procedures when printed or updated.

The software for the procedure generation and maintenance system for emergency operating procedures is currently being developed but will not be completed by June 1,

1988.

The procedure generation and maintenance system will be installed and fully functional by August 1,1988.

If you have any questions, please contact us.

V ry truly yours, m

s b

D. S. Cr cc:

U. S. Nuclear Regulatory Commission 101 Marietta Street, N. W.

Suite 2900 Atlanta, Georgia 30323 Mr. J. L. Caldwell NRC Senior Resident Inspector North Anna Power Station P(O o

G80A130174 880601 PDR ADOCK 05000338 0

DCD

,