Advises That 850103,0521 & s Describing Groundwater Monitoring Plan Acceptable & Satisfy Requirements of Section 4.2.1 of Plan
ML20154S530
Person / Time
Site: Shoreham File:Long Island Lighting Company icon.png
Issue date: 03/14/1986
From: Butler W
Office of Nuclear Reactor Regulation
To: Leonard J
LONG ISLAND LIGHTING CO.
References
NUDOCS 8604010309
Download: ML20154S530 (5)


Text

- -.

.ma neraq'o UNITED STATES g

8 NUCLEAR REGULATORY COMMISSION o

n y

WASHINGTON. D. C. 20555

\\*****/

MAR 141986 Docket No. 50-322 Mr. John D. Leonard, Jr.

Vice President - Nuclear Operations Long Island Lighting Company Shoreham Nuclear Power Station P.O. Box 618 Wading River, NY 11792

Dear Mr. Leonard:

SUBJECT:

GROUNDWATER MONITORING PROGRAM - SH0REHAM NUCLEAR POWER STATION Appendix B to Facility Operating License No. NPF-36 contains the Non-Radio-logical Environmental Protection Plan (EPP) for the Shorehan Nuclear Power Station. Section 4.2.1 of the EPP requires that a program be established, commencing at the initiation of low power testing above 5% power, to establish the effect'of station freshwater consumption on ground water levels and quality.

By letters dated January 3, 1985 (SNRC-1124), May 21, 1985 (SNRC-1162), and January 16, 1986 (SNRC-1224), you described the groundwater monitoring plan you propose to use to satisfy this requirement. The staff has completed its review of that plan..

The three Monitoring Wells (M-1, F-2, and M-3) and the one Control Wil C.1) proposed by the licensee are located so as the monitor both the upgradient (inland) and downgradient (seaward) effects on both groundwater levels and chloride content of the groundwater that may result from the station's use of its water supply wells. The nearest upgradient offsite wells are 2500 feet to the west and 2900 feet southwest of the station's wells. The nearest offsite downgradient wells are located on the beach on the north side of Wading River and the adjoining marsh, approximately 2100 feet north of the supply wells. The monitoring wells are located approximately 400 feet to the south-southwest, 900 feet to the south, and 2100 feet to the north, and the control well is 1500 feet to southwest of the station wells. The monitoring well to the north will determine the effects of the station groundwater withdrawal on the downgradient wells while the other monitorirg wells will indicate changes in groundwater level and chloride content before upgradient wells are affected.

The staff has also reviewed data on chloride concentration in the station supply wells during th'e years 1983-1985 and notes that station usage has not resulted in any noticeable increase in chloride concentration in the water withdrawn for plant use. We have also discussed these results with Mr. D. Picha of the New York State Department of Environmental Conservation. He had no objection to the proposed plan.

8604010309 e60314 PDR ADOCK 05000322 P

PDR

}

'l

's 7..

Based on this review, the staff has concluded that your groundwater monitoring plan'is acceptable and satisfies the requirements of section 4.2.1 of the EPP.

Sincerely, A

Walter R. Butler, Director BWR Project Directorate No. 4 Division of BWR Licensing cc: See next page 1

l l

i I

l l

t

Mr. John D. Leonard, Jr.

Shoreham Nuclear Power Station Long Island Lighting Company (list 1) cc:

Stephen B. Latham, Esq.

Gerald C. Crotty, Esq.

John F. Shea, III, Esq.

Ben Wiles, Esq.

Twomey, Latham & Shea Counsel to the Governor Attorneys at Law Executive Chamber Post Office Box 398 State Capitol 33 West Second Street Albany, New York 12224 Riverhead, New York 11901 Herbert H. Brown, Esq.

Alan S. Rosenthal, Esq., Chairman Lawrence Coe Lanpher, Esq.

Atomic Safety & Licensing Appeal Board Karla J. Letsche, Esq.

U.S. Nuclear Regulatory Commission Kirkpatrick & Lockhart Washington, D.C.

20555 1900 M Street, NW - 8th Floor Washington, D.C.

20036 W. Taylor Reveley, III, Esq.

Hunton & Williams Dr. Monroe Schneider 707 East Main Street North Shore Committee Post Office Box 1535 Post Office Box 231 Richmond, Virginia 23212 Wading River, New York 11792 Howard A. Wilber Fabian G. Palomino, Esq.

Atomic Safety & Licensing Appeal Board Special Counsel to the Governor U.S. Nuclear Regulatory Commission Executive Chamber - State Capitol Washington, D.C.

20555 Albany, New York 12224 Atomic Safety & Licensing Board Panel Anthony F. Earley, Jr., Esq.

U.S. Nuclear Regulatory Comission General Counsel Washington, D.C.

20555 Long Island Lighting Company 175 East Old County Road Atomic Safety & Licensing Appeal Board Hicksville, New York 11801 Panel U.S. Nuclear Regulatory Commission Mr. Lawrence Britt Washington, D.C.

20555 Shoreham Nuclear Power Station Post Office Box 618 Gary J. Edles, Esq.

Wading River, New York 11792 Atomic Safety & Licensing Appeal Board U.S. Nuclear Regulatory Comission Martin Bradley Ashare, Esq.

Washington, D.C.

20S55 Suffolk County Attorney H. Lee Dennison Building Richard M. Kessel Veteran's Memorial Highway Chairman & Executive Director Hauppauge, New York 11788 New York State Consumer Protection Board Room 1725 Resident Inspector 250 Broadway Shoreham NPS New York, New York 10007 U.S. Nuclear Regulatory Commission Post Office Box B Jonathan D. Feinberg, Esq.

Rocky Point, New York 11778 New York State Department of Public Service Regional Administrator, Region I Three Empire State Plaza U.S. Nuclear Regulatory Commission Albany, New York 12223 631 Park Avenue King of Prussia, Pennsylvania 19406 1

~.

.. Shoreham(1) cc:

Robert Abrams, Esq.

Attorney General of the State of New York ATTN: Peter Bienstock, Esq.

Department of Law State of New York Two World Trade Center Room 46 New York, New York 10041 Mr. William Steiger Plant Manager Shoreham Nuclear Power Station Post Office Box 628 Wading ~ River, New York 11792 MHB Technical Associates 1723 Hamilton Aenue - Suite K San Jose, California 95125 Honorable Peter Cahalan Suffolk County Executive County Executive / Legislative Building Veteran's Memorial Highway Hauppauge, New York' 11788 Mr. Jay Dunkleberger New York State Energy Office Agency Building 2 Empire State Plaza-Albany, New York 12223 Ms. Nora Bredes Shoreham Opponents Coalition 195 East Main Street Smithtown, New York 11787 Chris Nolin New York State Assembly

' Energy Committee 626 Legislative Office Building Albany, New York 12248 Peter S. Everett, Esq.

Hunton & Williams 2000 Pennsylvania Avenue, NW Washington, D.C.

20036

7

' _ Based on this review, the staff has concluded that your groundwater monitoring plan is acceptable and satisfies the requirements of section

~4.2.1 of the EPP.

Sincerely, oneshet asned by Walter R. Butler, Director BWR Project Directorate No. 4 Divisien of BWR Licensing cc: See next page DISTRIBUTION netmet J11e-NRC PDR Local PDR PD#4 Reading RBernero-4 Bordenick, OELD EJordan BGrimes

-JPartlow RCaruso EHylton ACks (10)

RWescott RLaGrange BDLiaw' Glainas WHouston 1

i PD# FEM.

PD#4/D RCariso:lb WButler (n 03/ /86 03/gh/86

-,..