ML20154S417

From kanterella
Jump to navigation Jump to search
Discusses 880524 Telcon Re Insp Rept 50-298/86-28 & Util 870617 Response to Noted Violations.Subjs Discussed During Telcon Described in Encl Meeting Summary
ML20154S417
Person / Time
Site: Cooper Entergy icon.png
Issue date: 05/26/1988
From: Callan L
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
To: Trevors G
NEBRASKA PUBLIC POWER DISTRICT
References
NUDOCS 8806090064
Download: ML20154S417 (5)


See also: IR 05000298/1986028

Text

- - - - - - - _ _ _ _

,

,

,

,. .

.

Myw.... g g 1988

In Reply Refer To:

Docket: 50-298.

Nebraska Public Power District

ATTN:

George A. Trevors

Division Manager - Nuclear Support

P.O. Box 499

Columbus, NE 68601

Gentlemen:-

This refers to the telephone conference call conducted on May 24, 1988, with

you and other members of your staff, and Region IV personnel. This conference

call regarded certain findings documented in our NRC Inspection Report 50-298/

86-28, dated April 1,1987, and your June 17, 1987 response to those findings.

The subjects discussed during the conference call are described in the enclosed

Meeting Sumary.

In accordance with Section 2.790 of the NRC's "Rules of Practice," Part 2,

Title 10, Code of Federal Regulations, a copy of this letter will be placed in

the NRC's Public Document Room.

Should you have any questions concerning this matter, we will be pleased to

discuss them with you.

Sincerely,

k

k

L. J. Callan, Director

Division of Reactor Projects

Enclosure:

Meeting Sumary

cc w/ encl:

(seenextpage)

RIV:DRP/C *

TS/DRS *

D/DRS *

D D

D/DRP b

EJHoller:gb

REIreland

JMilhoan

AB' ach

,LJCallan

<

'

/ /88

/ /88

/ /88

/88

5 /26/88

t

  • Previously concurred

jll

8806090064 880526

h

,

PDR

ADOCK 05000298

Q

DCD

.-

.

. . .

-

_ - . -

.

.

_

L

1

, . U.

Nebrasks Public Power District

2

Cooper Nuclear Station

ATTN: Guy Horn, Division Manager.

of. Nuclear Operations-

P.O. Box 98

JBrownv111e, Nebraska 68321-

'

Kansas Radiation Control Program Director

Nebraska Radiation Control Program Director

bec to DMB (IE-01) - DRS & DRP

bec distrib. by RIV:

4

  • RRI

R. D. Martin, RA

-

  • SectionChief(DRP/C)

Lisa Shea, RM/ALF

  • RPSB-DRSS
  • RIV File
  • Project Engineer, DRP/C

RSTS Operator

  • W. Long, NRR Project Manager
  • DRS
  • DRP

i

u

!

.

1

.

1

}

- -

-

.

>

.

s

s .

.

ENCLOSURE

NEBRASKA PUBLIC POWER DISTRICT

JANUARY 28 -1988

MEETING SUMMARY

Licensee:

Nebraska Public Power District (NPPD)

Facility:

CooperNuclearStation(CNS)

License:

DRP-46

Docket:

50-237

SUBJECT:

COMPLIANCE WITH 10 CFR 50.49 AT COOPER NUCLEAR STATION

On May 24, 1988, representatives of Nebraska Pbblic Power District (NPPD)

participated in a telephone conference cell with NRC Region IV personnel to

discuss the findings documented id NRC Inspection Report 50-298/86-28 dated

April 1, 1987, and NPPD's re 90nse to that report dated June 17, 1987. The

participant list for the .. . phone conference is attached. The

conference call was held at the request of Region IV.

'

The NRC discussed its concern with the operability of certain items addressed

in NRC Inspection Report 50-298/86-28 and requested an update from NPPD

regarding the corrective steps noted in NPPD's June 17, 1987 response to the

report. The particular items discussed were:

1.

Boston Insulated Wire (BIW) Bostrad 7E Cable (Item 50-298/8628-01).

NPPD

f

'

advised that BIW Bostrad 7E cable installations had been modified to

provide for conduit shielding of the cable.

2.

Kerite 600 Volt Cable (Item 50-298/8628-03). NPPD advised that an

operability analysis had been performed regarding this cable.

NPPD also

indicated that modifications at CNS may have replaced Kerite 600 volt

cable applications inside containment. NPPD offered to make further

comments regarding Kerite 600 volt cable in a subsequent telephone

conference call scheduled for Friday, May 27, 1988.

,

3.

Raychem Coaxial Cable (Item 50-298/8628-04). NPPD indicated that

cable inspections to date had not identified use of this cable in EQ

applications but that inspection results were still being evaluated.

NPPD

agreed to inform the NRC if Raychem cable installations of interest were

'

identified and to address this item in the Friday, May 27, 1988 telephone

conference call.

4.

General Electric Electrical Penetrations (Item 50-298/8628-5). NPPD

advised that the EQ file nad been revised to clearly show the link

between tested and installed items at CNS.

- _ _____ _ ____________

- _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ - _ _ _ _ - _ _ _ _ _ _ _ _ - _ _

_ _ _ _ _ _ _ _ _ _ _

<t.

r

,

.

2

5.

Model OP-N Microswitches (Item'50-298/8628-11).

NPPD advised that

similarity comparisons have been completed.

6.

ASCO. Solenoid Valves (Item 50-298/8628-14).

NPPD advised that plant air

system pressure is limited to 110 psig and that EQ data packages have

,

been revised.-

7.

Okonite Splices in Limitorque Motor Operators (Item 50-298/8620-09).

NPPD advised that it would address this item in the Friday, May 27, 1988

telephone conference call.

8.

Scotch Taped Splices and Blind Barrel Splices (Item 50-298/8628-08).

NPPD

advised that the taped splices had been replaced and that these items

were addressed in a NPPD letter to the NRC dated August 24, 1987.

Region IV and NPPD agreed to further discuss items 2. , 3. , and 7. above in a

subsequent telephone conference cal'i at 1:00 p.m. (CDT) on Friday, May 27,

1988.

Attachment:

Participation List.

l

.

.

.

._

-

.g :

_$

.-

, . . .

,

Attachment

_ Telephone Conference Call May 24, 2988

4

With Nebraska Public Power District

NRC Participants:

J. Milhoan, Director, Division of Reactor Safety _

B. Beach, Deputy Director, Division of Reactor Projects

R. Ireland, Chief, Plant Safety Section

A. Johnson, Reactor Inspector

E. Holler, Chief, Projects Section C

W. Bennett, Senior Re;ident Inspector

,.

Licensee Participants:

G. H.-Trevors, Nuclear Support Division Manager

R. E. Wilbur, Nuclear Engineering and Construction

Division Manager

W. C. Fisher, Electrical Engineering Supervisor

E. M. Hace, Engineering Manager

J. R. Flaherty, Plant Engineering Supervisor

_S. J. Jobe, Simulator Supervisor

J. R. Hackney, Senior Staff Engineer

D. E. Buman, Electrical Engineer

G. R. Smith, Licensing and Safety Supervisor

,