Forwards Insp Repts 50-348/88-10 & 50-364/88-10 on 880328-0401 & Notice of Violation
ML20154P583
Person / Time
Site: Farley  Southern Nuclear icon.png
Issue date: 05/20/1988
From: Dan Collins
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To: Mcdonald R
ALABAMA POWER CO.
Shared Package
ML20154P588 List:
References
NUDOCS 8806030388
Download: ML20154P583 (2)


See also: IR 05000348/1988010

Text

..;

'

-

+ .

- .

,,

- t

O

NAY 4 V 1986

Docket Nos. 50-348, 50-364

License Nos. NPF-2 and NPF-8

Alfbama Power Company

fTN: Mr. R. P. Mcdonald-

Senior Vice President

P. O. Box 2641

Birmingham, AL. 35291-0400

Gentlemen:

SUBJECT: NOTICE OF VIOLATION

(NRC INSPECTION REPORT NOS. 50-348/88-10 AND 50-364/88-10)

This refers to the Nuclear Regulatory Comission (NRC) ir.spection conducted by

S. Adamovitz on March 28 - April 1,1988. The inspection included a review of

activities authorized for your Farley facility. At the conclusion of the

inspection, the findings were discussed with those members of your staff

identified in the enclosed inspection report.

Areas examined during the inspection are identified in the report. Within

these areas, the inspection consisted of selective examinations of procedures

and representative records, interviews with personnel, and observation of

activities in progress.

The inspection findings indicate that certain activities appeared to violate

NRC requirements. The violation, references to pertinent requirements, and

elements to be included in your response are described in the enclosed Notice

of Violation.

In accordance with Section 2.790 of the NRC's "Rules of Practice, Part 2

Title 10, Code of Federal Regulations, a copy of this letter and its enclosures

will be placed in the NRC Public Document Room.

1

The responses directed by this letter and its enclosure are not subject to the  !

clearance procedures of the Office of Management and Budget as required by the i

Paperwork Reduction Act of 1980, Pub. L. No.96-511. i

i

Should you have any questions concerning this letter, please contact us, s -

1

Sincer ly {

J

Douglas M. Collins, Chief i

Emergency Preparedness and

Radiological Protection Branch

Division of Radiation Safety

and Safeguards l

Enclosures: (See page 2)

8806030388 880520

PDR ADOCK 05000348

Q DCD

(( t

'

c6 j

-

.

.- ,

-

~

.. . MAY 2 01988

.

Alabama Power Company 2

Enclosures:

1. Notice of Violation

.2. 'NRC Inspection' Report

ep w/encis:

4. M. Guthrie, Executive Vice President

J. D. Woodard,-General Manager -

Juclear Plant

V. G. Hairston, 110. Vice President -

Nuclear Support

M W. McGowan, Manager-Safety Audit

gnd Engineering Review

F. Fulmer, Supervisor-Safety

Audit and Engineering Review

beg w/encis:

MC Resident Inspector

DRS Technical Assistant

(F. Reeves, Project Manager, NRR-

State of Alabama

Documer.t Control Desk

i

!

q

4

Ril I RII j

CML -$f4'1 i

MSqdamovitz:es J $ {e HDance

]NJ/ w/88 i

1 5/11/88 Ij/88 [F j

l

lll