Mr. James ! nubel

- c er 1

8 l...-

=

Chiaf Nucleil Officer Power Authority of th3 Stats of New York 123 Main Street White Plains, NY-10601

SUBJECT:

JAMES A. FITZPATRICK NUCLEAR POWER PLANT - BULLETIN 96-03,

  • POTENTIAL ~ PLUGGING OF EMERGENCY CORE COOLING SUCTION STRAINERS BY DEBRIS IN BOILING WATER REACTORS (TAC NO. M96146)

Dear Mr. Knubel:

L On September 16,1998, the New York Power Authority (NYPA) provided information regarding NRC Bulletin (B) 96-03," Potential Plugging of Emergency Core Cooling Suction Strainers by Debris in Boiling Water Reactors" for the James A. FitzPatrick Nuclear Power Plant. This information addressed issues discussed in a May 21,1998, meeting between the NRC staff and NYPA personnel, and documented NYPA's basis for proposing to change commitments regarding completion of the B 96-03 requested actions at FitzPatrick.'

Your letter describes plans to sponsor testing of microporous insulation to determine if such material presently installed in the FitzPatrick drywell can remain in place or should be replaced.

if required, this insulation will be replaced during the R14/C15 refueling outage presently scheduled for the fourth _ quarter of 2000. Until that time, the cinent licensing basis, which assumes 50% suction strainer blockage, will remain in effect.

We find that your request to defer completion of the actions requested in B 96-03 is acceptable, based on your commitments to ensure suppression pool cleanliness, to replace mineral wool insulation in the drywell, and to complete installation of improved suction strainers during the 1998 refueling outage. These actions provide assurance of the safe operation of the FitzPatrick plant until the R14/C15 refueling outage.

\\

if you have any questions regarding this matter, please contact me at (301) 415-1470.

p Sincerely, O ri g i n a 1 Signed by:

Joseph F. Williams, Project Manager

-()/

Project Directorate I-1 Division of Reactor Projects - 1/ll Office of Nuclear Reactor Regulation 1

i Docket No. 50-333 J

cc: See next page DISTRIBI) TION.

}i\\{

~

,,.y g m, a TOnelset Piled S. Bajwa ACRS n;;MZ O NA N_

PUBLIC S. Little C. Hehl, Region i 4

PDI-1 R/F J. Williams J. Zwolinski OGC

. DOCUMENT NAME: G:\\FITZ\\N96146B.LTR To receive a copy of this document, indicate in the box: "C" = Copy without attachment / enclosure "E" = Copy with t_ttachment/ enclosure ' "N" = No copy jqlA OFFICE PM:PDI 1

/',/ l E LA:PDI 1 b 4 W I

D:PDI-1,j h l

SCSB (T-l l

NAME JWilliams:tec/fPl/-

SLittle ' Y!f SBajwa F C8ertinger i

DATE 10/$( /98 /i 10/ N /98 b 10/ 11/98 10/ 4 /98 kid l

Official flecord Copy

~

9810190187 981013 PDR ADOCK 05000333 G

PM

Mr. Jrmes Knubel October 13, 1998

~

Chtf Nuclear Officer i

Pow:r Authority of thm Stats of i _.

New York l

123 Main Street White Plains, NY 10601

SUBJECT:

JAMES A. FITZPATRICK NUCLEAR POWER PLANT - BULLETIN 96-03,

  • POTENTIAL PLUGGING OF EMERGENCY CORE COOLING SUCTION STRAINERS BY DEBRIS IN BOILING WATER REACTORS" (TAC NO. M96146) i

Dear Mr. Knubel:

i On September 16,1998, the New York Power Authority (NYPA) provided information regarding j

i NRC Bulletin (B) 96-03," Potential Plugging of Emergency Core Cooling Suction Strainers by l

Debris in Boiling Water Reactors" for the James A. FitzPatrick Nuclear Power Plant. This information addressed issues discussed in a May 21,1998, meeting between the NRC staff and NYPA personnel, and documented NYPA's basis for proposing to change commitments regarding completion of the B 96-03 requested actions at FitzPatrick.

Your letter describes plans to sponsor testing of microporous insulation to determine if such material presently installed in the FitzPatrick drywell can remain in place or should be replaced.

if required, this insulation will be replaced during the R14/C15 refueling outage presently l

scheduled for the fourth quarter of 2000. Until that time, the current licensing basis, which l

assumes 50% suction strainer blockage, will remain in effect.

We find that your request to defer completion of the actions requested in B 96-03 is acceptable, based on your commitments to ensure suppression pool cleanliness, to replace mineral wool insulation in the drywell, and to complete installation of improved suction strainers during the l

1998 refueling outage. These actions provide assurance of the safe operation of the FitzPatrick l

plant until the R14/C15 refueling outage.

l If you have any questions regarding this matter, please contact me at (301) 415-1470.

l j

Sincerely, O ri g i n a l S i g n e d by :

Joseph F. Williams, Project Manager Project Directorate 1-1 Division of Reactor Projects - 1/11 Office of Nuclear Reactor Regulation i

Docket No. 50-333 cc: See next page DISTRIBUTION-Docket File S. Bajwa ACRS PUBLIC S. Little C. Hehl, Region I PDI-1 R/F J. Williams J. Zwolinski OGC DOCUMENT NAME: G:\\FITZ\\N96146B.LTR To receive a copy of this document, indicate in the box: "C" = Copy without attachment /encicsure *E" = Copy with cttachment/enciosure "N" = No copy

() l k OFFICE PM:PDI 1

/,7/ lEl LA:PDI 1

'e),

I l D:PDI 1,/ b l

SCSB

\\,I l

l NAME JWilliams:lec[/3/

Slittle

f.

SBajwa F CBerlinger DATE 10/ )( /98 //

10/ s /98 ~

10/ 11/98 10/ Q /98 LO Official Record Copy

~

T

E

' J;mes Knubel

. James A. FitzPatrick Nuclear 0

Power Authority of the State Power Plant 4

of New York

' cc:

h Mr. Gerald C. Goldstein Regional Administrator, Region I

.. Assistant General Counsel.

U.S. Nuclear Regulatory Commission

^

/ Power Authority of the State -

475 Allendale Road

' of New York King of Prussia,' PA 19406 -

1633 Broadway New York, NY 10019 Mr. F. William Valentino, President i

New York State Energy, Research,

[

Resident inspector's Office and Development Authority U. S. Nuclear Regulatory Commission Corporate Plaza West P.0, Box.136 286 Washington Avenue Extension Lycoming, NY.13093 Albany, NY 12203-6399

. Mr. Harry P. Salmon, Jr.

Mr. Richard L. Patch, Director j

Vice President - Engineering Quality Assurance Power Authority of the State Power Authority of the State of New York -

of New York 123 Main Street 123 Main Street '

i White Plains, NY.10601 White Plains, NY 10601 Ms. Charlene D. Faison -

Mr. Gerard Goering l

Director Nuclear Licensing 28112 Bayview Drive Power Authority of the State Red Wing, MN 55066 of New York -

,123 Main Street -

Mr.' James Gagliardo White Plains, NY 10601 Safety Review Committee 708 Castlewood Avenue L Supervisor Arlington,TX 76012 Town of Scriba Route 8, Box 382 Mr. Arthur Zaremba, Licensing Manager Oswego, NY 13126 James A. FitzPatrick Nuclear l'

Power Plant Mr. Eugene W. Zeltmann P.O. Box 41

President and Chief Operating Lycoming, NY 13093 l.

Officer i

Power Authority of the State Mr. Paul Eddy L

of New York New York State Dept. of l

99 Washington Ave., Suite No. 2005 Public Service h'

Albany, NY 12210-2820 3 Empire State Plaza,10th Floor Albany, NY 12223 i

Charles Donaldson, Esquire i

Assistant Attorney General Michael J. Colomb i

New York Department of Law Site Executive Officer 120 Broadway James A. FitzPatrick Nuclear Power Plant i

New York, NY 10271 P.O. Box 41 Lycoming, NY 13093 L

1 i.

. _ _