Concludes That Licensee Adequately Met Acceptance Criteria for Leakage Reduction Program in Response to TMI Action Item III.D.1.1 Re Leakage Reduction Program of Potential Primary Coolant Sources Outside Containment
ML20154K927
Person / Time
Site: Perry FirstEnergy icon.png
Issue date: 09/20/1988
From: Colburn T
Office of Nuclear Reactor Regulation
To: Kaplan A
CLEVELAND ELECTRIC ILLUMINATING CO.
References
TAC-69180, NUDOCS 8809260047
Download: ML20154K927 (3)


Text

_ _ _ _ _ _ _ _ _ _ _ _ _ __

Septanber 20, 1988 Docket No. 50-440 DISTRIBUTION:

< Docket J Hes , NRC & Local PDRs PDIII-S r/f KPerkins MVirgilio PKreutzer  !

TColburn OGC-WF1 Mr. Alvin Kaplan, Vice President EJordan BGrimes Nuclear Group ACRS(10) PDIII-3 Gray Files

  • The Cleveland Electric Illuminating Company 10 Center Road Perry, Ohio 44081 t Dear Mr. Keplar-t

SUBJECT:

LEAK REDUCTION PROGRAM - LICENSE COMMITHENT 15 0F SECTION IB 0F USAR (UPDATEDSAFETYANALYSISREPORT)FORTHEPERRYNUCLEARPLANTUNIT1 (TACNO.69180) ,

In response to TMI Action Plan Item III.D.1.1, "Integrity of Systems Outside I Containment Likely to Contain Radioactive Material for Pressurized-Water Reactors and Boiling-Water Reactors," licensees were required to implement a  !

program to reduce leakage from systems outside containment that would or could  !

contain highly radioactive fluids during a serious accident or transient to  !

4 as low as practical levels. The NRC staff's acceptance of the leak reduction program for Perry Unit 1 is documented in Supplemental Safety Evaluation Report l (SSER) No. 8 dated January 1986, Section 11.5. This program was required (as l committed to by you in the USAR under License Condition No. 15) to be implemented prior to full power operation.

, On June 28 5 1987 you transmitted the results of your leakage reduction program j of potential primary coolant sources outside containment. The results of your i tests indicate a total leakage rate of 0 standard cubic cantimeters per minute "

(SCCM) air for components outside containment and not included in the secondary .

containment bypass leakage rate surveillance and a total leakage rate of less  !

than 5.0 gallons per hour (GPH) liquid for systems and components outside the I secondary containment which could carry primary coolant after a serious i transient or accident.

i Based upon our review of your test results, we conclude that you have adequately net the acceptance criteria for this item and, therefore, we consider this item ,

closed for your facility. We further conclude that you have acceptably fulfilled i i

[

l [

i I

[

[

8809260047 880920 >

{DR ADOCK 05000440 J PDC D Fo l yo  ;

4- Mr. Alvin Kaplan  :

I your comitments as described in License Condition 15 of the USAR. This completes y

l our review effort under TAC No. 69180.  ;

i j If you have any questions, please contact met at (301) 492-1369.

Sincerely,  !

! Timothy G. Colburn, Project Manager Project Directorate III-3 i Division of Reactor Projects - III, IV, V and Special Projects cc: See next page .

I 1

r

?

i

! f

! f i.

I i

l

! l 1

1 I I I l 1 5

// iW 8  ;

E" J.Crag

( "6 l l Office: LA/PD111-3 PN/PDIll-3 PD I-3  :

1 Surname: PKrWHter TColburn/tg ' ": d ;n KP lins i f//A/88 Date: 7 / fp /88  %/t 5/88 7/:p/88 l

t i

Y

?

'l t

I

  • Mr. Alvin Kaplan Perry Nuclear Power Plant The Cleveland Electric Unit 1 Illuminating Company cc:

Shaw, Pittman, Potts & Trowbridge Mr. James W. Harris, Director 2300 N Street, N.W. Division of Power Generation Washington, D.C. 20037 Oaio Department of Industrial Relations David E. Burke P.O. Box 825 The Cleveland Electric Columbus, Ohio 43216 Illuminating Company P.O. Box 5000 The Honorable Lawrence Logan Cleveland, Ohio 44101 Mayor, Village of Perry 4203 Harper Street Resident inspector's Office Perry, Ohio 44081 U.S. Nuclear Regulatory Comission Parmly at Center Road The Honorable Robert V. Orosz Perry, Ohio 44081 Mayor, Village of North Perry North Perry Village Hall Regional Aaministrator, Region III 4778 Lockwood Road U.S. Nuclear Regulatory Comission North Perry Village, Ohio 44081 799 Roosevelt Road Glen Ellyn, Illinois 60137 Attorney General Department of Attorney General Frank P. Weiss. Esq. 30 East Broad Street Assistant Prosecuting Attorney Columbus, Ohio 43216 105 Main Street Lake County Administration Center Radiological Health Program Painesville, Ohio 44077 Ohio Department of Health 1224 Kinnear Road Ms. Sue Hiatt Columbus, Ohio 43212 OCRE Interim Representative 8275 Munson Ohio Environtrental Protection Mentor, Ohio 44060 Agency 361 East Broad Street Terry J. Lodge, Esq. Columbus, Ohio 43266-0558 618 N. Michigan Street Suite 105 Mr. Phillip S. Haskell, Chaiman Toledo, Ohio 43624 Perry Township Board of Trustees Box 65 John G. Cardinal, Esq. 4171 Main Street Prosecuting Attorney Perry, Ohio 44081 Ashtabula County Courthouse Jefferson, Ohio 44047 State of Ohio Public Utilities Comission E11eer M. Buzzelli 180 East Broad Street The Cleveland Eltctric Columbus, Ohio 43266-0573 Illuminating Company P. O. Box 97 E-210 Mr. Murray R. Edelman Perry, Ohio 44081 Centerior Energy 6200 Oaktree Blvd.

Independence Ohio 44131