ML20154K117
| ML20154K117 | |
| Person / Time | |
|---|---|
| Site: | Fort Calhoun |
| Issue date: | 09/16/1988 |
| From: | Holahan G Office of Nuclear Reactor Regulation |
| To: | Petersen F OMAHA PUBLIC POWER DISTRICT |
| Shared Package | |
| ML20154K120 | List: |
| References | |
| IEB-79-14, NUDOCS 8809230224 | |
| Download: ML20154K117 (5) | |
See also: IR 05000285/1988200
Text
i
1
,, f
9,
UNITED STATES
+
y
i r g,[ ,j
NUCLEAR REGUL ATORY COMMISSION
s4
wasmNo os.o c.rosss
,
t%
a
g' ...../
September 16, 1988
v
Docket No. 50-285
M'r. Fred M. Petersen, President
anc Chief Executive Officer
Omaha Public Power District
IC3 Harney Street
Omaha, Nebraska S8102
Dear Mr. Petersen:
SUBJECT:
REINSPECTIOh 0F SAFtT) 3YSTFMS OUTAGE MODIFICATION 'NSPECTION
DESIGN FINDINGS, 50-/M/83-200
This letter conveys the results and nntiusions of the reinspection of the
findings originally documented in Safety Systems Outage Modification inspection
(550MI) Report 50-285/85-22 dated January 25, 1986.
The inspection team
consisted of personnel from NRC's Office of Nuclear Reactor Regulation (NRR),
Region IV, and consultants.
The inspection took place at your offices in
Omahe, Nebraska, on February 10 and the weeks of March 21 and April 4,1988.
The exit meeting was conducted on April 8, 1968.
The primary purpose of the inspection was to review the corrective actions
and implementation of corrective ae.tions for ali the findings documented in
the original SSCMI design inspection report.
The secondary purpose of the
inspe: tion was to perform a programatic review of Fort Calhoun's design basis
reconstitution program whitn was developed as a result of the original SSOMI
design inspection.
With regard to the corrective action review of the original SSON! findings.
39 of the original 47 findings identified in Inspection Report 50-285/85-22
were c?o;ed. One new issue was identified in the mechanical components
discipline ard was closed for the purpose cf the inspection report.
There-
fore, 40 of the 48 findings identified by NRC are closed. However, four of the
closed findings are licensing issues that Omaha Public Power District (OPFD)
needs to 'esolve.
The licensino issues include adequacy of the piping analyses
performed in response to NRC Bulletin 79-14 and compliance with Updated Safety
Anslysis Report (USAR) seismic design requirements for valves, electric motor
operators, junction boxes, and pressure switches. See findings 03.1-4, D3.2-4,
03.2-6, and 03.2-8 in the mechanical components area for a more cceprehtnsive
discussion of these licensing issues.
In review 49 the corrective actions assretated with the SSOMI findings, the
inspection teani identified the following significant itens for which
increased OPPD management involvement appears to be warranted to bring the
issues identified to effective resolution.
First, the functioral testing
associatec with the accurulators for air-operated valves wat inacaquate.
Previously tested air-operated valves need to be retested or the test data
es09230224 880916
- [,g
.-
ADOCK 050002S5
(
I ll
Q
I
I
Mr. Fred M. Petersen
-2-
September 16, I U
should be reevaluated to ensure that adequate function:1 tests were performed.
' All air-operated valves with accumulators need to be functionally tested before
the end of the next refueling outage using techniques that include consideration
of worst-case operating conditions. Also, development of criteria for functional
testing and surveillance testing of air-operated valves is recomended to
ensure consistent postmodification testing and assurance of design adequacy
over the life of the plant. Second, many of the corrective actions for the
previously identified findings were not complete at the beginning of the
inspection. Since the findings were identified by the NRC more than two years
ago, the fact that many corrective actions were incomplete is indicative of a
lack of attentio:' to NRC identifieo issues.
Further, closure of the findings
required direct NRC involvement to define actions nececsary for resolution.
Once the inspection team identified the required actio , OPPD was able to close
many of the findings.
However, OPPD must be more self-sufficient and should
have closed many of these findings without relying on interaction with the
inspection team.
It was the feeling of the inspection team that, were it not
for the NRC presence, many of these corrective actions would have languished
for a considerable time before being completed
Third, the inspection team
identified areas where the USAR is not being ktpt current. An updated and
ac urate USAR is essential for Fort Calhoun because it remains the major source
of design-basis information until the design-basis reconstitution program is
completed.
Finally, the team identified areas where USAR comitments were not
being implemented.
For example, containment isolation valve position indica-
tion as not maintained for all operating modes (Deficiency 04.3-1) and valve
actuator seismic acceleration design requirements were not censistently utilized
(Deficiency D3.2-7).
As a result of this recent inspection, the team became aware of the many
enhancements made by 0 PPD to its design process.
OPPD's comitment to the
design reconstitution program is a necessary and major undertaking. The
programatic changes were apparent to the inspection team and if properly
implemented should result in an acceptable documented design tasis when the work
!
is com,'leted in 1991, as scheduled. The team was generally impressed by the
overall structure and content of the auxiliary feedwater system design basis
document as well As the number of desig* attributes addressed in-depth in
that document.
,
I
You are rcquested to respond in writing to the eight open items listed on
t
pages A-1 through A-3 of the enclosed report within 60 days after receipt of
this letter.
You should address the specific action required for each item
and the schedule for completion of that action.
In accordance with 10 CFR 2.790(a), a copy of this letter and enclosures will
be placed in the hRC Public Document Room.
1
.
.
-
.__
.
__
_
..
_
_ _ - _ - _ _ _ _ _ _ _ _
\\
\\
Mr. Fred M. Petersen
-3-
September 16, 1988
Should you have any questions concerning this inspection, please contact Mr.
Ronald Parkhill (301-492-0963) of this office.
Sincerely,
@W
w
Gary M. Hola
n. Acting Director
Division of Reactor Projects. III, IV, V
and Special Projects
Office of Nuclear Reactor Regulation
Enclosure:
Inspection Report 50-265/88-200
,
/
.
.
_ _ _ _ _ _
_ . _ . _
I
I
Mr. Fred M. Petersen
-4-
September 16, 1988
cc w/ enclosure:
Mr. Harry H. Voigt. Esq.
LeBoeuf, Lamb, Leiby & MacRae
1333 New Hampshire Avenue, NW
Washington, D.C.
20036
'
Mr. Jack Jensen, Chairman
Washington County Board
of Supervisor
Blair, Nebraska 68008
Mr. Phillip Harrell, Hesident Inspector
U.S. Nuclear Regulatory Commission
P.O. Box 309
Fort Calhoun, Nebraska 68023
Mr. Charles B. Brinkman, Manager
Washington Nuclear Operations
C-E Power Systems
7910 Woodmont Avenue
Bethesda, Maryland 20814
Regional Administrator, Region IV
U.S. Nuclear Regulatory Comission
Office of Executive Director
for Operations
611 Ryan * .aza Drive, Suite IF
Arlington, Texas 76011
Mr. Harolo Borchert, Dire t',r
Division of Radiological halth
Department of Health
301 Centennial Mall, South
P.O. Box 95007
Lincoln, Nebraska. 68509
i
Mr. W. G. Gates, Manager
l
Fort Calhoun Station
P.O. Box 399
Fort Calhoun, Nebraska 68023
l
1100 Circle 75 Parkway
Atlanta, Georgia 30339
I
l
l
-
'A
Mr. Fred M. Pet rsen
5-
September 16, 1988
Distribution:
Docket File 50-285
RSIB R/F
DRIS R/F
RWParl' hill, NRR
EVImbro, NRR
CHaughney, NRR
JEKonklin, NRR
BKGrimes, hRR
LBMarsh, NRR
PTKuo, NRR
Alee, NRR
ABeach, RIV
JMilhoan, PlV
TWestermun, RIV
JJaudon, RIV
ABournia, NRR
JCalvo, NRR
VNoonan, NRR
PHHarrell, SRI
MMurphy, Rly
Regional Administrators
Regional Division Directors
POR
LPUR
ACRS(3)
OGC (3)
1" .'istribution
0f*I
Ift
c. 9l,1 't 6
$lYlY!Y
0.
I3f VL
i/
OFC
- RSIB:DRIS:NRR
- RSIB:DRIS:NRR :RSIB:
RR :05
I"S:t
- DRP:hRR
- /4
[.
. : . . . . . . . 4pf g./. - - - - . . . .
......:................:...- g ...:
-
- ..
NAME
- RWParkhill:jj
- EVlmbro
- CJHaugt
- BK 1m
- DC+u
6eM :
. . . . . . : . . . . . . . . . . . . . . . . : . . . . . . . - - . . . . . : . . . . . . . . . . ' . . . : . . . . . . . . . . . . . . : US M{" ^d'- . . .
,
lDATE
- 08/0/fs8
- 08//f/88
- 08/2/88
- 08/d/88
- 0f/I'688
'
'
.
Sh4
1
NT
.