j%.

.

-

. WAY 131988 fde

Docket Nos. 50-348, 50-364

License Nos. NPF-2 and NPF-8

Alabama Power Company

ATTN: Mr. R. P. Mcdonald

Senior Vice President

P. O. Box 2641

Birmingham, AL 35291-0400

Gentlemen:

SUBJECT: NOTICE OF DEVIATION

(NRC INSPECTION REPORT NOS. 50-348/88-13 AND 50-364/88-13)

This refers to the Nuclear Regulatory Commission (NRC) inspection conducted by

G. R. Wiseman on April 4-8, 1988. The inspection included a review of

activities authorized for your Farley facility. At the conclusion of the

inspection, the findings were discussed with those members of your staff

identified in the enclosed inspection report.

Areas examined during the inspection are identified in the report. Within

these areas, the inspection consisted of selective examinations of procedures

and representative records, interviews with personnel, and observation of

activities in progress.

The inspection revealed no violations of NRC requirements. However, certain

activities having safety significance appeared to deviate from a commitment to

the NRC. The deviation and elements to be included in your response are

described in the enclosed Notice of Deviation.

In accordance with Section 2.790 of the NRC's "Rules of Practice," Part 2,

Title 10, Code of Federal Regulations, a copy of this letter and its enclosures

will be placed in the NRC Public Document Room.

The responses directed by this letter and its enclosures are not subject to the

clearance procedures of the Office of Management and Budget as required by tne

Paperwork Reduction Act of 1980, Pub. L. No.96-511.

Should you have any questions concerning this letter, please contact us.

Sincerely,

')

Alan . b t, Chief

Engineering Branch

Division of Reactor Safety

Enclosures: (See page 2)

8805250166 880513 i\

ADOCK 0500

{DR 3rc

.

'., WAY 181988

.. .

Alabama Power Company 2

Enclosures:

1. Notice of Deviation

2. NRC Inspection Report

cc w/encis:

B. M. Guthrie, Executive Vice President

J. D. Woodard, General Manager -

Nuclear Plant

W. G. Hairston, III, Vice President -

Nuclear Support

J. W. McGowan, Manager-Safety Audit

and Engineerir2 Review

S. Fulmer, Supervisor-Safety

Audit and Engineering Review

bec w/encis:

D. Kubicki, NRR

A. Krasopoulos, RI

J. Ullie, RIII

J. Singh, RIV

C. Ramsey, RV

NRC Resident Inspector

DRS Technical Assistant

E. Reeves, Project Manager, NRR

Document Control Desk

State of Alabama

RII RII,.g/

'

RII RI '

GWiseman: ser TConlon HDance GJenkins

05/q/88 05/ll/88 05/gi/88 05//g/88