Text
'
v
..o SEP 9195 In' Reply Refer To:
Docket:
50-285/0L 88-03
~ ')maha Public Power District ATTN:
Kenneth J. Morris, Division Manager -
Nuclear Operations 1623 Harney Street Omaha, NE. 68102 Gentlemen:
SUBJECT:
EXAMINATIONREPORT,FORTCALHOUNSTATION(FCS)
On July 26, 1988, NRC administered examinations to employees of your company who had applied for licenses to operate your FCS facility. At the conclusion of the examinations, the examination keys were provided to facility staff personnel. All applicants passed these examinations.
During examination development, it was determined that lesson plans or other training material for all the systems listed in NUREG-1122 had not been provided to the NRC for examination preparation. Additionally, some questions in the examination bank provided by the facility licensee referenced lesson plans which had not been given to the NRC.
Section 3.c. of the enclosed report provides further details. We expect that the information discussed in Sectior
- . of the enclosed report to be provided no less than 90 days prior to the to,xt scheduled examination.
Should you have any questions concerning this letter, please contact us.
Sincerely, Original Sir,ned B -
A.D. Ucach 3
L. J. Callan, Director Division of Reactor Projects Enclosurc:
Examination Report 50-285/0L 88-03 cc w/ enclosures:
Fort Calhoun Station ATTN:
W. G. Gates, Manager P.O. Box 399 Fort Calhoun, NE 68023 RIV:0LS
- C:0LJ
- 0:DRS
- D:D gdl SLMcCrory JLPellet JLMilhoan L[Cyllan
/ /88
/ /88
/ /88 V 9/88
- previously concurred g
8809190222 880909 f
PDR ADOCK 05000205 l l V
PNV
1 vi In Reply Refer To:
Docket:
50-285/0L 88-03 Omaha Public Power District o
ATTN:
Kenneth J. Morris, Division Manager -
Nuclear Operations 1623 Harney Street Omaha, NE.
68102 Gentlemen:
SUBJECT:
EXAMINATIONREPORT,FORTCALHOUNSTATION(FCS)
On July 26, 1988, NRC administered examinations to employees of your company who had applied for licenses to operate your FCS facility. At the conclusion of the examinations, the examination keys were provided to facility staff personnel. All applicants passed these examinations.
During examination development, it was determined that lesson plans or other training material for all the systems listed in NUREG-1122 had not been provided to the NRC for examination preparation.
Additionally, some questions in the examination bank provided by the facility licensee referenced lesson plans which had not been given to the NRC.
Section 3.c. of the enclosed examination report specifies the requirements that must be satisfied prior to the next examination.
Failure to satisfy these requirements may result in cancellation of the scheduled examination.
Shvold you have any questions concerning this letter, please contact us.
Sincerely, L. J. Callan, Director Division of Reactor Projects
Enclosure:
Examination Report 50-285/0L 88-03 cc w/ enclosures:
Fort Calhoun Station l
ATTN:
W. G. Gates, Manager P.O. Box 399 Fort Calhoun, Nebraska 68023
- RIV:0LS *C:0LS DI f 0 D:DRP SLMcCrory JLPellet JLkl hoan LJCallan
/ /88
/ /88 9/l,/88
/ /88 CPreviously Concurred
(
3 in Reply Refer To:
Docket:
50-285/0L88-03 Omaha Public Power District ATTN:
Kenneth J. Morris, Division Manager -
Nuclear Operations 1623 Harney Street Omaha, Ne 68102 Gentlemen:
SUBJECT:
EXAMINATION REPORT, FORT CALHOUN STATION (FCS)
On July 26, 1988, NRC administered examinations to employees of your company who had applied for licenses to operate your FCS facility. At the conclusion of the examinations, the examination keys were provided to facility staff personnel. All applicants passed these examinations.
During examination development, it was datermined that lesson plans or other training material for all the systems listed in NUREG-1122 had not been provided to the NRC for examination preparation.
Additionally, some questions in the examination bank provided by the facility licensee referrenced lesson plans which had not been given to the NRC.
Section 3.c. of the enclosed examination report specifies the requirements that must be satisfied prior to the next examination.
Failure to satisfy these requirements may result in cancellation of the scheduled examination.
Should you have any questions concerning this letter, please contact us.
Sincerely, L. J. Callan, Director Division of Reactor Projects
Enclosure:
Examination Report 50-285/0L88-03 cc: w/ enclosures (see next page RIV:RIEC:f.t.
dLS A :DRS D:DRP D
SLMcCrBry JLPell JLMilhoan LJCallan 4 O}/88 4/$/88
/ /88
/ /88
q.
o n.
8 Omaha Public Power District,
J. Fluehr, Manager, Station Training Fort Calhoun Station P.O. Box 399 Fort Calhoun, NE 68023 Joe Gasper, Manager of Admin & Training Omaha Public Power District 1623 Harney Street Omaha, Nebraska 68102 Harry H. Voigt. Esq.
LeBoeuf. Lamb, Leiby & MacRae 1333 New Hampshire Avenue, NW Washington, D. C.
20036
. Nebraska Radiation Control Program Director bectoDMB(IE4?.)
bec distrib. by~RIV:
R.D. Martin, RA RPB-DRSS Section Chief (DRP/B)
MIS System RIV File DRP RSTS Operator Project Engineer, DRP/B LFMB Facilities Section P. Milano. NRR Project Manager DRS RRI
.