Text
w c'.*
/
'o UNITED STATES
~,
NUCLEAR REGULATORY COMMISSION
{
.I ADVISORY COMMITTEE ON RE ACTOR SAFEGUARDS W ASHINGT ON, D. C. 20SSS
[
o
'+4,,,,, #
August 27, 1987 PEPORANDUM FOR:
D. Moeller, Chainnan ACRS Subcomittee on Occupational and E61ronmental Protection Systems C
FROM:
Es gne, Senior Staff Engineer
SUBJECT:
OFFSITE EPERGENCY PLANNING AT PILGRIM Attached is a package I requested from the Pilgrim Project Manager on FEMA's self-initiated review and interim finding on the offsite emergen-4 cy planning at Pilgrim. The botton line is that, "FEMA has concluded that Massachusetts offsite radiological emergency planning and prept. red-ress are inadequate to protect the public health and safety in the event of an accident at the Pilgrim Nuclear Power Station. Because of the changed circumstances discussed in the report, the finding of adequacy contained in FEMA's previous interin finding no longer applies and that interim finding is hereby superseded."
Pilgrim is in the refueling mode of operation and plans to startup in early November 1987.
As per your suggestion. I will pursue this matter further with Dr. R.
Bellamy of Region 1.
I will keep you abreast on this matter.
Attachment:
As stated cc: With
Attachment:
ACRS Members:
C. Mark G. Reed F. Remick C. Wylie M. Steindler With Cover letter only:
ACRS Members 4
i i
8e09160091 Boos 23 J$NS
-198 PDR (1
.