Insp Repts 50-338/88-09 & 50-339/88-09 on 880418-22.No Violations or Deviations Noted.Major Areas Inspected: Radiological Effluents & Radiological Environ Monitoring
ML20154D152
Person / Time
Site: North Anna  Dominion icon.png
Issue date: 05/05/1988
From: Kahle J, Marston R
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To:
Shared Package
ML20154D150 List:
References
50-338-88-09, 50-338-88-9, 50-339-88-09, 50-339-88-9, NUDOCS 8805190065
Download: ML20154D152 (7)


See also: IR 05000338/1988009

Text

- - - - - - - - - - - - - - - . _ - - - - - - - -

. _ - -

, , .

. . . . . .

.

'

pa sseg

.

.

[

t'

UNITED STATES

.!

j

NUCLEAR REGUL ATORY COMMISSION

e

REGION 11

[

101 MARIETTA ST., N.W.

ATLANTA, GEORGIA 30323

,,,,,

MAY 0 91998

Report Nos.: 50-338/88-09 and 50-339/88-09

Licensee: Virginia Electric and Power Company

Richmond, VA 23261

Docket Nos.: 50-338 and 50-339

License Nos.: NPF-4 and NPF-7

'

Facility Name: North Anna 1 and 2

Inspection Conducted: April 18-22, 1988

Inspecor[

(M

$

8

R/ . 7tarston

Date Sitjned

~

'

I

/

/

Approved by:

w /[ ] M M

.t

/7

J, 5. Kahle, Section Chief

Date Si'gned

Q}ylsionofRadiationSafetyandSafeguards

SUMARY

Scope:

This routine, unannounced inspection was conducted in the area of

radiological effluents and radiological environmental monitoring.

Results: No violations or deviations were identified.

G805190065 0805C4

PDR

ADOCK 05000338

Q

DCD

-

- - - - -

-.

__ ---------- -- - ---- ----

--- ---- -------- -- -------_-- ___

,

,

'

'

.

.

REPORT DETAILS

l

1.

Persons Contacted

,

Licensee Employees

-

W. Barnes, III, Assistant Supervisor, Health Physics

E. Dreyer, Supervisor Health Physics - Technical Services

  • R. Enfinger, Assistant Station Manager (0perations & Maintenance)
  • S. Hamill, Supervisor, ISI Engineering
  • L. Hartz, Instruments Supervisor
  • D. Heacock, Superintendent of Technical Services
  • J. Leberstien Engineer

M. Marino, Assistant Instrument Supervisor - Unit 2

  • D. Roth, Nuclear Safety & Licensing Engineer
  • E. Schnell, Corporate Health Physicist
  • A. Stafford, Superintendent Health Physics
  • G. Swann, Senior Engineering Technician

C. Swope, Staff Quality Specialist, Programs

  • F. Teminella. Supervisor - Quality

Other licensee employees contacted included technicians, security force

members, and office personnel.

NRC Resident inspector

L. King

.

  • Attended exit interview

2.

Exit Interview

The inspection scope and findings were summarized on April 22, 1988, with

those persons indicated in Paragraph 1 above. The inspector described the

areas inspected and discussed in detail the inspection findings.

No

dissenting comments were received from the licensee.

The licensee did not

identify as proprietary any of the materials provided to or reviewed by

the inspector during this inspection.

3.

Licensee Action on Previous Enforcement Matters

This subject was not addressed in the inspection.

4.

Audit (80721,84723,84724)

Technical Specification 6.5.3.1 requires that the Quality Assurance (QA)

Department audit station activities to include:

.

-.

I

-

.

,

2

The conformance of facility operatMn to provisions contained within

the Technical Specifications and applicable licensee conditions at

least once per 12 months;

The radiological environmental monitoring program and the results

I

thereof at least once per 12 months;

The Offsite Dose Calculation Manual (ODCM) and implementing

,

j

procedures at least once per 24 months;

'

The Process Control Program and implementing procedures for

processing and packaging of radioactive wastes at least once per 24

'

months; and

The performance of activities required by the Quality Assurance

Program to meet the provisions of Regulatory Guide 1.21. Revision 1,

June 1974, and Regulatory Guide 4.1, Revision 1. April 1975, at least

once per 12 months

!

The inspector discussed the audit program with licensee representatives

and reviewed the following audits conducted by the QA Department:

'

~

N-87-04

Health Physics Dose Control and Administration August 15,

,

1987, this audit included Radiation Monitor Alarm / Trip setpoints and

calibration of count room equipment;

i

N-87-05, Radiological Environmental Monitoring, conducted April 14 -

July 2,1987.

This audit included a finding on calibration and

4

maintenance of air sampler kits, which was subsequently closed;

,

i

l

N-87-12, Process Control Program, conducted July 20 - October 21,

'

1987; and

N-87-15, Offsite Dose Calculation Manual, conducted August 31 -

November 13, 1987.

The audits appeared tn be thorough and comprehensive, and response,

r

followup, and closecut were conducted in a timely manner.

l

No violations or deviations were identified.

,

j

5.

Procedures (80721, 84723, 84724)

Technical Specification 6.8.1 requires that written procedures be

estabiished, implemented and maintained covering in part the activities

referenced below:

l

The applicable procedure recorrnended is ,,ppendix "A" of Regulatory

Guide 1.33 Revision 2 February 1978;

'

!

process Control Program inplementation;

'

I

. _ _

- . - _ _ _ _ _ _ _ - - _ _ - _ _ _ _ _ , . .

. _ _ _

.. .

.-

..

. . _

_

.

.

'

.

.

,

3

ODCM implementation; and

Quality Assurance Program for e' .Jent and environmental monitoring,

using the guidance in Regulatory Juide 1.21. Revision 1, June 1974,

!

and Regulatory Guide 4.1, Revision 1, April 1975.

The inspector selectively reviewed Health Physics Procedures in the

following areas:

HP-REMM.

The ten procedures in this group constitute the REM Manual

which defines the Radiological Environmental Monitoring Progran

HP-00CM.

These fourteen procedures plus Appendices constitute the

00CM.

Health Physics Procedures covering calibration, opera *. ion , and

performance checks of count room equipment; liquid and gaseous

radwaste sampling and analysis; radwaste release, release records,

and dose assessment; effluent monitor setpoints; and accidental,

unplanned or uncontrolled radwaste release.

The inspector also

selectively reviewed Instrument Calibration Procedures specified for

effluent monitor calibration and functional checks and meteorological

instrumentation calibration and functional checks.

The inspector determined through selective reviews of the procedures and

discussions with licensee representatives that the requirements of the

Technical Specifications appeared to have been met.

Licensee

representatives stated the corporate Health Physics was rewriting

performance and calibration procedures to ensure conformity with the

Radiation Protection Plan.

-

No violations or deviations were identified.

6.

Radioactive Effluent Monitoring Instrumentation (84723, 84724)

Technical Specifications 3.3.3.10 (Unit 1) and 3.3.3.9 (Unit 2) require

radioactive liquid and gaseous effluent monitoring instrumentation

channels to be operable with their alarm / trip setpoints set in accordance

with the ODCM.

Technical Specification Tables 4.3-13 (Unit 1) and 4.3-12

(Unit 2) establish frequencies for channel checks source checks, channel

calibrations, and channel functional tests for radioactive liquid effluent

monitoring instrumentation, and Tables 3.3-14 (Unit 1) and 3.3-13 (Unit 2)

established frequencies for channel checks, source checks, channel

i

calibrations, and channel functional tests for radioactive gaseous

effluent monitoring instrumentation.

The inspector selectively reviewed calibration and channel check records

for liquid and gaseous effluent radiation monitoring systems.

Calibratiens and checks appeared to have been done at intervals required

by Technical Specifications and procedures.

The inspector noted several

.

.

.

1

,

-

-

,

,

4

f

liquid and gaseous effluent monitors during a tour of the plant.

The

monitoring systems appeared to be properly installed and maintained.

'

No violations or deviations were identified.

7.

CountRoomInstrumentation(84723,84734)

The inspector toured the count room, discussed the equipment and

procedures with licensee representative and examined calibration and

functional check records for the instruments.

The counting room is equipped with three HPGe Ortec detector systems with

Nuclear Data MCA 6700 analysis and display, one Beckman LS-100C Liquid

Scintillation system, and two PC-5 HMC Proportional counters.

Licensee

representatives stated that an additional gamma spectroscopy system and a

PC-4 proportional counter were maintained in the Plant Training Center.

,

i

The inspector reviewed the records for the count room instruments and

verified that calibrations and functional checks appeared to have been

.

done at frequencies specified in appropriate procedures.

l

-

No violations or deviations were identified.

l

,

t

8.

Radioactive Liquid Waste (84723)

l

'

Technical

Specification 3/4.11.1 establishes upper limits for

4

,

concentrations of radioactive material in liquid effluents.

The inspector

selectively reviewed release records for the period June 1987 to

r

April 1988; which included release reports, abnormal release reports, dose

assessment records, and dose projections.

All releases reviewed were

'

within Technical Specification limits.

No violations or deviations were identified.

9.

RadioactiveGaseousWaste(84724)

'

Technical

Specification 3/4.11.2 establishes upper limits for

concentration of radioactive material in gaseous effluents. The inspector

'

selectively reviewed release records for the period from June 1987; to

April 1988; which included release reports, abnormal release reports, dose

assessment records, and dose projections.

All releases reviewed were

within Technical Specification limits.

!

No violations or deviations were identified.

10. Radiological Environmental Monituring (80721)

a.

Technical Specification 3.12.1

requires

the

radiological

i

environmental monitoring program to be conducted as specified in

-

Table 4.12.1.

The Table specifies:

,

4

a

i

'

-

.

. - _ -

_ _ _ _ _ _ , _ _

__

_ . . , ,

_ _ . _ _ ,

- - . _ - _ - _ ,

-

_ _ . .

,

,

'

'

.

.

5

'

Exposure Pathway and/or Sample;

Number of Samples and Sample Locations;

Sampling and Collection Frequency; and

Type and frequency of Analysis

The licensee implements the Technical Specification requirements

through the REM Manual and the ODCM.

The inspector and a licensee representative visited five

environmental sampling sites where collocated NRC and licensee

thermoluminescent dosimeters (TLDs) were located.

Licensee air

samplers were located at three of the stations and State TLDs were

collocated at two of the stations.

Licensee representatives stated that all environmental sample's were

shipped to a contractor for analysis.

The inspector selectively

reviewed environmental analysis reports for the period from July 1986

through January 12, 1988.

The inspector noted that the contractor

listed those samples not taken due to nonavailability. The inspector

determined that sampling and analyses appeared to have been done at

the required frequencies, and that no results exceeded the Action

Levels specified in Technical Specification Table 4.12-2.

b.

Technical Specifications 3/4.12.2 requires a land use census to be

conducted during the growing season at least once per 12 months. The

inspector reviewed the results of the census conducted in July 28-30,

1987.

The census provided the data specified in the Technical

Specification.

c.

Technical Specific

lon 3/4.3.3.4 requires that the meteorological

monitoring instrumentation channels shown in Technical Specification

Table 3.3-8 be operable, and that each of these channels be

demonstrated operable by performance of the channel checks and

channel calibration at the frequencies shown in Technical

Specification Table 4.3-5.

The inspector eviewed calibration records for the primary and backup

,

meteorological systems which showed that the systems were calibrated

'

in April 1988.

No violations or deviations were identified.

11. Collocated TLDs (25022)

The inspector verified the location of collocated NRC and licensee TLDs

and collected the data required by the Temporary Instruction.

No violations or deviations were identified.

L

__ - - - - - _

,

-

.

,

,

6

12. Environmental Reports (80721)

a.

Technical Specification 6.9.1.8 requires the submittal of an annual

Radiological Environmental Surveillance Report.

The inspector

reviewed the report for calendar year 1986.

Generally, the resultu

were as expected with no trends noted. Naturally occurring activity

was observed in sample media in the expected activity ranges.

Fission-related isotopes resulting from the Chernobyl accident were

detected in the vicinity of the plant from early May through June.

At other times, occasional samples showed the presence of man-made

j

isotopes, which were discussed in appropriate parts of the report.

l

These activities were at very lcw concent:ations and had no

significant dose consequence.

No violations or deviations were identified.

13.

Followup of Significant Events (93701)

During the period of December 1-5, 1986, a control room habitability

survey was conducted at North Anna Units 1 and 2 by members of NRC (NRR

and Region II) and NRC consultants.

During this evaluation, flow tests

were conducted on the control room emergency ventilation system. The flow

tests showed that all four subsystems had flow rates in excess of the flow

rates specified in Technical Specification 3.7.7.

The NRC determined that

these high ficu rates could result in control room personnel receiving

doses greater than 5 Rem during an accident due to shorter iodine

residence times in the charcoal adsorber beds.

As a result of this

finding, the licensee issued Licensee Event Report (LER) 86-019-00.

According to the LER, the cause of the incident was inadequate post

maintenance testing af ter filter (demister) cleaning.

No cleaning

procedure existed to ensure post maintenance testing.

The inspector verified that procedures had been issued (PM-M-10-Fl./R-3 and

PM-M-20-FL/R-3) which provided for cleaning the demisters and performing

Periodic Tests (1-PT-76.12A, 1-PT-76.12B, 2-PT-76.12A, and 2-PT-76.12B) to

perform post maintenance testing on the control room emergency ventilation

system.

(Closed) LER 86-019-00.

,

,. ..

..

.