Ack Granting of Enforcement Discretion to Plant from Provisions of Tech Spec 3.6.5.1, Secondary Containment Integrity-Operating, Per .Enforcement Discretion Granted by NRC on 880826
ML20154C359
Person / Time
Site: River Bend Entergy icon.png
Issue date: 09/02/1988
From: Callan L
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
To: Deddens J
GULF STATES UTILITIES CO.
References
NUDOCS 8809140332
Download: ML20154C359 (2)


Text

_ _ _ _

~~ ~

SEP 2 1988 In Reply Refer To:

Docket: 50-458 Gulf States Utilities ATTN: Mr. James C. Deddens Senior Vice President (RBNG)

P.O. Box 220

) St. Francisville Louisiana 70775 l

l Gentlemen:

This acknowledges the granting of enforcement discretion to River Bend l Station from the provisions of Technical Specification 3.6.5.1, "Secondary Containment Integrity-Operating." Your letter (RBG-28571) to this office, dated August 26, 1988, provides your basis for the enforcement discretion request.

Enforcement diccretion was granted by NRC Region IV on August 26, 1988, allowing River Bend Statio.1 to remain in Hot Standby (Mode 3) for an additional 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> beyond that alloweo by the action requirements.

Sincerely, Original Signect By:

A.B. BEACH I L. J. Callan, Director Division of Reactor Projer.ts cc: j Gulf States Utilities ATTN: J. E. Booker, Manager-River Bend Oversight P.O. Box 2951 Beaumont, Texas 77704 Gulf States Utilities ATTN: Les England, Director Nuclear Licensing - RBhG P.O. Box 220 St. Francisvillo, Louisiana 70775 Louisiana State University, Governtrent Documents Departnent Louisiana Radiaticn Co trol Program Director RIV:AC:PSC, LPG llen jh EFord .df 8/3 /S8 L

4/1/08 /p j

8809140332 eso902 PDR ADOCK 05000458 P PDC

Gulf States Utilities bec to DM8 (IE01) bec distrib. by RIV:

DRP RRI R. D. Martin, RA SectionChief(DRP/C)

Lisa Shea, RM/ALF MIS System RPB-DRSS RSTS Operator Project Engineer DRP/C RIV File W. Paulsca, fiRR Project Manager DRS r

I r

I i

t i

l J

1 2

l