Order Extending Const Completion Dates for CP CPPR-107 to 890501 & 920101,respectively
ML20154A875
Person / Time
Site: Limerick Constellation icon.png
Issue date: 05/03/1988
From: Varga S
Office of Nuclear Reactor Regulation
To:
PECO ENERGY CO., (FORMERLY PHILADELPHIA ELECTRIC
Shared Package
ML20154A867 List:
References
NUDOCS 8805160218
Download: ML20154A875 (2)


Text

.

7590-01 PHILADELPHIA ELECTRIC COMPANY LIMERICK GENERATING STATION, UNIT NO. 2 DOCKET N0. 50-353 ORDER EXTENDING CONSTRUCTION COMPLETION DATE Philadelphia Electric Company is the holder of Construction Permit CPPR-107 issued by the Commission on June 19, 1974. This permit authorizes construction of the Limerick Generating Station, Unit No. 2, presently under construction at the Company's site on the Schuylkill River, near Pottstown, in Limerick Township, Montgomery County, Pennsylvania.

On August 13, 1987, Philadelphia Electric Company (Applicant) filed a request pursuant to the Code of Federal Regulaticrs, Title 10, Part 50, Section 50.55(b) for an extension of the construction completion dates for tnis unit.

The specific request was that the earliest and latest completion dates specified in Construction Permit No. CPPR-107 for Limerick it ' be extenc'ed to May 1,1989 and January 1,1992, respectivelv.

The change in the schedule for completien of the construction of Unit 2 results from suspension of construction by Applicant in accordance with the terms of an order issued by the Pennsylvania Public Utility Commission (PaPUC) on December 23, 1983.

Such order directed the Applicant to:

(1) suspend construction of Unit 2 pending operation of Unit 1; or (?) cancel Unit 2 or (3) continue construction of Unit 2 solely with internally generated funding. Applicant advised the PaPUC on January 24, 1984 that of the choices available, it had suspended construction of Unit 2 pending operation of Unit 1.

As a result of this action all activities at the Unit 2 construction site were suspended during the period from January 1, 1984 to February 1, 1986 except essential activities required to protect the site, the public and workers and actions required to allow a prompt resumption of construction.

8805160218 880503 PDR ADOCK 050 3

  • C e The NRC staff has concluded that good cause has been shown for the delay, the extension is for a reasonable period, and that this action involves no significant hazards consideration, the bases for which are set forth in the staff's evaluation of the request for extension dated May 3, 1988 The NRC staff has prepared an environmental assessment and finding of no significant impact which was published in the FEDERAL REGISTER on January 14, 1988 (53 FR 970).

Pursuant to 10 CFR 51.32, the Comission has determined that extending the construction completion date will have no significant impact on the environment.

The applicant's letter dated August 13, 1987, and the NRC staff's letter and safety evaluation on the request for extension of the construction permit, l

dated May 3, 1988

, are available for public inspection at the Comission's Public Document Room, 1717 H 5treet, N% Washington, D.C.

20555 and the local l

Public Document Room, Pottstown Public Library, 500 High Street, Pottstown, Pennsylvania 19464 1

It is HEREBY ORDERED THAT THE earliest and latest completion dates for 1

1 CPPR-107 be extended to May 1, 1989 and January 1, 1992, respectively.

Dated at Rockville, Maryland, this 3rd day of May 1988.

FOR THE NUCLEAR R GULATORY COMBISSION b

hve bia,be Division of Reactor P jects I/II Office of Nuclear Reactor Regulation