rhQ SOUTH CAROLINA ELECTRIC & GAS COMPANY VIRGlL C. SUMMER NUCLEAR STATION NUCLEAR OPERATIONS Th FORMAT ON Ol\\ LY l
FIRE EMERGENCY PROCEDURE FEP-1.0 FIRE EMERGENCY PROCEDURE SELECTION REVISION 10 i
(M SAFETY RELATED
/=
3 25 W
~
CflSCIPfdNE1 SUPERVISOR DATE o $ b $ldb.
3f)5'id k
APPRfVAL AUTHORITY DATE /
RECORD OF CHANGES
$TiTR CHEE NNE DA R
CH E
e 64 -n-sn CONTINUOUS USE Continuous Use of Procedure Required.
Read Each Step Prior to Performing.
9809295293 980924 DR ADOCK 0500 3 5
NUCLEAR OPERATIONS SAP-139 ATTACHMENTIV l
PAGE 1 OF 3 COPY NO*
REVISION 16 i-PROCEDURE DEVELOPMENT FORM-A CHANGEF QP 4/ZbKr EP 63MP 1.
DATE: M = \\0" %
PROC. # b~i -M REV.#
0 CHG.$ COMu.#
)
TITLE: T-TT f k%tft 2:ncOCY UL-% NIT C"T"CDd NEW PROC CHANGE _g, PERMANENT _E:
SAFETY RELATED M
REVISION RESTRICTED FROM TO QUAUTY RELATED NON-SAFETY RELATED W
MY h
Q,,,,f
%M ty %
z.m cA-g ct-B.s-REASON FOR CHANGE:
h Ybk F h et(
Onginator llL WILL THIS REVISION / CHANGE /NEW PROCEDURE:
- YES NO N/A 1.
Result in significant increased personnel radiation exposure? (ALARA review) 2.
Result in a release of effluents to the Environrnent?
3.
Degrade the effectiveness of the Rad:stion Ernergency Plan?
4 4.
Degrade the safeguards effectiveness of the Physical Security, Safeguards Contingency or Training and Qualification Plans?
- If any question 1 through 41s answered "YES", refer to appropriate section of procedure for direction, REQUIRED REVIEW AND COMMENT:
s q OPS
[) NL&OE i ) CHS
}GMNPO gb V
,) PAS
) NPS i MNT
'i GMES igililine Supennsor
~Date
( MNTS i i
HPS i
-GMNS$
ll QA L)TS
( DE V,QRf bi
'TDs? Ktc/7/Jfe6 i
/
IV. 10CFR50.59 SCREENING REVIEW / SAFETY EVALUATION (REQUIRED C EXEMPT KPSRC SUPPORTING DOCUMt.d:Y YN e
6isciplir((Sg orconcurrence V.
TEMPORARYAPPROVAL:
QUALIFIED REVIEWER DATE QA REVIEW DATE TELECON BY TELECON BY SHIFT SUPERVISOR DATE FINAL APPROYAL REQUIRED BY: DATE VIL P/ CAP ACC ABLE VL DISOPLINE SUPERVISOR FINAL REVIEW:
C YES
/
NL&OE Date TRAINING REQUIRED? YES _ NO _
M; 5 RESP.MGR.
Date IF YES.PRIORTO PROCEDUREIMPLEMENTATION? YES
/#f*4 Vill FINAL QA REVIEW ble)
P/ CAP AFFECTED? YES NO
/# Yhs /kg Date
/*/[13 QA Concurrence p-COMMENTS RESOLVED:
7
/Disciplisip46pervisor
&} $/YY I
Appropl/ Concurrence
/
/ Date X.
PSRC REVIEW:
A.
REVIEWED BY:
B.
PSRC COMMENTS RESOLVED:
PSRC Chairrnan Date Responsible Manager Date COMMENTS:
YES _ NO _
/
PSRC Chairrnan 6a_te
FEP-1.0 s
PAGEi REVISION 10 TABLE OF CONTENTS SECTION PAGE 1.0 PURPOSE
'1 2.0 INITIAL CONDITIONS 1
3.0 OPERATOR ACTIONS 2
4.0 REVISION
SUMMARY
3 ATTACHMENTS Fire Procedure / Attachment Cross Reference Attachment I i
Fire Procedure Step Substitutions 1 O
O
s.
FEP-1.0 1.0 PURPOSE This procedure,provides direction in determining which fire zone is affected based on information coming in from the plant. It also directs operations personnel to the correct procedure or attachment once the exact f;re zone is determined.
I 2.0 INITIAL CONDITIONS 2.1 A fire within the protected area has been reported to the Control Room or has alarmed on the Simplex Fire System.
2.2 Fire brigade is on the scene and is providing information as to the exact location and the severity of the fire.
2.3 The fire is of such a nature (due to magnitude, location, or equipment involved) that there is concern about maintaining the ability to safely control the plant.
O O
PAGE 1 OF 3
l.
4, FEP 1.0 REVISION 10 V
CAUTION 3.0 a.
Many assumptions were made when the Fire Emergency Procedures (FEP's) were written. The major assumptions were.
1)
No other accident or failure occurs with the fire except that caused by the fire.
2)
All equipment was operable or replaced by swing components. All equipment starts and functions or can be locally operated.
3)
All actions could be performed as written. However, in some cases, access to certain equipment may be hampered by fire. It l
may be necessary to delete steps in order to avoid personnel injury. These cases should be evaluated by the Shift Supervisor.
b.
If the assumed plant conditions do not exist, the situation must be evaluated. Additional Operator actions may be required to maintain the plant in a safe condition. Some equipment may be operated from a location other than that listed.
3.0.
OPERATOR ACTIONS l
3.1 If the exact fire zone is not known, determine from personnel in the plant the exact location of the fire.
a.
Building and elevation.
b.
Area (East, West, North or South).
c.
Room number.
d.
Equipment affected or in the area.
NOTE 3.2 E 023-000 series drawings, located in the control room, should be used to determine the exact fire zone when fire zone number is not known.
3.2 Determine the exact fire zone in which the fire is located.
l 3.3 Use Attachment I to determine the correct procedure and Attachment il Part Number.
1 PAGE 2 OF 3
l.
4, FEP 1.0 REVISION 10 V
NOTE 3.4 Part Numbers which are bold and underlined contain immediate Actions and must be implemented promptly.
3.4 Implement the procedure and Attachment ll Part Number determined above.
4.0 REVISION
SUMMARY
4.1 Incorporated changes A through F.
4.2 Updated format and font.
4.3 Corrected typographical errors.
4.4-Converted to Word.
O i O PAGE 3 OF 3
FEP-1.0 ATTACHMENTI 1
PAGE 1 OF 6 REVISION 10 FIRE PROCEDURE / ATTACHMENT CROSS REFERENCE I
FIRE ZONE DRAWING FEP MODIFIED BY ATTACHMENT ll PART NUMBER E-023-CRS A RO SE AB IB (UPPER)
CB-1.1 018,020 2.0 1
1 1
1 1
CB-1.2 019,020 2.0 1
1 1
1 1
CB-2 018 2.0 2
43 44 50
- C B-3.1 018,020 2.0 CB-3.2 020 2.0 CB-4 019,020 4.0 CB-5 018 3.0 3,4 CB-6 018,019,020 4.0 CB-7 018,020 2.0 5
CB-8.1 018,020 2.0 0-CB-8.2 018,019,020 2.0 CB-8.3 018,019 2.0 CB-8.4 019,020 2.0 0-K*
CB-8.5 019 2.0 CB-9 018,020 2.0 CB-10 018,019,020 3.0 6,7,8 42 43 44 50,51 47 CB-12 018,020 2.0 5,6 40 43 44 50 54 CB-14 018 2.0 CB-15 019,020 4.0 CB-17.1 018,020 4.0 49 CB-17.2 018,020 4.0 49 CB-17.3 018,020 4.0 49 CB-18 018,020 3.0 6
41 42 43 CB-20 018,020 2.0 9
CB-21 018 2.0 CB-22 018,020 3.0 10 CB-23 018,020 2.0
~~
CB-24 019 2.0 0
i FEP 1.0 ATTACHMENTI PAGE 2 OF 6 REVISION 10 FIRE PROCEDURE / ATTACHMENT CROSS REFERENCE FIRE ZONE DRAWING FEP MODIFIED BY ATTACHMENT 11 PART NUMBER E-023-CRS A RO SE AB IB (UPPER)
AB-1.1.1 002 3.0 11 AB-1.1.2 002 2.0 4
AB-1.1.3 002.016 3.0 12 AB 1.2 002 3.0 11 AB-1.3 002 2.0 AB-1.4 004,016 SEE PART H
13 AB 1.5 003 2.0 AB-1.6 003 SEE PART H
13 AB-1.7 003 3.0 AB-1.8.1 003,004 3.0 14 AB-1.8.2 003,004 2.0 15 AB-1.9 004,016 SEE PART g
16 AB-1.10 005,006,016 3.0 17
__ AB-1.11 004,005,006 2.0 AB-1.12 004,005,006 2.0 AB-1.13 005 2.0 AB-1.14 005 2.0 AB-1.15 005,006 3.0 AB-1.16 005.006 2.0 AB-1.17 005,006 2.0 AB-1.18.1 008,009,016,02 3.0 18 41, 52 1
AB-1.18.2 008,009,016 2.0 19 AB-1.19 008 2.0 AB-1.20 008,021 2.0 l
AB-1.21.1 011 3.0 41 42 AB-1.21.2 011,016 2.0 20 41 AB 1.22 011 2.0 AB 1.23 011 2.0 AB-1.24 011 2.0
FEP-1.0
{
ATTACHMENT l PAGE 3 OF 6 REVISION 10 FIRE PROCEDURE / ATTACHMENT CROSS REFERENCE FIRE ZONE DRAWING FEP MODIFIED BY ATTACHMENT 11 PART NUMBER E 023-CRS A RO SE AB IB 1
i (UPPER)
AB-1.25 011 2.0 AB-1.26 011 2.0 AB-1.27 011 2.0 AB-1.28 011.014,016 2.0 i
AB-1.29 011 2.0 10 AB-1.30 014,016 2.0 AB-1.31 014.016 2.0 FH-1.1 005 3.0 FH-1.2 005 2.0 FH-1.3 005,008 2.0 FH-1.4 005,008 2.0 0
R B-1.1.1 005,016 2.0 21 4_0 54 RB 1.1.2 005,015,016 3.0 22 40 R B-1.2.1 005,008,011, 2.0 42 013,015.016 RB-1.2.2 008,011,013, 3.0 22 015 RB-1.2.3 008,011,013, 2.0 40, 015 RB 1.3.1 008 2.0 RB-1.3.2 008,016 2.0 23 42 54 RB-1.3.3 008,015,016 3.0 22 RB 1.4.1 008,011,013, 2.0 23 015.016 RB 1.4.2 011,013,015, 3.0 22 016 RB-1.5 015,016 2.0 IB-1 007.017 2.0 IB-2 007,017 3.0 4
i IB-3 007,017 3.0 24 55 18 4 007,017 2.0 25 55 1B-5 007 3.0 26 56 IB-6 007,017 2.0 4
1
~
j FEP-1.0 i
ATTACHMENTI i
PAGE 4 0F 6 l
REVISION 10 FIRE PROCEDURE / ATTACHMENT CROSS REFERENCE 4
I i
)
FIRE ZONE DRAWING FEP MODIFIED BY ATTACHMENT 11 PART NUMBER l
E-023-CRS A RO SE AB IB (UPPER)
)-
1B-7.1 007 3.0 IB-7.2 007 SEE PART 27 1
27 1B-7.3 007 2.0 I
IB 8 007 SEE PART 27 l
27
{
IB 9 007 2.0 j
IB-10 007,017 2.0 5
l 18-11 007 2.0 5,7 l
IB-12 010 2.0 7
i 1B 13 010 SEE PART 28 j
28 IB-14 010 3.0 7
42
- I IB-15 010 2.0 5
45 IB-16 010,017 3.0 IB-17 010,017 3.0 29 47 51 18-18 010,017 3.0 IB-19 010 017 2.0 IB-20 012,017 3.0 6
42 M 4_4 50 18 21.1 012,017 3.0 42 j
l 18 21.2 012,017 3.0 42 i
18 22.1 007 2.0 30 44 50 f
18-22.2 010,017 2.0 30 44 50 IB 23.1 007,017 3.0 4
IB-23.2 007,017 3.0 i
1B-23.3 010.017 3.0 18-24 010,017 3.0 IB-25.1.1 007 3.0 31 i
!B-25.1.2 007,017 2.0 32 M 43 44_
50 55 18-25.1.3 007,017 3.0 33 45 M 48 53 58 i
IB-25.1.4 007 3.0 31
)
IB-25.1.5 007 SEE PART 34 43 44 CASE 1-50 CASE 11-58 34 CASE ll 53 4
(
I FEP-1.0 ATTACHMENT I PAGE o LF 6 g
REVISION 10 FIRE PROCEDURE / ATTACHMENT CROSS REFERENCE FIRE ZONE
~ iAWING FEP MODIFIED BY ATTACHMENT 11 PART NUMBER E-023-CRS A RO SE AB IB (UPPER) 18-25.2 007 3.0 31 18-25.3.1 007 3.0 22 46 50 IB-25.3.2 007 3.0 22 4_6 50 18-25.4 010,016 2.0 35 M 41 50 IB 25.5.1 010 2.0 3
M 50 18 25.5.2 010 3.0 31 50 18-25.6.1 010,017 3.0 36 43 45 47 50,51 57 18 25.6.2 010,017 3.0 36 4_3 45 47 50,51 57 IB-25.7 010,017 3.0 36 43 4_547 50,51 57 1B 25.8 008,016 2.0 37 41 50 10-25.9 011,016 3.0 38 41 42 18 26 010 3.0 18-27 010 2.0 50 DG 1.1 007,017 3.0 DG 1.2 010,012,017 3.0 DG 2.1 007 2.0 DG 2.2 010.012 2.0 YD-1 005 2.0 YD 2.1 010 3.0 YD 2.2 010 2.0 M H-2.1 023 2.0 MH 2.2 023 3.0 SWPH-1 023 3.0 SWPH-2 023 SEE PART 39 CASE Il 59 39 SWPH 3 023 2.0 SWPH-4.1 023 2.0 60 SWPH 4.2 023 2.0 60 SWPH-5.1.1 023 l
3.0 0
FEP 1.0 6
ATTACHMENT I PAGE 6 OF 6 REVISION 10 FIRE PROCEDURE / ATTACHMENT CROSS REFERENCE FIRE ZONE DRAWING FEP MODIFIED BY ATTACHMENT 11 PART NUMBER E-023-CRS A RO SE AB IB (UPPER)
SWPH 5.1.2 023 2.0 SWPH 5.1.3 023 SEE PART H
CASEIl-39 59 SWPH 5.2.1 023 3.0 SWPH 5.2.2 023 2.0 SWPH 5.2.3 023 SEE PART H
CASE 11-39 59 SWPH 6 023 2.0 TB 1 007 3.0 8
47 51 l
i 4
h i
'v i
FEP-1.0 6
ATTACHMENT ll PART1 PAGE 1 OF 13 REVISION 10 CONTROL ROOM SUPERVISOR Page 1 of 2 NOTE This Part applies to fire in Zones CB-1.1 and CB-1.2.
1.
Substitute the following equipment throughout FEP-2.0 and FEP-2.1:
.ljge Instead Of FE NI33 NI-31 Reactor Power XVT08100-C5 XVT 8112 Seal Return isolation Local Manual Remote IPV 2010 Local Manual Remote IFV-3556 Local Manual Remote XSW1DB Normal and Emerg incoming Breakers, and Diesel Generator B Control NOTE 2 and 3 Much Train B equipment is affected by this fire. XSW1DB should be rapidly de-energized locally, stripped, then should be energized from Diesel Generator B to power NI-33. Diesel Generator B Control will be local.
2.
Verify the following conditions are met:
a.
The Intermediate Building Operator has reported Diesel Generator B in LOCAL.
b.
The Auxiliary Building Upper Operator has reported that XSW1DB1 Main incoming Breaker is open.
c.
The Shift Engineer has reported XSW1DB and XSW1DB2 are stripped.
3.
Have the Shift Engineer energize XSW1DB from Diesel Generator B.
O
FEP-1.0 6
ATTACHMENT 11 PART1 PAGE 2 OF 13 REVISION 10 CONTROL ROOM SUPERVISOR PAGE 2 OF 2 4.
Within eight hours, have Maintenance install temporary ventilation in place of the following fans:
a.
XFN0133, AUX BLDG MCC-SWGR ROOM COOLING UNIT FAN (AB-463).
b.
XFN0076, ESF SWGR ROOM 1DB AH UNIT SUPPLY FAN (IB-455).
c.
XFN01068, SPEED SWITCH ROOMS AH UNIT B SUPPLY FAN (1B-455).
O O
FEP-1.0 ATTACHMENT ll PART1 PAGE 3 OF 13 REVISION 10 A NUCLEAR REACTOR OPERATOR f
Page 1 of 2 i
_ NOTE 1.
Step 1 is an immediate Action.
2.
This Part is to be performed in conjunction with the duties specified by FEP 2.0.
3.
This Part applies to fire in Zones CB-1.1 and CB-1.2.
1.
De-energize the following by opening their respective Disconnect Switches located inside the Main Control Board:
Sub Panel 19A (XCP-6112):
a.
Switch Valve Number 1)
DS-3 1-XVM-2801 A 1-XVM 2801B 1 XVM 2801C A-XVT-2869A A-XVT 2869B 1
A-XVT-2869C 2)
DS-4 PCV-2000A 3)
DS 5 PCV-2010A 4)
DS-6 PCV-2020A 5)
DS-32 IPV-445A 6)
DS-33 IPV-445B O
j FEP-1.0 ATTACHMENT ll O
PART1 PAGE 4 OF 13 REVISION 10 A NUCLEAR REACTOR OPERATOR Page 2 OF 2 b.
Sub Panel-19B (XCP-6113):
Switch Valve Number 1)
DS-7 PCV-2000B 2)
DS 8 PCV-2010B 3)
DS-9 POV 2020B 4)
DS-10 XVT 8153 5)
DS-11 XVT-8154 6)
DS-12 2-XVM-2801 A 2-XVM-2801B 2-XVM 2801C B-XVT-2869A B-XVT-2869B B-XVT-28690 7)
DS-13 XVT-8145 8)
DS 31 IPV-444B 2.
Do not remove power from XSW1DB per FEP-2.0 because it is deenergized locally.
O f
FEP-1.0 ATTACHMENT ll 4
PART1 PAGE 5 0F 13 REVISION 10 i
4 i
SHIFT ENGINEER Page 1 of 5 fiQTg This Part applies to fire in Zones CB-1.1 and CB-1,2.
1.
Obtain keys, radio and flashlight from the Control Room and oroceed to XSW1DB Switchgear Room (1B-436).
2.
Within 30 minutes, de energize Bus 1DB as follows:
At XSW1DB 10, DIESEL GEN B XEG0001B-DG, perform the following a.
)
1)
Open the following breakers inside XSW1DB 10:
F a)
XSW1DB 10 CCP1, CLOSING CNTRL PWR XEGW t B-DG (RRPA).
b)
XSW1DB 10 CCP2, CLOSING CNTRL PWR XEG00018 DG t
(RRP).
c)
XSW1DB 10 TCP, TRIPPING CNTRL PWR XEG0001 B-DG l
(RRT).
2)
Push the MANUAL TRIP on the 7.2 KV breaker.
1 b.
At XSW1DB 01, BUS 1DB EMERG INCOMING BKR, perform the following:
1)
Open XSW1DB 01 TCP, TRIPPING CNTRL PWR EMERG INCM 1
BKR (RRT).
2)
Open XSW1DB 01 CCP, CLOSING CNTRL PWR EMERG INCM BKR (RRP).
3)
Push the MANUAL TRIP on the 7.2 KV breaker.
i O
1 FEP-1.0 ATTACHMENT 11
)
PART1 PAGE 6 OF 13 REVISION 10 i
SHIFT ENGINEER Page 2 of 5 c.
At XSW1DB 16, BUS 1DB NORMAL INCOMING BKR, perform the following:
1)
Open XSW1DB 161OP, NORMAL INCM BKR TRIPPING CNTRL
- PWR, 2)
Open XSW1DB 16 CCP, NORMAL INCM BKR CLOSING CNTRL PWR.
3)
Push the MANUAL TRIP on the 7.2 KV breaker.
3.
Within 30 minutes, strip XSW1 DB as follows:
a.
At XSW1DB 15, CHARGING INJ PUMP B XPP0043B-CS, perform the following:
1)
Place 43 CS06, XFER UNIT 15, to LOCAL.
2)
Momentarily place SS-CS06, UNIT 15, to STOP.
b.
At XSW1 DB 14, CHARGING INJ PUMP C, XPP0043C-CS, perform the following:
1)
Place 43 CS08, XFER UNIT 14, to LOCAL.
2)
Momentarily place SS-CS08, UNIT 14, to STOP.
c.
At XSW1DB 13, CC PUMP B XPP0001B-CC, perform the following:
1)
Place 43 CCO2, XFER UNIT 13, to LOCAL.
2)
Momentarily place SS-CCO2, UNIT 13, to STOP.
d.
At XSW1DB 11, CC PUMP C XPP0001C-CC, perform the following:
1)
Place 43-CC04, XFER UNIT 11, to LOCAL.
2)
Momentarily place SS-CC04, UNIT 11, to STOP.
FEP-1.0 ATTACHMENT ll
~
O PART1 G'
PAGEU OF 13 REVISION 10 SHIFT ENGINEER l
Page 3 of 5 t
\\
At XSW1DB 07, TRANSF 1DB1 & 1DB2, perform the following:
e.
1)
Place 43 ES19, XFER UNIT 7, to LOCAL.
2)
Momentarily place SS-ES19, UNIT 7, to CLOSE.
f.
At XSW1DB 06, RB SPRAY PUMP XPP0038B SP, perform the following:
1)
Open XSW1DB 06 TCP, TRIPPING CNTRL PWR XPP0038B-SP (RRT).
2)
Open XSW1DB 06 CCP, CLOSING CNTRL PWR XPP0038B-SP (RRP).
3)
Push the MANUAL TRIP on the 7.2 KV breaker.
I At XSW1DB 05, PZR HTR BKUP GRP 2 XTF4102 RC, perform the g.
l following:
1)
Open XSW1DB 05 TCP, TRIPPING CNTRL PWR XTF4102-RC (RRT).
2)
Open XSW1DB 05 CCP, CLOSING CNTRL PWR XTF4102 RC (RRP).
3)
Push the MANUAL TRIP on the 7.2 KV breaker.
h.
At XSW1DB 04, XSW1EB FDR BKR, perform the following:
1)
Place 43 ES23, XFER UNIT 4, to LOCAL.
2)
Momentarily place SS-ES23, UNIT 4, to CLOSE.
FEP-1.0 ATTACHMENT 11 C)
PART1 V
PAGE 8 OF 13 REVISION 10 SHIFT ENGINEER Page 4 of 5 i.
At XSW1DB 03, EMERG FD WTR PUMP XPP0021B-EF, perform the following:
1)
Open XSW1DB 03 TCP, TRIPPING CNTRL PWR XPP00218-EF (RRT).
2)
Open XSW1DB 03 CCP, CLOSING CNTRL PWR XPP0021B-EF (RRP).
3)
Push the MANUAL TRIP on the 7.2 KV breaker.
4.
Within 30 minutes, strip loads from XSW1DB2 as follows:
i At XSW1 DB2 03A perform the following:
a.
1)
Place 43-VUO6, XFER UNIT 6C, to LOCAL.
O 2)
Momentarily place SS-VUO6, UNIT 6C, to STOP.
3)
Place 43-VUO8, XFER UNIT SA, to LOCAL.
l 4)
Momentarily place SS VUO8, UNIT SA, to STOP, b.
Open XSW1DB2 OSB, FEEDER MCC 1DB2X XMC1DB2X-ES.
Open XSW1DB2 068, FEEDER MCC 1DB2Y PRI UNIT 1 AC SEC UNIT c.
25AD XMC1DB2Y-ES.
d.
At XSW1DB2 03A, close the Main incoming Breaker as follows:
1)
Place 43-ES37, XFER UNIT 48, to LOCAL.
2)
Momentarily place SS-ES37, UNIT 4B, to CLOSE.
Report to the Control Room Supervisor that XSW1DB and XSW1DB2 e.
are stripped.
O
1 4
FEP 1.0 ATTACHMENT 11
{
PART1
. PAGE 9 OF 13 REVISION 10 SHIFT ENGINEER i
1 -
Page 5 of 5 g
5.
When directed, energize XSW1DB from Diesel Generator B as follows:
At XSW1DB 10, DlESEL GEN B XEG00018-DG, perform the following:
a.
1)
Close XSW1DB 10 CCP1, CLOSING CNTRL PWR XEG0001B-DG (RRPA).
2)
Ensure the 7.2 KV breaker closes.
b.
If the Diesel Generator breaker does not close, proceed to Diesel Generator B and perform the following:
4 1)
Verify that LOCAL / REMOTE /MAINT switch is in LOCAL.
2)
Verify that the Diesel Generator is running with normal voltage and frequency indicated.
3)
Investigate and attempt to start the Diesel Generator and close the breaker as necessary.
6.
Proceed to XPN-7200B, Control Room Evacuation Panel, and Start Service i
Water Pump B(C) as follows:
i Place SW PUMP B XFER XPP-0039B, to LOCAL.
a.
b.
Place SW PUMP C TRAIN B XFER XPP 00390, to LOCAL.
Start SW PUMP B, XPP 0039B, or SW PUMP C TRAIN B, XPP-00390.
c.
7.
At XPN7300, Remote Source Range Instrument Panel, place N33 DET HIGH VOLTAGE, to ON.
O
FEP 1.0 ATTACHMENT 11 a
PART1 PAGE 10 OF 13 REVISION 10 AUXILIARY BLDG OPERATOR (UPPER)
Page 1 of 1 i.
NOT.E 1.
This Part is to be performed in conjunction with the duties specified by FEP-2.0.
?
{
2.
This Part applies to fire in Zones CB-1.1 and CB 1.2.
4 I
1.
Within 30 minutes, immediately after completing FEP-2.0 ATTACHMENT XI, l
CROSS TRAIN CONNECTION OF BATTERY CHARGER XBC1 A 1B, pedorm the following:
l At XSW1DB103A (AB 463) open the main incoming breaker as follows:
a.
a 1)
Place 43-ES36, XFER UNIT 4B, to LOCAL.
e 2)
Momentarily place SS-ES36, UNIT 48, to OPEN.
3)
Report to the Control Room Supervisor that XSW1DB1 main incoming breaker is open.
2.
Within 90 minutes, close XVT08100-CS, RC PUMP SEAL RETURN HDR ISOL VLV (ORC) (AB-412 West Pen).
O
- - -.... - - -. =.. - - - -. -.. - -.. - -..
2 FEP-1.0 ATTACHMENT ll
[N PART1
\\
PAGE 110F 13 REVISION 10 INTERMEDIATE BUILDING OPERATOR Page 1 of 3 NOTE 1.
Step 1 is an immediate Action.
2.
This Part is to be performed instead of FEP 2.0, Attachment IV.
l 3.
This Part applies to fire in - -.ies CB-1.1 and CB-1.2.
1.
If directed by the Nuclear Reactor Operator At The Controls, trip the Reactor locally at XSWOOO1-CR (IB-463) by opening the following:
a.
XSWOOO1-RTA, REACTOR TRIP BREAKER A.
b.
XSWOOOf RTB, REACTOR TRIP BREAKER B.
c.
XSWOOO1 BYA, REACTOR TRIP BYPASS BREAKER A.
d.
XSWOOO1-BYB, REACTOR TRIP BYP. ASS BREAKER B.
2.
Obtain plant keys, tool bag, and flashlight from the IB-436.
NOTE 3 The Shift Engineer is de-energizing Bus 1 DB, which will automatically start Diesel Generator B.
3.
Place Diesel Generator B in LOCAL as fo!!ows (DB-436):
a.
Place the REMOTE / LOCAL /MAINT Switch to LOCAL.
b.
Notify the Control Room Supervisor that Diesel Generator B is in LOCAL.
FEP 1.0 ATTACHMENT ll PART1 PAGE 12 OF 13 REVISION 10 INTERMEDIATE BUILDING OPERATOR Page 2 of 3 4.
Within 30 minutes,~ isolate blowdown by closing the following valves (TB 424):
XVT00542A-BD, SG A BLOWDOWN HEAT EXCHANGER INLET VLV.
a.
b.
XVT005428-BD, SG B BLOWDOWN HEAT EXCHANGER INLET VLV.
XVT00542C-BD, SG C BLOWDOWN HEAT EXCHANGER INLET VLV.
c.
5.
Within 30 minutes, proceed to the Service Water Pump House and perform the following(SW-440 ):
1 At XSW1EB103A, close the main incoming breaker as follows:
a.
1)
Place 43 ES40, XFER UNIT 4B, to LOCAL.
2)
Momentarily place SS-ES40, UNIT 4B, to CLOSE.
b.
At XSW1EB 03, close the XSW1EB1 feeder breaker as fol!ows:
1)
Place 43-ES21, XFER UNIT 3, to LOCAL.
2)
F.cmentarily place SS-ES21, UNIT 3, to CLOSE.
Start XFN80B AH. SERVICE WATER BUILDING SUPPLY FAN B from c.
XPN 5527, as follows (behind XSW1EB1):
1)
Place 43-AH327 XFER, XMC1EB1X U4FH, to LOCAL.
2)
Place SS AH327X, XMC1EB1X U4FH, to START.
O
l 1
FEP 1.0 l
ATTACHMENT 11 PART1 l
PAGE 13 OF 13 REVISION 10 INTERMEDIA'i': BUILDING OPERATOR Page 3 of 3 d.
Reposition Service Water Pump House ventilation dampers by isolating Instrument Air to the Service Water Pump House as follows (behind XSW1EB):
o 1)
Close XVAi2969-SA, SW PUMP HOUSE INST AIR HDR SUPPLY l
VALVE.
2)
Open XVT22923 SA, SW SA SUPPLY HEADER LOW POINT DRAIN VLV, to depressurize the header.
l NOTE 6 Frequent trips will be required out of the high noise area to communicate with the Control Room Supervisor at the CREP.
- 6.
Proceed to Diesel Generator B and monitor its operation.
7.
Within 30 minutes, start XFN-45A(B), DG AREA B VENTILATION AIR SUPPLY FAN A(B), from XPN 5526-AH (DB-436) as follows:
a.
Place A3-AH164 XFER, XMC1DB2Z U3AC, to LOCAL.
b.
Place SS AH164X, XMC1DB2Z U3AC, to START.
c.
Place 43-AH165 XFER, XMC1DB2Z U2AC, to LOCAL.
d.
Place SS-AH165X, XMC1DB2Z U2AC, to START.
!O 4
4 4
.. _.. _.. - _. ~.....
FEP-1.0 ATTACHMENT ll
!gQ PART2 l
PAGE 1 OF 1 REVISION 10 CONTROL ROOM SUPERVISOR NOTE l
1.
This Part applies to fire in Zone CB-2.
l 2.
PART ARO-43,44 and SE 50 are also applicable to this zone.
l 1.
Substitute the following equipment throughout FEP-2.0 and FEP-2.1:
Use Instead Of For Local Manual Remote IFV-3541 Local Manual Remote IPV-2010 l
l Attachment IV (FEP-2.1)
TR-604A RHR Temperature r'
i l
e O
V
FEP-1.0 ATTACHMENT 11 O
PART3 PAGE 1 OF 1 REVISION 10 CONTROL ROOM SUPERVISOR NOTE 1.
This Part applies to fire in Zones CB-5 and IB-25.5.1.
2.
PART 4 is also applicable to Zone CB-5.
3.
PARTS ARO-46 and SE-50 are also applicable to Zone IB 25.5.1.
1.
Substitute the following equipment throughout FEPs:
Use Instead Of For Local Manual Remote IPV-2020 O
O
FEP-1.0 ATTACHMENT 11
-I PART4 PAGE 1 OF 1 REVISION 10 CONTROL ROOM SUPERVISOR NOTE 1.
This Part applies to fire in Zones CB-5 and 18-2.
2.
PART 3 is also applicable to Zone CB-5.
1.
Substitute the following equipment throughout FEP-3.0 and FEP-3.1:
i Use Instead Of For TI-430A (CREP)
TI430 Loop C T-Cold j
TI-433A (CREP)
TI-403 Loop C T-Hot l
Vl O
FEP-1.0 ATTACHMENT 11 l (
PART5 l
PAGE 1 OF 1 REVISION 10 CONTROL ROOM SUPERVISOR l
NOTE 1.
This Part applies to fire in Zones CB 7, CB-12, IB-10, IB-11 and 1B 15.
2.
PARTS 6, ARO-40,43,44, SE-50 and AB 54 are also applicable to Zone CB-12.
3.
PART 7 is also applicable to Zone IB-11.
4.
PART AP.O-45 is also applicable to Zone 18-15.
l 1.
Substitute the following equipment throughout FEP 2.0 and FEP-2.1:
Use Instead Of For o
Local Manual Remote IFV-3541 b
2.
Within eight hours, if XFN-38A and XFN-39A are not available have temporary
'd ventilation installed in Battery Charger A room.
1
!O
=~
FEP-1.0 l
ATTACHMENT ll i
PART6 PAGE 1 OF 1 REVISION 10 CONTROL ROOM SUPERVISOR NOTE 1.
This Part applies to fire in Zones CB-10, CB-12, CB-18 and IB 20.
2.
PARTS 7,8, ARO-42,43,44 47, SE-50 and 51 are also applicable to Zone CB-10.
3.
PARTS 5, ARO-40,43,44, SE-50 and AB-54 are also applicable to l
Zone CB-12.
4.
PARTS ARO-41,42 and 43 are also applicable to Zone CB-18.
5.
PARTS ARO-42,43,44 and SE-50 are also applicable to Zone IB-20.
1.
Substitute the following equipment throughout FEPs:
i l
Use Instead Of For Local Manual Remote All Steam Generator PORV's l
l l
l 1
l l
FEP 1.0 ATTACHMENT ll
{
PART7 l
PAGE 1 OF 1 REVISION 10 CONTROL ROOM SUPERVISOR
.N,QTE 1.
This Part applies to fire in Zones CB-10,18-11,18-12, and 18-14, 2.
PART 5 is also applicable to Zone 1811.
3.
PART ARO-42 is also applicable to Zone IB-14.
4.
PARTS 6,8, ARO-42,43,44,47, SE-50 and 51 are also applicable to Zone CB-10.
1.
Substitute the following equipment throughout FEPs:
Use Instead Of For Local Remote C Chiller p
2.
Within 90 minutes, have the intermediate Building Operator place VU t
Chiller C in LOCAL at XPN-7208 (1B-412).
l O
FEP 1.0
~
ATTACHMENT 11 PART8 PAGE 1 OF 1 REVISION 10 CONTROL ROOM SUPERVISOR NOTE 1.
This Part applies to fire in Zones TB-1 and CB-10.
2.
PARTS ARO-47 and SE 51 are also applicable to Zone TB-1.
3.
PARTS 6,7, ARO-42,43,44,47, SE-50 and 51 are also applicable to Zone CB-10.
NOTE 1 This fire can cause control problems with Bus 1DB normal and emergency incoming breakers and with Diesel Generator B remote control. The A Nuclear Reactor Operator will coordinate with the Shift Engineer to establish local control.
1.
Use local control of Diesel Generator B throughout FEP-3.0 and FEP 3.1.
}
l
.. - _.. - -._.... _ =. - - -. -.. -..... _. - - -..
FEP-1.0 ATTACHMENT ll PART 9 PAGE 1 OF 1 REVISION 10 CONTROL ROOM SUPERVISOR IL lE This Part applies to fire in Zone CB-20.
1.
Substitute the following equipment throughout FEP-2.0 and FEP-2.1:
Use-Instead Of For 1
PI402 PI-403 RCS Pressure FEP-2.1 Attachment IV TR 604A RHR Temperature O
i s
1
l FEP-1.0 ATTACHMENT 11 6
PART 10 PAGE 1 OF 1 REVISION 10 CONTROL ROOM SUPERVISOR NOTE This Part applies to fire in Zones CB-22 and AB-1.29.
1.
Substitute the following equipment throughout FEPs:
Use Instead Of For Plant Page Radios Communication l
s
)
. _ ~..
. -. ~.
FEP-1.0 O.-
ATTACHMENT ll PART 11 PAGE 1 OF 1 REVISION 10 CONTROL ROOM SUPERVISOR NOTE This Part applies to fire in Zones AB 1.1.1 and AB-1.2.
1.
Use FEP-3.1 Attachment IV for monitoring RHR Temperature when implementing FEP-3.1.
I r
a l
i O
FEP-1.0 ATTACHMENT 11 t
PART 12 PAGE 10F 1 REVISION 10 CONTROL ROOM SUPERVISOR NOTE This Part applies to fire in Zone AB-1.1.3.
NOTE 1 The cable supplying XPP-31B, RHR PUMP B, and XFN-49B, RHR/ SPRAY PUMP ROOM 2 COOLING UNIT FAN, are routed through firs Zone AB-1.1.3.
1.
If cable tray 2017 has been damaged, direct the Emergency Maintenance Team to install a temporary cable for RHR Pump B per EMP-100.002, prior to reaching 350 degrees RCS Temperature, and rig temporary ventilation for RHR B Room cooling.
(
i V I
FEP-1.0 i
ATTACHMENT ll PART 13 PAGE 10F 1 l
REVISION 10 CONTROL ROOM SUPERVISOR NOTE 1.
Step 1 is an immediate Action.
2.
This Part applies to fire in Zones AB-1.4 and AB 1.6.
l 3.
Charging Pump C will not be available due to the fire.
4.
The fire may have to be extinguished before the AB Operator can open l
LCV00115B(D) CS, XVG08131 A-CS, XVG08131 B-CS, XVG08132A-CS, XVG08132B CS, XVG08133A CS, and XVG08133B-CS, to establish Seal Injection (90 minute action).
l l
CASE I-Charaina Pumo A - OPERABLE l
1.
Implement FEP-2.0.
O CASE 11 - Charaina Pump A - INOPERABLE 1.
Implement FEP-3.0.
t i
4 I
l FEP-1.0 ATTACHMENT 11 o
PART 14 PAGE 1 OF 1 REVISION 10 CONTROL ROOM SUPERVISOR l
NOTE 1.
This Part applies to fire in Zone AB-1.8.1.
2.
The fire may have to be extinguished before the AB Operator can close XVG03001 A-SP, RB SPRAY PP A RWST SUCTION HDR VALVE, and XVG08812A SI, RH PUMP A SUCTION HEADER VALVE (30 minute action).
l l
tU l
l l
l
FEP-1.0 l
ATTACHMENT ll 1
l PART 15 PAGE 1 OF 1 REVISION 10 CONTROL ROOM SUPERVISOR NOTE l
l 1.
This Part applies to fire in Zone AB-1.8.2.
2.
The fire may have to be extinguished before the AB Operator can close XVG03001B SP, RB SPRAY PP B RWST SUCTION HDR VALVE, and t
I XVG08812B-SI, RH PUMP B SUCTION HEADER VALVE (30 minute action).
i 1.
Substitute the following equipment throughout FEP-2.0 and FEP-2.1:
l Use instead Of For o
FEP-2.0 Attachment Vlli Remote Charging Pump C l
(XSW1DA) e FEP-2.1 Attachment IV TR-604A RHR Temperature r
l l
I t
i O
. - - ~
FEP-1.0 ATTACHMENT 11 P
E 10F 1 REVISION 10 CONTROL ROOM SUPERVISOR
.N._QTE 1.
Step 1 is an immediate Action.
2.
This Part applies to fire in Zone AB 1.9.
3.
Charging Pump C will not be available due to the fire, CASE I-Charaina Pumo B - OPERABLE 1.
Implement FEP-3.0.
l CASE 11 - Charaina Pumo B - INOPERABLE 1.
Implement FEP 2.0.
O O
FEP 1.0 ATTACHMENT 11 O
PART 17 O
PAGE 1 OF 1 REVISION 10 CONTROL ROOM SUPERVISOR M
1.
This Part applies to fire in Zone AB-1.10.
2.
The fire may have to be extinguished before the AB Operator can close LCV00115E-CS, VOLUME CONTROL TANK OUTLET HDR ISOL VLV, and open XVG08106-CS, CHARGING PUMPS MINI FLOW HDR ISOL VALVE, to establish Seal Injection (90 minute action).
1.
Substitute the following equipment throughout FEP-3.0 and FEP-3.1:
Use instead Of For TI-430A (CREP)
TI-430 Loop C T Cold TI-433A (CREP)
TI-433 Loop C T-Hot O
O
FEP-1.0
~
ATTACHMENT ll
[
PART 18 4
PAGE 1 OF 1 REVISION 10 CONTROL ROOM SUPERVISOR NOTE 1.
This Part applies to fire in Zone AB-1.18.1.
2.
PARTS ARO-41 and SE-52 are also applicable to this zone.
1.
Substitute the following equipment throughout FEP-3.0 and FEP-3.1:
Use Instead Of For Local Manual Remote IPV-2000 Local Manual Remote XSW1DB1 Main incoming Breaker O
O
FEP 1.0 6
ATTACHMENT ll PART 19 PAGE 10F 1 REVISION 10 CONTROL ROOM SUPERVISOR j
NOTE 1.
This Part applies to fire in Zone AB-1.18.2.
2.
The fire may have to be extinguished before the AB Operator can open XVT08389-CS, SEAL INJECTION HEADER FLOW BYPASS VALVE, to establish Seal Injection (90 minute action).
1.
Use Attachment IV for monitoring RHR temperature in FEP-2.1.
i i O 4
2 t
i l
1 2
}
lO w
e
FEP-1.0 6
ATTACHMENT 11 PART 20 PAGE 1 OF 1 REVISION 10 CONTROL ROOM SUPERVISOR NOTE 1.
This Part applies to fire in Zones AB 1.21.2.
2.
PART ARO-41 is also applicable to this zone.
1.
Substitute the following equipment throughout FEP-2.0 and FEP-2.1:
Use instead Of For Local Manual Remote IPV-2000 PI-402 Pl-403 RCS Pressure FEP-2.1 Attachment IV TR 604A RHR Temperature Plant Page Radios Communication O
l O
FEP-1.0 ATTACHMENT ll C
PART 21 PAGE 1 OF 1 REVISION 10 CONTROL ROOM SUPERVISOR NOTE 1.
This Part applies to fire in Zone RB-1.1.1.
2.
PARTS ARO-40 and AB-54 are also applicable to this zone.
1.
Substitute the following equipment throughout FEP-2.0 and FEP-2.1:
Use Instead Of For PI-402 PI-403 RCS Pressure PI-484 and TI-420 RCS T-Cold Steam Ta,bles XVT08100-CS XVT-8112 Seal Return isolation O
FEP-1.0 i
l ATTACHMENT 11 l
PART 22 PAGE 10F 1 REVISION 10 CONTROL ROOM SUPERVISOR NOTE l
l
\\
l 1.
This Part applies to fire in Zones RB-1.1.2, RB-1.2.2, RB-1.3.3, RB-1.4.2, IB-25.3.1 and IB-25.3.2.
2.
PART ARO-40 is also applicable to Zone RB-1.1.2 only.
3.
PARTS ARO-46 and SE-50 are also applicable to Zones iB-25.3.1 and 18-25.33.2 only.
NOTE 1 For fire in these zones, Steam Generator A and its associated instrumentation will be the most reliable.
1.
Substitute the following equipment throughout FEP-3.0 and FEP-3.1:
O Use Instead Of For Ll462 LI461 Pressurizer Level LI-475 LI-496 Steam Generator Level PI-475 PI-495 Steam Generator Pressure PI-2000 PI2020 Main Steam Line Pressure IPV-2000 IPV-2020 Steam Generator PORV IFV-3531 IFV-3551 Steam Generator Feed TI410 TI-430 RCS T-Cold ITE-0413A (CREP)
TI-433 RCS T-Hot (TI-413(MCB) for RB-1.4.2 only)
NI-32 NI-33 Reactor Power (NI-31 for RB-1.2.2 only)
O.
t
FEP-1.0 ATTACHMENT ll PART 23 q
PAGE 1 OF 1 REVISION 10 CONTROL ROOM SUPERVISOR l
j i
NOTE 1.
This Part applies to fire in Zones RB-1.3.2 and RB-1.4.1.
2.
PARTS ARO-42 and AB 54 are also applicable to Zone RB-1.3.2 only.
1.
Substitute the following instrumentation throughout FEP-2.0 and FEP-2.1:
I Use instead Of For Ll-462 Li-459 Pressurizer Level i
O O
FEP-1.0 ATTACHMENT ll PART 24 l
PAGE 10F 1 REVISION 10 CONTROL RCIOM SUPERVISOR l
NOTE 1.
This Part applies to fire in Zone IB-3.
2.
PART AB 55 is also applicable to this zone.
I NOTE 1 Train A control power will be lost when the battery discharges. Local manusi control of all Steam Generator PORVs will be necessary.
1.
Substitute the fcn.using equipment throughout FEP-3.0 and FEP 3.1:
Use Instead Of For PI-495 and Steam Tables TI430 RCS T-Cold TI-433A (CREP)
TI-433 RCS T-Hot Local Manual Remote All Steam Generator PORVs i
FEP 1.0 RT 25 PAGE 1 OF 1 RF. VISION 10 CONTROL ROOM SUPERVISOR NOTE 1.
This Part applies to fire in Zone IB-4.
2.
PART AB 55 is also applicable to this zone.
NOTE 1 Train B control power will be lost when the battery discharges. Local manual control of the emergency feed valves and Steam Generator PORVs will be necessary.
1 d
1.
Substitute the following equipment throughout FEP-2.0 and FEP 2.1:
Use Instead Of For I
PI-484 and Steam Tables TI-420 RCS T-Cold e
i Local Manual Remote All Steam Generator PORVs Local Manual Remote IFV-3531,3541 and 3551 4
1 4
4 4
4
' O
f FEP 1.0 ATTACHMENT 11 PART 26 PAGE 1 OF 1 REVISION 10 CONTROL ROOM SUPERVISOR NOTE i
1.
This Part applies to fire in Zone IB-5.
2.
PART AB-56 is also applicable to this zone.
l' NOTE 1 1
For this fire zone Battery Charger 1 A 1B will not be available. The AB Operator l
removes unnecessary loads from DPN1HA and DPN1HA1. Local manual control of all Steam Generator PORVs will be necessary.
l 1.
Substitute the following equipment throughout FEP-3.0 and FEP-3.1:
Use Instead Of Fgr TI-430A (CREP)
TI-430 RCS T-Cold TI-433A (CREP)
TI-433 RCS T Hot 1
Local Manual Remote All Steam Generator PORVs l
l l
!. ON U
l l
w
,ww
-v
_._.__.__ _ ~.__._.._
FEP-1.0 l
ATTACHMENT ll PART 27 i
l PAGE 10F 1 REVISION 10 CONTROL ROOM SUPERVISOR EQIE 1.
Step 1 is an immediate Action.
2.
This Part applies to fire in Zones 18-7.2 and IB-8.
CASE I-Chiller A - OPERABLE 1.
Implement FEP-2.0.
l CASE il-Chiller A - INOPERABLE l
1.
Implement FEP-3.0.
O l
l l
l i
i
)
1 i
i
FEP-1.0
~
ATTACHMENT 11
> (
PART 28 PAGE 1 OF 1 REVISION 10 l
CONTROL ROOM SUPERVISOR i
NOTE 1.
Step 1 is an immediate Action.
2.
This Part applies to fire in Zone 18-13.
CASE I - Component Coolina Pumo A - OPERABLE 1.
Implement FEP-2.0.
1 CASE 11 - Component Coolina Pumo A - INOPERABLE 1.
Implement FEP 3.0.
1 l
l l
l I
l O
. - _ - ~ _
FEP 1.0 ATTACHMENT il PART 29 PAGE 1 OF 1 REVISION 10 CONTROL ROOM SUPERVISOR NOTE 1.
This Part applies to fire in Zone 1817.
l 2.
PARTS ARO-47 and SE-51 are also applicable to this zone.
NOTE 1 This fire can cause control problems with Bus 1DB normal and emergency incoming breakers and with Diesel Generator B remote control. The A Nuclear j
Reactor Operator will coordinate with the Shift Engineer to establish local l
control.
1.
Substitute the following equipment throughout FEP-3.0 and FEP-3.1:
Use Instead Of For Local Remote VU Chiller C Portable Ventilation XFN-76 Cooling 1DB Switchgear Room i
Local Remote Diesel Generator B 2.
Within 90 minutes, have the IB Operator place VU Chiller C in LOCAL at XPN 7208 (IB-412).
3.
Within eight hours, if XFN-76,1DB Cooling Fan is disabled, have maintenance or the fire brigade rig temporary fans.
3O f
l
1 FEP-1.0
{
ATTACHMENT !!
6 PART 30 PAGE 1 OF 1 REVISION 10 CONTROL ROOM SUPERVISOR i
NO_TE 1.
This Part applies to fire in Zones IB-22.1 and 18-22.2.
2.
PARTS ARO-44 and SE 50 are also applicable to these zones.
1.
Substitute the following equipment throughout FEP-2.0 and FEP-2.1:
Use Instead Of For Local Manual Remote IFV-3541 Local Manual Remote PCV 2000 FEP 2.0 Attachment IX Remote XFN-38A, Battery Room Fan (1DA2X)
O I
J 4
1 i
!O s
I
.. -.= -_. _-
FEP-1.0 i
ATTACHMENT 11 PART 31 PAGE 1 OF 1 REVISION 10 CONTROL ROOM SUPERVISOR fiQTg 1.
This Part applies to fire in Zones 18-25.1.1,18-25.1.4,18-25.2 and 18-25.5.2.
2.
PART SE 50 is also applicable to Zone 18-25.5.2 only.
l 1.
Substitute the following instrumentation throughout FEP-3.0 and FEP-3.1:
-Use Instead Of For LI-462 Ll461 Pressurizer Level LI-497 LI-496 i
Steam Generator C Level PI-2020 PI-495 Steam Generator C Pressure i
I l
l v
FEP 1.0 ATTACHMENT ll g
PART 32 PAGE 10F 1 REVISION 10 CONTROL ROOM SUPERVISOR NOTE 1.
This Part applies to fire in Zone 18-25.1.2.
2.
PARTS ARO-40,43,44 and SE-50 are also applicable to this zone.
1.
Substitute the following equipment throughout FEP 2.0 and FEP 2.1:
Use Instead Of For Local Manual Remote All Steam Generator PORVs Local Manual Remote IFV-3541 Local (XPN-7208)
Remote VU Chiller C Attachment Vlli(XSW1DA1)
Remote XPP-45A, SW Booster 4
Pump Attachment IX (XSW1DA2X)
Remote XFN-38A, Battery Room Fan l
2.
Within 90 minutes, have the IB Operator place VU Chiller C in LOCAL at XPN-7208 (1B 412).
l l
I llO
i FEP-1.0 1
ATTACHMENT 11 PART 33 V
PAGE 1 OF 1 REVISION 10 l
CONTROL ROOM SUPERVISOR NOTE 1.
This Part applies to fire in Zone 18-25.1.3.
2.
PARTS ARO-45,46,48, SE-53 and 18-58 are also applicable to this zone.
1.
Substitute the following equipment throughout FEP-3.0 and FEP 3.1:
Use Instead Of Fqr LI-462 LI-461 Pressurizer Level Ll-497 Ll-496 Steam Generator C Level PI2020 PI495 Steam Generator C Pressure Local Manual Remote IPV 2020 l
TDEFP Speed Flow Control Valves Controlling Steam l
Generator Level TDEFP MDEFP B Steam Generator Feed I
i O
l FEP-1.0 l
ATTACHMENT 11 g
PART 34 PAGE 10F 2 REVISION 10 CONTROL ROOM SUPERVISOR l
l NOTE l
1.
Step 1 is an immediate Action.
l l
P..
This Part applies to fire in Zone 18-25.1.5.
l i
3.
PARTS ARO-43,44, SE-50 (CASE 1), SE-53 (CASE II), and 18-58 l
(CASE 11) are also applicable to this zone.
l CASE I - Component Coolina Pumo A - OPERABLE 1.
Implement FEP 2.0, modified by PARTS ARO 43, ARO-44 and SE-50.
2.
Substitute the following equipment throughout FEP-2.0 and FEP 2.1:
i Use instead Of For PI-2010 Pl-484 Steam Generator B Pressure Local Manual Remote IFV-3541 Local Manual Remote All Steam Generator PORVs l
CASE II - Component Coolina Pumo A - INOPERABLE 1.
Implement FEP-3.0, modified by PARTS ARO-43, ARO-44, SE-53 and 18-58, 2.
Substitute the following equipment throughout FEP 3.0 and FEP 3.1:
l F2 l
Use Instead Of l
l LI-462 Ll-461 Pressurizer Level Ll-497 Ll-496 Steam Generator C Level NI32 NI-33A Reactor Power TDEFP MDEFP B Steam Generator Feed Local Manual Remote IFV-3556 i
l FEP-1.0 ATTACHMENT ll l
PART 34 l
PAGE 2 OF 2 i
REVISION 10 Use Instead Of For Local Manual Remote All Steam Generator PORVs l
i t
1 1
l l
r Ii O l
l h
l FEP 1.0 D
WE""""' "
PAGE 1 OF 1 REVISION 10 CONTROL ROOM SUPERVISOR NOTE 1.
This Part applies to fire in Zone 18-25.4.
2, PARTS ARO-40,41 and SE-50 are also applicable to this zone.
1.
Substitute the following equipment throughout FEP-2.0 and FEP-2.1:
Use Instead Of For PI 484 and Steam Tables TI-420 RCS T-Cold
!O i
1 i
i f
l i
j.
4 1
i
!O 4
4
- =.
FEP-1.0 ATTACHMENT 11 PART 36 PAGE 1 OF 1 REVISION 10 CONTROL ROOM SUPERVISOR i
1.
This Part applies to fire in Zones IB-25.6.1,18 25.6.2 and 1B 25.7.
l 2.
PARTS ARO-43,45,47, SE-50,51 and AB-57 are also applicable to i
these zones.
i I
NOTE 1 i
This fire can cause control problems with Bus 1DB normal and emergency incoming breakers and with Diesel Generator B remote control. The A Nuclear Reactor Operator will coordinate with the Shift Engineer to establish local control.
1.
Substitute the following equipment throughout FEP-3.0 and FEP 3.1:
- p Use instead Of Fgr O
LI-462 LI461 Pressurizer Level L1-497 LI496 Steam Generator C Level i
PI-2020 PI-495 Steam Generator C Pressure Local Manual Remote IPV-2010, 2020 Local Remote Diesel Generator B Local Remote VU Chiller C Local (AB-388)
Remote XFN-47 (Charging Pump C Room Fan) 2.
This fire can damage both the radio system and the plant page. Use Channel 2 on the radios, or runners if needed.
3.
Within 90 minutes, have the IB Operator place VU Chiller C in LOCAL on XPN-7208 (IB-412).
l
FEP 1.0 1
l ATTACHMENT 11 PART 37 PAGE 1 OF 1 REVISION 10 CONTROL ROOM SUPERVISOR NOTE 1.
This Part applies to fire in Zone 1B-25.8.
1 2.
PARTS ARO-41 and SE-50 are also applicable to this zone.
1.
Substitute the following equipment throughout FEP-2.0 and FEP-2.1:
Use Instead Of Fo_r o
Local Manual Remote IPV-2000 O
l iO
FEP 1.0 i
l p ATTACHMENT 11 1
PART 38 l
PAGE 1 OF 1 l
REVISION 10 CONTROL ROOM SUPERVISOR NOTE 1.
This Part applies to fire in Zone 1B-25.9.
2.
PARTS ARO-41 and ARO-42 are also applicable to this zone.
]
1.
Substitute the following equipment throughout FEP 3.0 and FEP 3.1:
Use Instead Of For i
Ll-462 LI461 Pressurizer Level LI497 LI-496 Steam Generator C Level Local Manual Remote IPV 2000 l
t i
=... -.- -
FEP-1.0 ATTACHMENT 11 o
PART 39 PAGE 1 OF 1 i
REVISION 10 l
CONTROL ROOM SUPERVISOR l
NOTE l
1.
Step 1 is an immediate Action.
2.
This Part applies to fire in Zones SWPH 2, SWPH 5.1.3 and SWPH 5.2.3.
l 3.
PART IB-59 is also applicable to these zones (CASE ll only).
l i
l CASE I - Service Water Pumo A - OPERABLE 1.
Implement FEP 2.0.
CASE 11 - Service Water Pumo A - INOPERABLE I
1.
Implement FEP-3.0, modified by PART IB-59.
l.
l l-I I
.:O h
_. -.. _ - -.. _ _ _ - _ _. _ _... _ _. _ _. - _. _ - _ _. _ _. _.. _ _.. _ - ~. _. _. _. _. _. _.. _... _. _ _ _ _
FEP 1.0 ATTACHMENT 11 PART ARO-40 PAGE 1 OF 1 REVISION 10 i
A NUCLEAR REACTOR OPERATOR L
.N,QBi 1.
Step 1 is an immediate Action.
2.
This Part is to be performed in conjunction with the duties specified by FEP 2.0 (3.0).
3.
This Part applies to fire in Zones CB-12, RB 1.1.1, RB-1.1.2, RB-1.2.3, 18-25.1.2 and IB 25.4.
1.
De-energize the following by opening their respective Disconnect Switches located inside the Main Control Board:
Sub Panel-19B (XCP-6113):
a.
Switch Valve Number 1)
DS-10 XVT-8153 1)
DS 11 XVT-8154 r" s
!V
l FEP 1.0 ATTACHMENT ll nl PART ARO-41 PAGE 10F 1 REVISION 10 A NUCLEAR REACTOR OPERATOR.
NOTE 1.
Step 1 is an immediate Action.
i 2.
This Part is to be performed in conjunction with the duties specified by FEP 2.0 (3.0).
l' j
3.
This Part applies to fire in Zones CB-18, AB-1.18.1, AB-1.21.1, i
AB-1.21.2,1B-25.4,1B 25.8, and 18-25.9.
i 1.
De-energize the following by opening their respective Disconnect Switches l
located inside the Main Control Board:
Sub Panel-19A (XCP-6112):
a.
Switch Va!ve Number 1)
DS-4 PCV-2000A b.
Sub Panel-19B (XCP-6113):
Switch Valve Number 1)
DS-7 PCV 20008 i
l l
lO
. _ = _ -
l FEP 1.0 ATTACHMENT 11 V]
/
PART ARO-42 PAGE 1 OF 1 REVISION 10 A NUCLEAR REACTOR OPERATOR NOTE 1.
Step 1 is an immediate Action.
2.
This Part is to be performed in conjunction with the duties specified by FEP-2.0(3.0).
3.
This Part applies to fire in Zones CB 10, CB 18, AB 1.21.1, RB-1.2.1, RB-1.3.2,1B 14, IB 20,1B-21.1,18 21.2 and 1B 25.9.
1.
De-energize the following by opening their respective Disconnect Switches located inside the Main Control Board:
a.
Sub Panel 19A (XCP-6112):
Switch Valve Number O
1)
DS-1 ILV-459 V
XVT-8146 2)
DS-2 ILV-460 XVT 8147
FEP 1.0 ATTACHMENT ll PART ARO-43 PAGE 10F 1 REVISION 10 A NUCLEAR REACTOR OPERATOR i
NOTE 1.
Step 1 is an Immediate Action.
2.
This Part is to be performed in conjunction with the duties specified by FEP 2.0(3.0).
3.
This Part applies to fire in Zones CB-2, CB-10, CB-12, CB-18,13-20, 18 25.1.2,18 25.1.5, IB-25.6.1,18 25.6.2 and 1B 25.7.
l 1.
De-energize the following by opening their respective Disconnect Switches located inside the Main Control Board:
l a.
Sub Panel 19A (XCP 6112):
Switch Valve Number 1)
DS-5 PCV 2010A 2)
DS 6 PCV 2020A b.
Sub Panel-19B (XCP 6113):
Switch Valve Number 1)
DS 8 PCV-2010B 2)
DS-9 PCV 2020B r
i l
O I
FEP 1.0 ATTACHMENT 11 qQ PART ARO-44 PAGE 1 OF 1 d
REVISION 10 A NUCLEAR REACTOR OPERATOR M9.T,g 1.
Step 1 is an immediate Action.
2.
This Part is to be performed in conjunction with the duties specified by FEP-2.0(3.0).
3.
This Part applies to fire in Zones CB 2, CB-10, CB-12, IB 20,18-22.1, IB 22.2,1B 25.1.2 and 18-25.1.5.
1.
De-energize the following by opening their respective Disconnect Switches located inside the Main Control Board:
Sub Panel-19A (XCP-6112):
a.
Switch Valve Number 1)
DS-3 1-XVM-2801A L
1-XVM 28018 1-XVM 28010 A-XVT-2869A A-XVT-2869B A-XVT-2869C 2)
DS-4 PCV-2000A b.
Sub Panel-19B (XCP-6113):
Switch Valve Number 1)
DS-7 POV-2000B 2)
DS-12 2-XVM-2801 A 2-XVM-2801B 2-XVM-2801C B-XVT-2869A B-XVT-2869B B-XVT-2869C O
FEP-1.0 T#^"a"""s" PAGE 1 OF 1 REVISION 10 A NUCLEAR REACTOR OPERATOR NOTE 1.
Step 1 is an immediate Action.
2.
This Part is to be performed in conjunction with the duties specified by FEP-2.0(3.0).
3.
This Part applies to fire in Zones 1815, IB 25.1.3,18 25.6.1,18-25-6.2 and IB-25.7.
1.
De-energize the following by opening their respective Disconnect Switches located inside the Main Control Board:
a.
Sub Panel-19A (XCP-6112):
Switch Valve Number 1)
DS 3 1-XVM 2801 A 1 XVM-2801B 1 XVM-2801C A-XVT-2869A A XVT-2869B A-XVT-2869C b.
Sub FP.nel-19B (XCP-6113):
Switch Valve Number 1)
DS-12 2-XVM-2801 A 2 XVM-2801B 2 XVM-2801C B-XVT-2869A B-XVT-28698 B-XVT 2869C O
FEP-1.0 ATTACHMENT !!
h PART ARO-46 PAGE 1 OF 1 REVISION 10 A NUCLEAR REACTOR OPERATOR NOTE 1.
Step 1 is an immediate Action.
2.
This Part is to be performed in conjunction with the duties specified by FEP-2.0(3.0).
3.
This Part applies to fire in Zones 18-25.1.3,1B-25.3.1, IB-25.3.2 and 1B-25.5.1.
1.
De-energize the following by opening their respective Disconnect Switches located inside the Main Control Board:
Sub Panel-19A (XCP-6112):
a.
Switch Valve Number 1)
DS-6 PCV-2020A b.
Sub Panel-19B (XCP 6113):
Switch Valve Number 1)
DS-9 PCV 2020B O
V
a FEP-1.0 ATTACHMENT ll
~
5 PART ARO-47 PAGE 1 OF 1 REVISION 10 A NUCLEAR REACTOR OPERATOR i
NOTE 4
1.
This Part is to be performed in conjunction with the duties specified by FEP-3.0.
i
]
2.
This Part applies to fire in Zones CB-10, IB-17, IB-25.6.1, IB-25.6.2, 1B-25.7 and TB-1.
I' l
1.
When establishing power to Bus 1DB from Diesel Generator B, it must be performed locally. Contact the Shift Engineer and direct him to perform PART SE-51.
I i
j j
i
!O i
i i
1' e
O
FEP-1.0 6
ATTACHMENT ll PART ARO-48 PAGE 1 OF 1 REVISION 10 A NUCLEAR REACTOR OPERATOR l
NOTE l
1.
This Part is to be performed in addition to the duties specified by FEP-3.0.
This Part applies to fire in Zone IB-25.1.3.
2.
1.
After FEP-3.0, Attachment lll is completed, perform the following:
a.
Remove the following fuses inside the MCB:
1)
FU-EF38A for FCV-3546 (XCP 6111).
2)
FU-EF39A for FCV-3556 (XCP 6111).
l
,O I
i
~
1 FEP-1.0 ATTACHMENT 11 PART ARO-49 1
PAGE 1 OF 1 REVISION 10 l
A NUCLEAR REACTOR OPERATOR l
NOTE 1.
Step 1 is an Irnmediate Action.
l 2.
- This Part is to be performed in conjunction with the duties specifi3d by FEP-4.0.
3.
This Part applies to fire in Zones CB 17.1, CB-17.2 and CB 17.3.
1.
Open the disconnects in the Termination Cabinets (CB-448) instead of inside the MCB.
v
FEP-1.0 ATTACHMENT ll
/
PART SE-50 PAGE 1 OF 1 REVISION 10 SHIFT ENGINEER HQlE This Part applies to fire in Zones CB-2, CB 10, CB 12, IB-20,18-22.1, IB 22.2, l
18 25.1.2, IB-25.1.5 CASE I,18 25.3.1, IB-25.3.2,18 25 4,18-25.5.1, IB-25.5.2 l
lB 25.6.1,1B 25.6.2,18 25.7,18-25.8 and 18 27.
1.
Within 30 minutes, isolata blowdown by closing the following valves (TB-424):
l l
XVT00542A-BD, SG A BLOWDOWN HEAT EXCHANGER INLET VLV.
a.
b.
XVT00342SBD, SG B BLOWDOWN HEAT EXCHANGER INLET VLV.
XVT00542C-BD, SG C BLOWDOWN HEAT EXCHANGER INLET VLV.
c.
O
.-.. ~. - -
FEP 1.0 ATTACHMENT 11 h
PART SE-51
'd PAGE 1 OF 2 REVISION 10 SHIFT ENGINEER NOTE This Part applies to fire in Zones CB-10, IB-17, IB 25.6.1, IB-25.6.2, IB-25.7 and TB-1.
1.
When directed, de-energize Bus 1DB (IB-436) as follows:
a.
At XSW1DB 01, BUS 1DB EMERG INCOMING BKR, perform the following:
1)
Open XSW1DB 01 CCP, CLOSING CNTRL PWR EMERG INCM BKR (RRP).
j 2)
Open XSW10B 01 TCP, TRIPPING CNTRL PWR EMERG INCM BKR (RRT).
q 3)
Push MANUAL TRIP on 7.2KV breaker.
V b.
At XSW1DB 16, BUS 1DB NORMAL INCOMING BKR, perform the following:
1)
Open XSW1DB 16 CCP, NORMAL INCM BKR CLOSING CNTRL PWR.
2)
Open XSW1DB 16 TCP, NORMAL INCM BKR TRIPPING CNTRL PWR.
3)
Push MANUAL TRIP on 7.2KV breaker.
2.
Go to Diesel Generator B (DB-436) and perform the following:
a.
Place the REMOTE / LOCAL /MAINT switch to LOCAL.
b.
Verify the Diesel Generator is running with the output breaker closed.
OV 4
FEP 1.0 ATTACHMENT ll PART SE-51 PAGE 2 OF 2 REVISION 10 NOTE 2.c 1)
XSW1DB 10 TCP, TRIPPING CNTRL PWR XEG00018 DG (RRT) for Diesel Generator B must remain closed.
2)
Electrical jumpers or lifted lead procedures must not be used to close the Diesel Generator output breaker.
If the Diesel Generator B output breaker is not closed, investigate cause c.
and attempt to start Diesel locally and close its output breaker.
v i
(
FEP-1.0 ATTACHMENT ll PART SE 52 PAGE 1 OF 1 REVISION 10 SHIFT ENGINEER NOTE This Part applies to fire in Zone AB-1.18.1.
1.
Obtain keys and flashlight from the Control Room.
2.
Close XSW1DB104B, MAIN INCOMING BREAKER as follows (AB-463):
a.
Place 43 ES36, XFER UNIT 4B, to LOCAL.
B.
Momentarily place SS-ES36, UNIT 4B, to CLOSE.
O l
l 1
i l
-l
. = _.. -
FEP-1.0 ATTACHMENT 11 PART SE-53 PAGE 1 of 2 l
REVISION 10 SHIFT ENGINEER MQlE This Part applies to fire in Zones 1B 25.1.3 and 18-25.1.5 CASE II.
i 1.
Obtain keys and flashlight from the Control Room.
2.
Within 30 minutes, start the Turbine Driven Emergency Feed Pun v follows:
(
Open XVG028028-MS, MS HEADER C EF PUMP TURBINE SUPPLY l
a.
b.
Take the emergency stairs to the IB-412 (next to TDEFP Room).
If necessary, reset the throttle valve XVT02865-MS, EF PUMP TURB c.
MAIN STEAM THROTTLE VALVE (18 412).
d.
Open IFV02030 MS, EF PUMP TURB STEAM SUPPLY FLOW CONT VLV as follows (18-412):
1)
Close IFV02030 AV1 MS, IA ISOLATION VALVE FOR l
IFV2030-MS.
2)
Vent IFV02030-PR1 MS, IA SUPPLY PRESS REG FOR l
IFV2030-MS.
Ensure full turbine speed as follows (IB-412):
e.
l 1)
Close ISYO2034 AV1 MS, IA ISOLATION VALVE FOR ISY2034.
2)
Vent ISYO2034-PR1 MS, lA SUPPLY PRESS REG FOR ISY2034.
l f.
Verify Turbine speed increases to greater than 4000 RPM on ISl13505 EF (EF Pump Turbine Tachometer).
3.
Close the following drains (18-412):
XVT02803A MS, EF PP TURB MS THROTTLE VLV DRAIN VLV A.
a.
j b.
XVTO2804A-MS, EF PUMP TURBINE CASING STEAM DRAIN VLV.
4O I
l l
FEP-1.0 ATTACHMENT ll l p PART SE-53 i \\
PAGE 2 of 2 REVISION 10 XVT02804B MS, EF PUMP TURBINE CASING STEAM DRAIN VLV.
c.
4.
Within 30 minutes, feed the steam generators as follows:
Evaluate local instrumentation. The most reliable instrument for all fires a.
i is Ll-497B, SC C WIDE RANGE LEVEL (CREP).
b.
Coordinate with the Control Room Supervisor to maintain between 50%
and 60% WIDE RANGE LEVEL by throttling the following (18-423):
1)
IFV03536-EF, SG A TURB DR EF PUMP FLOW CONTROL VALVE.
2)
IFV03546-EF, SG B TURB DR EF PUMP FLOW CONTROL VALVE.
3)
IFV03556-EF, SG C TURB DR EF PUMP FLOW CONTROL VALVE.
If Control Valves cannot be throttled, then adjust Turbine speed to c.
control feed rate.
l 4
1 1
+
. =.
FEP-1.0 i
ATTACHMENT ll PART AB-54 3
PAGE 1 OF 1 t
REVISION 10 AUXILIARY BUILDING UPPER OPERATOR
.N_OTE 1.
This Part is to be performed in conjunction with the duties specified by FEP 2.0.
i 2.
This Part applies to fire in Zones CB-12, RB-1.1.1 and RB-1.3.2.
j 1.
Within 90 minutes, close XVT08100-CS, RC PUMP SEAL RETURN HDR ISOL VLV (ORC)(AB-412 West Pen).
j i
l l
l 2
l O
l
FEP-1.0 1
6' ATTACHMENT ll PART AB-55 PAGE 1 OF 1 REVISION 10 AUXILIARY BUILDING UPPER OPERATOR NOTE 1.
This Part is to be performed in conjunction with the duties specified by FEP-2.0(3.0).
2.
This Part applies to fire in Zones IB-3,18-4, and 18-25.1.2.
1.
Do not perform FEP 2.0(3.0) ATTACHMENT XI, CROSS TRAIN CONNECTION OF BATTERY CHARGER XBC1 A-1B.
V I
l i
!!O I
l
FEP 1.0 ATTACHMENT 11 h
PART AB-56 PAGE 1 OF 1 REVISION 10 AUXILIARY BUILDING UPPER OPERATOR NOTE 1.
This Part is to be performed in conjunction with the duties specified by FEP-3.0.
2.
This Part applies to fire in Zone IB 5.
1.
Do not perform FEP-3.0, ATTACHMENT XI, CROSS TRAIN CONNECTION OF BATTERY CHARGER XBC1 A 1B.
2.
Contact the Control Room and verify that Bus 1 DA has been de energized, then perform the following (18-412):
a.
Open all breakers on DPN-1HA except M and 19.
I b.
Open all breakers on DPN-1HA1 except 10.
O O
_. ~ _. _ _
FEP-1.0
)
ATTACHMENT 11 p
PART AB-57 i
PAGE 10F 1 REVISION 10 AUXILIARY BUILDING UPPER OPERATOR NOTE 1.
This Part is to be performed in conjunction with the duties specified by FEP 3.0.
2.
This Part applies to fire in Zones 18-25.6.1,18-25.6.2 and IB-25.7.
Within 90 minutes, start XFN47 at XPN 5529-VL as follows (AB-388, behind 1.
Charging Pump C Transfer Switch):
Place 43-VLO7 XFER, XPN0040 (XFN47) in LOCAL.
a.
B.
Place SS-VLO7X, XPN0040 (XFN47) to START.
l l
+
4 O
I
i FEP 1.0 ATTACHMENT ll i
PART 18-58 PAGE 1 OF 1 REVISION 10 INTERMEDIATE BUILDING OPERATOR 1
NOTE 1.
This Part is to be performed in conjunction with the duties specified by l
FEP-3.0.
2.
This Part applies to fire in Zones 18-25.1.3 and 18-25.1.5 CASE 11.
1.
Within 30 minutes, isolate blowdown by closing the following valves (TB-424):
XVT00542A-BD, SG A BLOWDOWN HEAT EXCHANGER INLET a.
VLV.
3 b.
XVT005428-BD, SG B BLOWDOWN HEAT EXCHANGER INLET VLV.
l XVT00542C-BD, SG C BLOWDOWN HEAT EXCHANGER INLET c.
VLV.
l i
i i
i
FEP-1.0 RT B-9 PAGE 1 OF 1 REVISION 10 INTERMEDIATE BUILDING OPERATOR NOTE 1.
This Part is to be performed in conjunction with the duties specified by i
FEP-3.0.
2.
This Part applies to fire in Zones (CASE il only) SWPH 2, SWPH-5.1.3 i
and SWPH-5.2.3.
1.
Within 90 minutes, start XFN 80B AH (SW-440, behind XSW1EB1) as follows:
l a.
Place 43 AH327 XFER, XMC1EB1X U4FH in LOCAL.
j B.
Place SS AH 327X, XMC1EB1X U4FH to START.
O l
l I
lO
l
's FEP-1.0 ATTACHMENT ll PART IB-60 y
PAGE 1 OF 1 REVISION 10 INTERMEDIATE BUILDING OPERATOR NOTE 1.
This Part is to be performed in addition to the duties specified by FEP-2.0.
2.
This Part applies to fire in Zones SWPH 4.1 and SWPH 4.2.
1.
After completing FEP-2.0 ATTACHMENT IV, provide portable ventilation equipment to cool the Service Water Pump Room and the XSW1EA Switchgear Room.
- O
.,