Georg'a Power Compan/
i 333 P.edracnt Avenue edarta, Georg.a 30308 Tetephone 404 5266526 j
Maung M1ress Post Othce Box 4545 Adarta. Georgia 30302 h,c e's nt the soahcen c;cctrc s,wxn S
Nuclear Operatons VL-51 0014e X7GJ17-Y600 August 30, 1988 U. S. Nuclear Regulatory Comission ATTN: Document Control Desk Washington, D. C.
20555 PLANT V0GTLE - UNIT 1 NRC DOCKET 50-424 OPERATING LICENSE NPF-68 WITHDRAWAL OF PROPOSED REVISION TO TECHNICAL SPECIFICATION 3.2.2 Gentlemen:
On May 19,
- 1988, Georgia Power Company (GPC) proposed to amend Specification 3.2.2 of the Vogtle Electric Generating Plant Unit 1 Technical Specifications Appendix A to Operating License NPF-68.
GPC hereby withdraws that request for reasons discussed herein.
On January 27, 1988, GPC learned of new information related to the effect of the "as built" containment spray system flowrates upon the peak clad temperature calculated as part of the FSAR large break LOCA analysis.
To address this new information, GPC committed in letters SL-4072 and SL-4065 dated January 29, 1988, to op(rate Unit I with an administrative 1y controlled value for the Heat Flux Hot Channel Factor Fo(z) of 2.25 and requested a tecoorary exemption from compliance with 10CFR50.46.
The NRC response cordained in your March 10, 1988 letter, requested that GPC propose an amendment to Yogtle Electric Generating Plant Technical Specifications to incorporate the revised Fg ifmit (i.e. 2.25).
The NRC's letter also stated that a license amendment request to change Fg back to 2.30 at 100% power should be submitted when an analysis had been completed using the increased containment flowrate.
The proposed change to the Technical Specifications was made by our letter SL-4442 on May 19,1988, and is currently being reviewed by the NRC.
Since that time, an analysis has been completed which included the increased containment flowrate.
This analysis confirmed the acceptability of an Fg value of 2.30 at 1005 power.
A report on this analysis will be submitted for NRC review and concurrence in early September,1988.
pol G809070399 SG0830
,e PDR ADOCK 05000424 P
o,
.g Ge ugia Power d U. S. Nuclear Regulatory Comission August 30, 1988 Page Two t'
On the basis of this analysis, Georgia Power Company hereby withdraws the proposed change to the Technical Specification 3.2.2 contained in its letter SL-4442.
During fuel cycle 1, Georgia Power Company will continue to operate i
Plant Yogtle using an Fg of 2.25 until the NRC has completed its review of the revised analysis.
In accordance with 10CFR50.91, Mr.
J.L. Ledbotter of the Environmental Protection Olvision of the Georgia Department of Natural Resources will be sent a copy of this letter.
If you have questions or coments in this regard, please contact this office.
Sincerel,
W. G. Hairsto III WEB:llh c: Georgia Power Company Mr. P. D. Rice Mr. G. Bockhold, Jr.
GO-NORMS U. S. Nuclear Regulatory Comission Dr. J. N. Grace, Regional Administrator Mr. J. B. Hopkins, Licensing Project Manager, NRR (2 copies)
Mr. J. F. Rogge, Senior Resident Inspector - Operations, Yogtle State of Georgia f
Mr. J. L. Ledbetter, Environmental Protection Division, Georgia Department of Natural Resources l
0014e P
.