Lawrence LivemxwecMgional Laboratory L_- j vC ON rrn _,
CIl]: $ j O
regia: yoc N UC LE A R SYSTEMS SAFETY PRO G R A M February 4,1986 Mr. To m DiGalom a Resource Management and Administration U.S. Nuclear Regulatory Com mission, Region V 1450 M aria Lane, Suite 210 Wainut Creek, C A 94596
Dear Mr. DiGaloma:
Attached please find D R AFT 189 proposal:
" Readiness Review, Construction Assurance Program Inspector of W N P-3."
If this proposal meets with your approval, we willrequest formal approval by the LLN L m anage m ent.
Sincerely, Y
une Stuart, Asst. Resource Manager uclear Systems Safety Frogram cc:
J. M. Johnson R. L. Wrlte W. P. Ang g*e-8602250332 860221 ADOCK 0 % yB pga G
fn EqualCtprtwnyEnpopr* UnersitydCaMme = RO Bow 800 Lhemus CaRme 94550
- Tenephone(415)422-1100
- Twx 910-386-8339 UCLLL LVMR
nne..., m us.nuo6sAnnaciaaTonYcomensson oATsorPaeresA6 isen 1/24/86 I
I PROJECT AND SUDGET PDOPOSAL POR NRC WORK yms.
l Elaeveienneo.
I Pimnueosn rnesset t TLs Readiness Review. Construction Assurance Program Ins'pection of WNP-3 Imaceeamuwsen NRC of PICE l
NRC Region V - Walnut Creek. California I
l E iis's"sn * " " " l 003 cowTnAcTom University of California - Lawrence Livermore National' Laboratory I
i l oos sea munesen l
Livermore, California l
I coonizA=T Psneo==sk onsAmiaATion nsPMoNeNUbeggg p--- WPen -Z - ^ ="
NRC PROJECT MANAQ EA l STAATING DATE l
W. P. Ang NRC FTS-463-3700 1 4/01/86 I
QTHER NRC TECHNICAL sTAPP COMPLETION DATE
)
9/30/86 DOE PROJECT M AN AQ EM W. Gallagher DCE/ SAN FTS-536-7916 45NTAACTom-PaosEcT MAN 4aan Garth Cummings LLNL PIS-532-4949 PRINJPAL INVEsTIG ATomts)
Robert L. White LLNL-NV FTS-575-2411 J. M. Johnson (Resource Manager)
LLNL FTS-532-4948
~ " '
sTAPP vsAns os erPonT rae==4 se nes,ese senen era p rs lPY 86 FY FY PY FY FTE
.25 oowe Direct (or=eed l
3 l TOTAL oinsCT STAPP YEARS
.25 cost PRCPosAL 5K l
l 15 Meeertes and serv 6ese(Emesanne Aort AD'
- _o_
_o_
l ommestie 4
l ladirect Labor Caets 15 Recharge 1
l l
ceaers end Administratia ( 15 51 5
l TOTAL openAriwo cost 40 CAPITAL EQUIPMENT
]
PIN CHARGED:
N/A l
TOTAL PaoJEc7 cost
$40K 86 ociosta movsmosa osciusta w waar essawaar waaca
,y Mowtmv roascAsv I
sxrviss Ar*4 uAv Juns an.v AvewsT sectawasa 10K 10K 10K 10K g, au i..
NRC P Ames 999, U.S.kUCLE AR REOWLATORY CO6ahassesON pen Muheets
- ' 8 PROJECT AND BUDGET PROPOSAL FOR NRC WORK 2ATa 1/24/86-PROJECT E4TLE Re diniss Review, Construction Assurance Program Inspector of WNP-3
..g 1 DOE mOPOSING OAGAM82ATION Univsraity of California - Lawrence Livermore National Laboratory FORECAST MILESTON E CHA:tT: Seseuesd to Start - M -Compeeted(Jibown se gisertar Yasr/
PROVIDE ESTIMATED DOLLAR COST FOR EACH TASK FOR EACH FISCAL YEAR TASK FY FY FY FY FY ist l2ndl M l 4th ta l 2nd lM l 4th t ot l2ndl Ml4tti in l 2ndl 3rdl4th in l 2ndl 3rdl 4th TcCk 1 - Review and SCHEDULE M
IntpICt Construction
~
WNP-3 COST
$40K SCHEDULE COST SCHEDULE COST SCHEDULE COST SCHEDULE i
COST TOTAL ESTluATED PROJECT COST
$40K l
PROJECT DESCRIPTION: iPro sde narrasse dracrpoons of the foddoweny tapacs an she orper tatsuf. Atssch on pleen paper so Ins NAC Form 189. If en stem a
,,etappews.a,. :
- 1. CBJECTIVE OF PROPOSED WORK ll. Meetings and Travel
- 2.
SUMMARY
OF PRIOR EFFORTS
- 12. NRC Furnished Material
- 3. WORK TO 8E PERFORMED AND EXPECTED RESULTS 13 Proprietary Data
- 4. DESCRIPTION OF ANY FOLLOWCN EFFORTS I4, Patent Status
- s. ret 4 TION $wiP TO OTHER PROJECTS 15 Task 'X' On Call Assistance
- 6. REPORTING SCHEDULE
- 16. SumariZe Deliverables
- 7. SU8 CONTRACTOR INFORMATION
- 17. Resumes
- s. LIST NEW CAPITAL EQUIPMENT REQUIRED
- 9. DESCRIBE SPECIAL FACILITIES REQUIRED
- 10. LONFLICT OF INTEREST INFORMATION SEE NRC MANUAL CH APTER 1102 FOR ADDITIONAL INFORMATION APPKUV AL AUTHORITY-SIGN ATUR E lDATE
L'
'4 W
-T
. o -.i er Statement of Work Project
Title:
Readiness Review, Construction Assurance-FIN'No.
Program Inspection of WNP-3 B&R No..
..................................L.........
NRC Project Manager:
W. P. Ang Estimated Level of Effort:
.25 Staff Year Projected Completion Date: September 30, 1986 BACKGROUND Readiness Review Construction Assurance Program inspections involve the examination of the licensees procedures, completed work," and records.
Assistance is needed to review and inspect specialized aspects of geology, civil engineering and civil / structural engineering disciplines.
1.
OBJECTIVE The objective of this project is to provide technical assistance in the review and inspection of the WNP-3 Readiness Review Construction Assurance Program (CAP) modules scheduled for the third and fourth quarters of FY 86.
Review of f,our modules are enticipated during this time period.
2.
SUNMARY OF PRIOR EFFORTS LLNL has been participating in inspection projects' at San Onofre, Unit 1 and at Diablo Canyon, Units 1 and 2.
The prior work at San Onofre was completed on FIN A-0754 while the work at Diablo Canyon was completed on FIN B-8552. LLNL has established a background and familiarity with both of these plants that enables them to maintain a continuity of work effort.
3 WORK TO BE PERFORMED AND EXPECTED RESULTS Provide the services of a specialist in the field of geology and civil /
structural engineering to perform four cap inspections along with a Region V inspector.
The inspection effort will be performed in approximately three week increments. The first week will be devoted to inspection preparation in RV involving review of licensees NRC inspection and enforcement history for the subject area, definition of critical inspection elements for the subject area, review of the licensee's module report for the subject area, and assisting in the preparation of an inspection plan for the subject area.
~~
~
^
- 4 e
es Project
Title:
Readiness Review, Construction Assurance FIN No.
B&R No.
Program Inspection for WNP-3 3..............
3 WORK TO BE PERFORMED AND EXPECTED RESULTS (cont'd)
The second week will involyg WNP-3 on-site inspection in satsop, Washington. The inspection 'will be performed under the direction of an NRC inspector and in accordance with the NRC prepared inspection plan.
Any deviations from requirements which are identified during the inspection will be re-examined by the NRC prior to documentation and disposition.
The third week will be devoted to documentation of the inspection effort and assistance in preparing the Readiness Review Module Acceptance /
Disapproval Report.
Level and Effort and Period of Performance The level of effort is estimated at.25 staff years over a 6 month period ending June 1986.
4.
DESCRIPTION OF ANY FOLLOW-ON EFFORTS - N/A s
5.
RELATIONSHIP TO OTHER PROJECTS - N/A 6.
REPORTING SCHEDULE i
A.
Monthly Business Letter Report - A business letter report is to be
)
submitted by the 15th working day of each month to the Region V Project Manager, with copies to Tolbert Young, Chief, Engineering i
Section, Division of Reactor Safety and Projects, and T. DiGaloma, j
Resource Analyst Region V, covering, as a minimum:
A listing of any efforts completed during the period; milstones reached, or if missed an explanation provided; The amount of funds authorized to date and the amount of funds expended for both manpower and computer services during the period and cumulative to date for the projects; Any problems or delays encountered or anticipated and recommendations for their solutions; 1
A summary of the progress to date; Plans for the next reporting period.
l 1
l l
l l 1
j
\\
[ *'
.... 3
~,,..e, Project
Title:
Readiness Review, Construction Assurance FIN No.
Program Inspection of WNP-3 B&R No.
B.
Technical Letter Report - A technical letter report shall be submitted periodically to the Region V Project Manager.
Th,is letter report shall contain the following information:
A listing of all inspections completed during the reporting period (exclude items identified in previous reports);
A listing of the criteria (codes and standards) each modi-fication was inspected against; The results of each inspection, specifying any identified deviations from the evaluation criteria; The dates the inspections were conducted.
7.
SUB-CONTRACTOR INFORMATION Inspection may be conducted in part by employees of EG&G, Inc. - Energy Management Group (EMG) located in offices in San Ramon, California. EG&G EMG is under contract to DOE and has been providing assistance to LLNL-NSSP through the SANL contracts-division.
8.
LIST NEW CAPITAL EQUIPMENT REQUIREMENTS - N/A 9.
SPECIAL FACILITIES REQUIRED - N/A 10.
CONFLICT OF INTEREST INFORMATION The contractor shall assure that participants are not placed in a conflict of interest situation based on their inspection of NRC licensees.
11.
MEETINGS AND TRAVEL During the period of this work travel is required four times to and from the site by each assigned engineer (cost estimates reflect four roundtrip airfaces. Additional local travel is anticipated between LLNL and the NRC Region V offices for planning and progress meetings.
12.
NRC FURNISHED MATERIALS Copies of codes, standards, procedures, specifications,.and miscellaneous tools and supplies such as flashlights and weld gauges considered necessary by the NRC Project Manager or inspectors will be provided by the NRC or will be procurred from LLNL sources at NRC expense...
gp Project Titles' Readiness Review, Construction Assurance FIN No.
Program Inspection of WNP-3 B&R No.
13 PROPRIETARY DATA "In the event any proprieta,ry information is submitted by the NRC in connection with this project, it must be specifically identified. The University agrees to exercise its best efforts to protect such proprietary data. Furthermore, limitation shall not be imposed on the use of any information and data previously delivered to the University or government without limitations or previously published in any form as to be generally available."
14.
PATENT STATUS This proposal is being transmitted in advance of patent review for evaluation purposes only.
No further dissemination or publication shall be made without prior approval of the Assistant General Counsel for Patent, DOE.
- 15. TASK "X" ON-CALL ASSISTANCE - N/A
- 16. SUMMARIZE DELIVERABLES The deliverables are monthly business letter reports and technical letter reports as required to summarize inspection periods and activities.