ML20153E031

From kanterella
Jump to navigation Jump to search
Forwards Response to NRC Re Violations Noted in Insp Rept 50-424/88-14.Believes That Notice of Violation for Insp Rept 50-424/88-14 Incorrectly Refers to Unit 2 by Docket Number.Response Withheld (Ref 10CFR2.790 & 73.21)
ML20153E031
Person / Time
Site: Vogtle Southern Nuclear icon.png
Issue date: 04/29/1988
From: Mcdonald R
GEORGIA POWER CO.
To:
NRC OFFICE OF ADMINISTRATION & RESOURCES MANAGEMENT (ARM)
References
SL-4547, NUDOCS 8805090367
Download: ML20153E031 (2)


Text

as un, cvm

(

m r.

e.. m.;

j e a~ an ~. v =

T4

' e 404 EN MI6

(

, SAFECUAP05 N

)

A n

m s_

rj n m e, a5 5

( ENCLOSURE CONIAWIS S.M M l 1

L e

c.:,;:, r < :

(

UPON SEPARAT10N THIS PW 5 N 1

Georgia Power Executive Department IV' 5 MW" (W' c S c

?

SL-4547 0886m X7GJ17-V120 April 29,1988 U. S. Nuclear Regulatory Commission ATTN:

Document Control Desk Washington, D.C.

20555 PLANT V0GTLE - UNIT 1 NRC DOCKET 50-424 OPERATING LICENSE NPF-68 REPLY TO A NOTICE OF VIOLAHON Gentlemen:

In accordance with the provisions of 10 CFR 2.201, Georgia Power Company (GPC) hereby submits the enclosed information in response to NRC Inspection Report 50-424/88-14 which concerns the inspection conducted by Messrs.

A.

Tillman and D.

Thompson of the NRC Region II staff on February 22-26, 1988.

A copy of this response is being provided to the NRC Region II office for review.

We believe that the Notice of Violation for NRC Inspection Report 50-424/88-14 (as submitted by NRC Region II letter dated March 30,1988) incorrectly refers to Plant Vogtle Unit 2 by docket number and as a resul t implies that it is in violation also.

The Inspection Report "De tail s" section specifically identifies the violations as being applicable to Plant Vogtle Unit 1

by the violation designators "50-424/88-14-02,"

"50-424/88-14-03,"

"50-424/88-14-04,"

and "50-424/88-14-05."

While Paragraph 14 in the Report Details section of the subject inspection report does not contain a violation designator, it is our belief that the violation in question pertained to Plant Vogtle Unit 1 and should have been designated as 50-424/88-14-01.

Accordingly, our response addresses only Plant Vogtle Unit 1.

In each of the enclosures, transcription of the NRC violation precedes GPC's response.

f The information contained in the enclosures is safeguar* f nfomation l

and, in accordance with 10 CFR 2.790 and 10 CFR 73.21, should not be l

placed in the NRC f.3blic Document Room.

b l

~

ii-- seURMATION

)

l MWWassetGUARDSINFORWl0N

)

M QlBSS PAGE LS DECONTROLLED

)

C805090367 880429

{

l PDR ADOCK 05000424 0

DCD l

t_

3

(

sARouARot m ontArioIL

)

Georgia Power d

( ENCLOSURE CONTAINS SAFEGUARDS WORMATION )

s

(

UPON SEPARAil0N THIS PAGE IS DEMTROLLED

)

U. S. Nuclear Regulatory Commission April 29,1988 Page Two Should there ce any questions in this regard, please contact this office at any time.

Sincerel, ' f,l

/

l I S, R. P. Mcdonald Executive Vice President, Nuclear Operations JAE/Im

Enclosures:

1.

NRC Notice of Violation "A" and GPC Response 2.

NRC Notice of Violation "B" and GPC Response 3.

NRC Notice of Violation "C" and GPC Response 4.

NRC Notice of Violation "D" and GPC Response 5.

NRC Notice of Violation "E" and GPC Response c:

Georgia Power Company Mr. P. D. Rice w/o enclosure Mr. G. Bockhold, Jr. w/ enclosure Mr. J. H. Lukehart w/ enclosure Mr. J. E. Swartzwelder w/o enclosure Mr. F. R. Tininons w/o enclosure GO-NORMS w/o enclosure U. S. Nuclear Regulatory Connission Dr. J. N. Grace, Regional Administrator w/ enclosure Mr. J. B. Hopkins, Licensing Project Manager, NRR (2 copies) w/o enclosure Mr. J. F. Rogge, Senior Resf dent Inspector-Operations, Vogtle w/o enclosure 0886m mm