Confirms G Shear Site Visit on 880906 Re Emergency Response Facilities Per 880815 Telcon Between P Skiermont & G Shear. Outline of Areas for Review Encl
ML20153C408
Person / Time
Site: Quad Cities  Constellation icon.png
Issue date: 08/24/1988
From: Shafer W
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To: Reed C
COMMONWEALTH EDISON CO.
References
IEIN-86-016, IEIN-86-16, NUDOCS 8809010127
Download: ML20153C408 (3)


Text

.

9 AUG 2 41988 Docket No. 50-254 Docket No. 50-265 Commonwealth Edison Company ATTN: Mr. Cordell Reed Senior Vice' President Post Office Box 767 Chicago, IL 60690 Gentlemen:

Based on the August 15, 1988, telephone conversation between Mr. Paul Skiermont of Quad Cities Nuclear Generating Station and Mr. Gary Shear of my staff, it is my understanding that September 6, 1988, was agreed upon as the date for Mr. Shear's site visit to tour the emergency response facilities of the Quad Cities Nuclear Power Station.

Recent experience in the Fed.eral Field Exercise identified the need for Region III to evaluate each licensee's emergency response facilities to determine if the NRC's Expanded Activation Site Team can be adequately accommodate. IE Information Notice No. 86-16 described the planned composition and location of the NRC Site Team that would respond to a major '

nuclear power plant accident.

Region III does not expect licensees to backfit to provide increased facility space. Facilities that have been constructed and approved under current regulations and guidance may not have the capability to accommodate the NRC Expanded Site Team as outlined in Information Notice 86-16.

Our goal is to consider with each licensee, ways of making more efficient use of available space, of providing adequate communications, and of identifying alternate spac where relevant data could be made available in a timely, reliabic manner.

Attached to this letter is an outline of the areas we will be reviewing. If there are questions regarding any of the above, please contact' Gary Shear at (312) 790 5620.

Sincerely,

  • 0rldtini signM 4 P.D. Mer" 9809010127 880824 PDR W. D. Shafer, Chief F ADOCK 05000254 PNV Emergency Preparedness and Radiological Protection Branch

Attachment:

As stated See Attached Distribution l R!! Rf!I RIII RII < /

l iSs A Uiears ib wu Snell

  • Rirg aK WP y/ #  ;

kt)/88 , g l N

Comonwealth Edison Company 2-

'AUG 2 4' 1988 Distribution cc w/ enclosure:

-H. Bliss, Nuclear.

Licensing Manager-R.=L. Bax, Plant Manager

< DCD/DCB (RIOS)

~ Licensing Fee Management Branch Resident-Inspector, RIII-

  • Richard'Hubbard J. W. McCaffrey, Chief, Public Utilities Division John Golden, Ceco-Paul Skiermont, .QCPS Robert Hgjec, CECO

. p. ..

2 l

l

.. ATTACMMENT OUTLINE FOR EVALUATING LICENSEE ACCOMMODATIONS FOR NRC SITE T ,

1

1. Communications A. Telephone Capabilities
1. Number of Available Phones
2. Location of Available Phones
3. Type of Phone Service (e.g., voice activated) l B. Computer Compatability II. Size and Layout of TSC and EOF A. Space Availability for Expanded Site Team B. Seating and Desk Arrangements for Expanded Site Team C. Location of Key Counterpart Licensee Personnel D. Conferencing Space for NRC Personnel

!!!. Alternate Space I

l l

i l

1