ML20153B801

From kanterella
Jump to navigation Jump to search
Insp Rept 50-425/88-19 on 880511-0714.Violations Noted.Major Areas inspected:safety-related Supports & Readiness Review Module 11, Pipe Stress & Supports
ML20153B801
Person / Time
Site: Vogtle 
Issue date: 08/18/1988
From: Sinkule M, Vias S
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To:
Shared Package
ML20153B695 List:
References
50-425-88-19, NUDOCS 8808310096
Download: ML20153B801 (21)


See also: IR 05000425/1988019

Text

.

kO cec

UNITED STATES

oqP

,

,

.

o

NUCLEAR REGULATORY COMMISSION

'

g$

REGloN tl .

,

$

j

101 MARIETTA STREET.N.W.

c

ATLANTA, GEORGI A 30323

'+4 . . . . . $

Report No.:

50-425/88-19

Licensee: Georgia Power Company

P. O. Box 4545

Atlanta, GA 30302

Docke+ No.:

50-425

License No.: CPPR-109

Facility Name: Vogtle 2

Inspection Conducted: May 11-12, June 6-10, and July 11-14, 1988

Inspector: b k.

d

8bJD

S.J.@as,ProjectEngineer

Date Signed

Accompanying Personnel:

P. A. Balmain, Reactor Engineer, (June 6-10,1988)

i

S. Q. Ninh, Reactor Engineer, (July 11-14, 19 8

l

Approved by:

' [ /[ NT

.

.

M. V. Sir.kule, Section Chief

Dat'e Signed

Reactor Branch 3B

Division of Reactor Projects

SUMMARY

Scope:

This special, announced inspection, on site, involved the areas of

safety-related supports (Unit 2), and Readiness -Review Module 11,

Pipe Stress and Supports (Unit 2).

Results:

One violation was identified: Violation, 50-425/88-19-01, Failure to

)

Follow Procedures, Resulting in Errors in Pipe Support QC and Design

i

Documentation. See Paragraph 2.C.6) a.

'

Inspector Followup Item, 50-425/88-19-02, Potential Problems with

Spring Can Travel.

See Paragraph 2.C.6) a.(7).

8808310096 880818

PDR

O

ADOCK 05000425

PDC

_.

__. . _ -

.

-

'

.

.

.

REPORT DETAILS

1.

Persons Contacted

Licensee Employees

  • R. H. Pinson, Vice President - Construction
  • A. B. Gallant, Project Compliance Coordinator
  • J. J. Gilmartin, Mechanical Field Operations Staff
  • E. D. Groover, Quality Assurance (QA) Site Manager - Construction
  • C. W. Hayes, Quality Assurance Manager

R. W. McManus, Readiness Review (RR), Project Manager

  • W. C. Ramsey, Project Engineering Manager
  • C. W. Rau, Mechanical Discipline Manager
  • C. Garrett, Operations Engineering, Oglethorpe Power Corporation

Otner Organizations

R. Borgatti, Deputy Engineering Group Supervisor, Bechtel

Western Power Corporation (BWPC)

S. K. Gupta, Deputy Engineering Group Supervisor, BWPC

P. Patel, Engineering Group Leader, BWPC

  • 0. W. Strohman, Project QA Engineer, BWPC
  • R. C. Summerfeld, RR Team Leader, BWPC

"P. R. Thomas, RR Team Leader, BWPC

  • M. J. Beer, Technical Assistant, V-SAMU

W. E. Faires, Principal Engineer, V-SAMU

  • M. E. Maryak, Completion Manager, V-SAMU

N. R. Pasala, Mechanical Engineering Group Leader, V-SAMU

J

B. G. Schappell, Manager Mechanical Construction Support, V-SAMU

)

  • B. Edwards, Resident Construction Manager, Pullman Power

Products (PPP)

  • J. Miller, Quality Assurance Manager, PPP

R. Norton, Drafting Lead, PPP

T. Pacifico, Engineering Manager, PPP

H. Smith, Quality Control (QC) Manager, PPP

K. Weis, Chief Engineer, PPP

J. Morris, QC Inspector, PPP

i

A. Turner, QC Inspector, PPP

i

Other licensee employees contacted included construction craftsmen,

engineers, technicians, mechanics, and office personnel.

.

.

.

2

NRC Resident Inspectors

  • R. J. Schepens, Senior Resident Inspector - Construction
  • Attended exit interview

Acronyms and initialisms used throughout this report are listed in

Paragraph 4.

2.

Review of Readiness Review Module 11, Pipe Stress and Supports (Unit 2)

(50090)

A.

Scope of Review

This review consisted of an examination of GPC's Readiness Review

Module 11, Pipe Stress and Supports.

Sections 1, 2, 3, 4, and 5,

which presented data on introduction and module organization,

organization and division of responsibilities, commitments, program

description, and, audits and inspections.

These did not require as

extensive a review as Section 6, which covered program assessment.

The evaluation of Section 6 included an examination of content,

review of findings and conclusions, review of a small sample of items

previously riliewed in the Readiness Review Program, and review of an

independert y selected sample of documents,

both- design and

construction, and a field construction inspection. The methodology

used and an evaluation of each section are presented in the following

section.

B.

Methodology

The NRC review performed was concerned with all sections of the

report, but focused on Section 6.

The entire Module was read and

I

reviewed for organization and content after its receipt on April 19,

1988.

The Region II inspectors conducted one on-site preliminary set-up

meeting.

This was followed up with two on-site inspections at the

Vogtle Electric Generating Plant (VEGP) Unit 2.

The first visit to the Vogtle site, made on May 11-12, 1988, was to

discuss with licensee and Readiness Review personnel, the scope and

inspection plan for the evaluation of this module. The inspector was

able to identify the systems, P&ID's, isometrics, and pipe supports,

that were to be inspected and reviewed during the upcoming inspection

periods.

The

first

inspection also

invo'ived the following

accivities:

j

o

Reviewing the description of the Readiness Review program and

establishing organizational responsibilities for Module 11,

o

Verifying Module 11 review boundaries,

-

.

'

.

.

.

3

o

Inspecting and reviewing an independent sample of P& ids 'and

piping isometrics to be used in the assessment of Section 6 of

the Module 11 report,

A sample of five P&ID's covered by thirteen piping isometrics, having

56 associated pipe supports was selected to form

basis for the

o

detailed assessment of the Construction Program.

The isometrics

chosen represent a diversity of pipe systems, sizes, locations, and

pipe class.

The second inspection, was made during June 6-10, 1988, involved the

following activities:

o

A detailed walkdown of the piping systems, and pipe supports

previously identified,

o

A detailed review of the construction documentation for the

items inspected in the field,

o

An assessment of the one Level II finding reported in Section 6,

of the Module 11 report and a brief review of the 7 Level III

findings.

An evaluation of the Construction Program was made by performing a

field inspection of all piping installation and pipe supports

included in the selected sample of five P& ids, thirteen piping

isometrics and 56 pipe supports.

In addition to this field inspec-

tion, all of the Pullman Power Products (PPP) Quality Control (QC)

_

documents associated with the thirteen piping isometrics and 56 pipe

supports were reviewed for conformance to specifications and

procedures, and for compliance with design drawings.

Finally,

an

assessment was

made

on

the Level II

finding

(2RRF-011-002), resulting from Readiness Review's Program Assessment

Section. This finding involved PPP project procedures not clearly

defining authority, responsibilities, and limits of field engineers

performing verification of construction activities versus the

authority,

responsibilities,

and freedom of

quality control

inspectors

to perform

inspections

and witness

construction

activities.

The second on-site inspection was conducted during July 11-14, 1988,

included the following activities:

o

Performing a Construction Program review of findings from the

first inspection with the appropriate PPP personr.el,

o

Accomplishing general Module il review activities,

o

Performing a Design Program review, for the piping and supports

inspected during the first inspection on-site.

.-

,

.

..

-

-.

.

.

.

4-

General review activities included an assessment of the information

presented in Sections 1, 2, 4, and 5 of Module 11.

An evaluation of the Design Program was made by reviewing a sample of

the stress calculations for the thirteen selected piping isometrics

and their 56 associated pipe supports.

These calculations and

related design criteria, drawings, and change documentation were

reviewed for adequacy of design control, adherence to criteria and

procedures, and design integrity.

C.

Evaluatien

The evaluation of each Module section is provided below in the

section-by-section format used in the Module 11 report. Incitjed are

a description of the section, subject matter reviewed, basis for

j

acceptance, and statement of required follow-up or evaluation.

1)

Section 1 - Introduction

This section presents the scope of Module 11, outlines the

Module organization, and reports the project status.

The

section was examined by the NRC inspectors for appropriateness

of scope and for background information.

a.

Boundary Definition.

Module 11 included those activities

-

(stress analyses and pipe support design) for ASME, B&PV

Code, Section -III, Classes 2 and 3 piping within the scope

of Bechtel Western Power Corporation (BWPC) and Vogtle

Structural Analysis Mobile Unit (V-SAMU). The installation

of piping,Section III, Classes 2 and 3,

and mechanical

equipment were not covered in this module. The design and

construction of piping systems in the Nuclear Steam Supply

System (NSSS), were not included this module.

Also

i

contained in Module 11 were stress analyses of non-safety

related piping that must meet Seismic Category 1 require-

ments for protection of safety-related components.

The NRC inspectors found the description of Module 11

boundaries to be acceptable,

b.

Project Status.

Subsection 1.3 of Module 11 presents the

project status for design and construction of small-bore

and large-bore pipe supports.

Percentages of completion

were quoted as of September 1987.

These percentages were

shown as 77% completion for design of small-bore and 86%

completion for design of large-bore pipe supports, and with

7% completion of the analytical stress reconciliation

packages. On the construction side, it was shown as 56%

completion for installation of small-bore supports, and 86%

completion for installation of large-bore supports.

The NRC inspectors determined that the project status indicated

significant progress in the pipe support program.

,

.

.

5

2)

Section 2 - Organization and Division of Responsibility

This section describes the organizations . involved.in design and

construction for Module 11.

It explains what personnel are

responsible for specific design and construction activities, and

presents the matrix organization used by the architect /~

engineering contractor on the project.

This section was

reviewed by NRC inspectors for content and accuracy.

In the

process of this review, the responsibilities of the various

organizations and personnel within the organizations were

clarified.

The NRC inspectors had nu findings in this section.

3)

Section 3 - Commitments

This section contains listings of commitments and implementing

documents, which are displayed in two matrices.

The first

matrix, entitled "Commitment Matrix," identifies all of the

Module 11 commitments, their source documents subject and

feature. The second matrix, entitled "Implementation Matrix,"

lists the document or plant feature for each commitment, as

discussed in the source document, and the project document in

which the commitment is implemented.

During the review of Unit 1 Readiness Review of Module 11, it

was noted that two commitments contained in the FSAR were

omitted from the RR review of commitments.

This matter was

followed in Inspector Fellowup Item 50-424/86-62-01. This

inspector reviewed this matter during a later inspection and was

documented in NRC Inspection Report 50-424/86-116. This matter

was considered closed.

The ir,spection conducted at this time.

was not directed toward verifying this Readiness Review section.

4)

Section 4 - Program Description

This section describes procedures, documentation, control for

design and as-built and reconciliation activities; equipment and

material; site material control; and fabrication, installation

and inspection. The section was examined by the NRC inspectors

for content and background information. Some of the background

was useful in the review of later sections in the Module,

especially Section 6, Program Assessment.

a.

Design.

Subsection 4.1 divides the description of the

design program into several categories including the pipe

stress and pipe support design process; design criteria;

design documentation; design control and review; and design

change control.

This subsection describes the design

program from its earliest phase of design criteria

development

to

its

final

phase of design program

verification.

The NRC review of this subsection revealed

that the information presented therein gave a descriptive

_ _ _ _ _

~

.

.

4

6

accounting of the design process and defined the division

of responsibility between Bechtcl Western Power Corporation

and Westinghouse in pipe stress analysis activities.

It

also explained the interfaces between engineering groups

involved in the design effort.

The information proved

useful for developing an understanding of the design -

program, but did not lend itself to a detailed review. The

NRC inspectors identified no findings in the design program

described in this subsection.

Results from the review of

Section 6 of Module 11 were used to ' determine how

effectively the program actually functioned,

b.

Equipment and Material.

Subsection 4.2

describes

the

process for procuring safety-relating piping supports and

components or the material used to fabricate these items.

GPC serves as the purchasing agent, in compliance with

specifications written and controlled by BWPC, for these

items and supplies them to the contractors for instal-

lation.

No findings were identified in the procurement

process.

c.

Site Material Control.

Subsection 4.3

de:cribes

the

responsibilities of the pipe support installers relative to

receipt, inspection, and control of ASME Boiler and

Pressure Vessel Code material

within the scope of

Module 11. This subsection details the change from Unit 1,

in that GPC has subcontracted receipt inspection of ASME

B&PV,Section III, components and materials to Pullman

Power Products (PPP). GPC is the supplier of ASME B&PV

Code items and materials to the NA-installers, PPP, GPC's

Nuclear Construction Team,

and Nuclear

Installation

j

Services Company (NISCO).

Materials and equipment are

i

inspected when received at the job site by GPC.

After

j

satisfactory completion of this inspection, the material is

i

placed in storage locations maintained by GPC. The NRC did

not perform a detailed examination of this subsection since

the material contained a brief description and not an

as:essment.

The NRC inspectors had no findings in thf s

subsection.

d.

Fabrication, Installation, and Inspection.

Subsection 4.4

describes site fabrication, installation and inspection

activities for pipe supports and pipe whip restraints.

It

also references specification documents that control the

inspection of these items, such as codes, specifications,

and implementation procedures.

As indicated in this

subsection, the fabrication and installation of pipe

supports was performed in accordance with Bechtel_ Western

Power Corporation's Specification X4AZ01, Division P1,

General Requirements, and Division P5, Pipe Support Field

Fabrication and Installation.

It also describes the

,

.

.

7

preparation and control of the principc1 documents used

by PPP for site f abrication, installatioa and inspection

of pipe supports.

The material ~ in this subsection is

generally descriptive and was not assessed in detail

by the NRC inspectors.

The material presented does

indicate that the basic installation program addresses

project

requirements.

Results

from the review of

Module 11, Section 6 were used to determire how effectively

the program actually functioned. The NRC inspectors had

no findings relative to the description of this program.

5)

Section 5 - Audits and Inspections

This section discusses quality assurance audits and evaluatic,ns

that have been performed . by GPC, and Bechtel Western Power

Corporation, addressing pipe stress analysis and pipa supports;

and follow up of the Unit 1 findings.

It also describes

inspections and special evaluations conducted by the NRC. This

section discusses findings resulting from these audits relative

to the design and construction programs.

The section also

i

presents three design and construction problems identified since

the completion of Unit 1, Module 11, Assessment.

The three

concerns were considered significant enough by'GPC that the NRC

was informed of their potential reportability pursuant to

criteria of 10 CFR 50.55 (e).

The findings resulting from design program audits occurred in

the design functional areas, such as calculations, drawings,

field change requests, design documentat?cn, and design changes.

In addition, the NRC inspectors determined that items related to

Module 11 and past NRC findings were included in the Readiness

Review Team data base for Audits and Inspections.

The NRC inspectors concluded that findings from previous audits

and inspections were considered in the Readiness Review Team's

assessments for Module 11.

The NRC inspectors had no findings

in this section.

6)

Section 6 - Program Assessment

This section of the Module 11 Report describes activities

undertaken to ascertain whether construction and design

1

activities were adequately controlled to ensure implementation

I

of licensing commitments and conformance with project procedures

1

and design requirements related to pipe stress analysis and pipe

supports.

The section was reviewed in two phases covering

Construction Program Verification and Design Program Verifica-

tion.

The inspectors performed detailed evaluations in both

areas which are described below.

l

l

- _ _ _ _ _ _ _ _ _ _

'

.

.

.

8

,

a.

Construction Program Verification

,

The Construction Program Verification - performed by the

Readiness Review Team consisted o f- an assessment of-

installed safety-related supports that had been As-built,

and associated steel.

Also, the implementation of design

'

and construction programs with : emphasis on significant

,

changes

in

programs,

procedures

and

organization

responsibiiities.

The program had the objective - of-

determining whether the construction control

process

functioned effectively and whether it ensured acceptable

pipe support installations.

The assessments made and conclusions reached in Readiness

j

Review's verification program were divided into the

i

following major categories:

o

Implementation of licensing commitments,

o

Followup of corrective actions which resulted frcm the

Unit 1 Readiness Review Program,

o

Project performance in accordance with the ' quality

program, procedures, and design requirements.

During the preparation by the Readiness Review Team for

construction walkdowns, the programs and procedures for the

installers of pipe supports for safety-related systems were

l

reviewed.

All programs and procedures were found to be

acceptable.

The inspectors reviewed portions of various procedures

during the evaluation of the thirteen isometrics and

56 pipe supports described below.

The inspectors found

that portions of the construction procedures adequately

reflect project requirements with one exception.

The

inspectors determined that the PPP Procedure

X-24,

Section 4.1 "As-Builting Piping

Systems

and

Related

Components", was not being properly adhered to with respect

to the incorporation of information ' redlined' on pipe

support drawings, by field engineers and QC personnel, onto

the mylars for the pipe supports by the drafting group.

This is discussed in further detail in Section (1) below.

As discussed earlier in this report, the inspectors

selected thirteen piping isometrics with 56 associated pipe

supports to form a basis for evaluating the Construction

and Design Program Verifications.

The piping isometrics

and pipe supports examined are listed in Table 1.

The

inspectors examined the construction aspects of all 56 pipe

supports by first performing a field inspection on the pipe

isometrics and pipe supports. During this inspection, the

following information was recorded:

I

-

.

.

.

9

.

o

Pipe dimensions, component. locations and orientation,

o

Support dimensions and support locations,

o

Support configuration,

o

Weld size and type,

o

Support materials,

o

NF component heat numbers,

o

Clearances between pipe and support,

o

Snubber NPT Code Dats Plate information, cold set,

traceability markings on connecting hardware,

o

Spring support NPT Code Data Plate information, travel

stop installation, traceability markings on connecting

hardware.

The information recorded during- the field inspections was

then reviewed against the Line Designation List (LDL),

Valve List, Piping and Instrumentation Diagrams (P& ids),

pipe isometrics and support drawings, all associated

documents in the PPP QC document packages, and other

miscellaneous documents. The documents included in the PPP

QC packages were Process Sheets, MFCRBs, Authorizations to

Continue Work (ATCWs), DRs, DCN-Rs, Snubber and Strut

Checklists, Weld Process Sheets, and Weld Rod Requisition

Tickets.

Arong other miscellaneous construction documents

reviewed were Requests for Support Removal,

Liquid

Penetrant Exsmination Records, Material Inspection Reports,

Maintenance Work Orders, Cortificates of Compliance, and

Certified Mill Test Reports.

Based on the inspection of pipe supports and associated

documentation, the inspectors found that the pipe support

installations were generally consistent with the documen-

tation and in accordance with project requirements.

The inspectors did, however, identify several deficiencies

I

in the construction program, which are described as

follows:

(1) During the review of the as-built information gathered

in the field, and comparing the information to the PPP

Process Packages for the individual pipe supports, it

was noted on five occasions that all the information

that was

"redlined"

per PPP

Procedure

X-24,

"As-Builting Piping Systems and Related Components",

i

i

\\

.

.

10

Section 4.1, was not properly incorporated onto the

Mylars. The. following discrepancies were found to be

properly ' redlined' and documented on a copy of the

pipe support drawing in the PPP Process Package, but

were outside the tolerance of PPP Procedure X-24, and

not incorporated into the Mylars.

o

V2-1204-014-H004, the correct size of item 'b' .

o

V2-1204-014-H006,

the ' dimension

from

the

centerline W4 to ' the centerline of the embeded

plate,

o

V2-1208-005-H007, the dimension for item #4 was

shown on the drawing as 3 5/8", the inspectors

measured in the field and the ' redline' drawing,

both indicated that the dimension was 5 1/2".

o

V2-1208-145-H017, the pin-to pin' dimension of the

spring can, drawing shows 12'-10 5/16", and the

' redline'

and the dimension the

inspectors

measured was 12'-11".

o

V2-1208-145-H016, the Bill of Materials shows

item #5 as 8" wide, the inspectors measured the

dimension as 8 3/4", this is the same dimension

as the ' redline' drawing.

This matter of discrepancies between

' redline'

information and final pipe support drawings has been

previously identified by internal audits performed by

the licensee.

An audit, documented in an internal

Westinghouse memo, from V-SAMU As-Built Completion

Group to R. W. Braddy and M.W. Barlow, dated March 15,

1988, identified similar discrepancies during a two

stage audit. The conclusion was that all the supports

were found to be acceptable, but that three had a

slight reduction in margin of safety.

In a'PPP memo,

from B.L.

Edwards to C.W.

Rau, dated February 10,

1988, PPP listed actions to be taken to minimize

future occurrences.

(2) The following drawings, both pipe support and P& ids

were found to have discrepancies between the actual

i

condition in the field and the drawing; or pertinent

information was missing from support drawing.

,

o

P&ID 2X4DB122, shows a line, designated as Line

006-8", (coordinate C-5), and just to the left of

TE 0613, should be Line 008-8".

o

V2-1208-055-H052, shows the angle iron, item 5,

in the wrong orientation.

j

.

'

.

.

.

11

o

V2-1208-055-H014, in the Location Plan, the

vertical pipe is shown as going in the (-)Y-

direction, in the field it is going 'in the (+)Y

direction.

o

V2-1208-215-H003,

-H004,

-H005,

all

three

drawings did not have a locating dimension for

the attached support (baby) in relation to a -

connection point on the parent support.

This is

contrary to PPP Procedure X-24, "As-Builting

Piping Systems and Related Corrponents", Section

6.6.

(3) The following pipe supports were found to have

dimensions on the drawings that differed from the

dimensions measured in the field by the inspectors.

The dimensions are outside the tolerance of PPP

Procedure IX-50, "Pipe Support Field Installation and

Fabrication Procedure", Section 6.2.6.G.

o

V2-1208-255-H002, the drawing shows the dimension

from the centerline of item #2 to the centerline

of the pipe as l'-4 1/4" ACT., the inspectors

measured l'-2 1/4".

j

o

V2-1204-063-H004, the location of the attachment

for V2-1204-201-H002, item #a, to the embed

plate, shows the dimension from the right side of

the embed plate to the attachment as 2 3/8", the

inspectors measured 3 1/16".

(4) The following drawings had discrepancies between the

information obtained in the field and the information

on the drawings.

During the review of PPP Process

packages for the three drawings, it was found that the

correct information was noted somewhere in the

package, but was not incorporated onto the drawings.

(Note: the correct notation of the information was not

on the ' redline' drawings.)

o

Isometric 2K3-1208-146-01, Detail 2 & 3, indicate

a class change from 212/FG0, on Line 1208-145-4"

to 414/FG4, on Line 1208-A20-1/2".

The Line

Designation List (LDL) shows 1208-A20-1/2" as

424/FG4.

DCN-R #7, dated 2-3-86, changed the

line to 414/FG4.

o

V2-1208-145-H017,

the location of the beam

attachment on the drawing shows the 'as-built'

dimension as

l'-3 1/2", documentation in the

Process package and the Final Inspection Report,

both show the dimension to be l'-2 3/4".

.

.

.

12

o

Isometric 2K3-1205-006-01, from DCN #8, the class

.

information was not transferred correctly to the

isometric.

Also,- not , all the infermation from

FEDCNR-2262, was transferred - to the 'as-built'

isometric.

(5) The following PPP Process Packages, had documentation

in the package that did not correctly reflect what was

in the field or was confusing.

o

V2-1205-004-H016, in the process package, the

' Strut Reconciliation Report" (SRR), of 5-26-87,

indicates two struts were installed, SRR of

10-14-86, shows one strut and SRR of 5-18-88,

indicates that two struts were installed.

The

pipe support drawing, (R/3), shows one strut.

There is also a discrepancy of the offset angles,

in SRR of 10-14-86, it indicates 3 degrees, SRR

of 5-26-87, indicates 2 degrees.

o

V2-1205-006-H014, the Process Package has two

different issue tickets for the spring can that

was installed, both for the same ;erial number of

B015066, they also indicate two different spring -

can sizes.

(6) The NRC inspectors while performing the inspection in

the field noted a discrepancy with respect to pipe

support V2-1204-063-H007.

The support was designed

and the drawing located the support on a 4" riser, at

elevation 208'-8", and 3'-2" . West of Column A3.

The

pipe support was actually installed at the correct

elevation, but on a different riser, approximately

l'-11", West of Column A3.

The pipe support, at

varicus times was inspected no less than three times.

PPP has inued DR PP-18138, for disposition of this

problem.

The discrepancies, in the above six items between support

installation, design informatun, construction documen-

tation and QC documentation is a violation of 10 CFR 50,

Appendix B, Criterion V, and is identified as Violation

425/88-19-01 - Failure to Follow Procedures, Resulting in

Errors in Pipe Support QC and Design Documentation.

(7) During the inspection of V2-1204-063-H005, and during

subsequent discussions with both PPP and BWPC

personnel, it was determined that the spring can

installed for this support was very close to becoming

j

topped out.

Therefore, it was agreed upon, that the

'

spring can would be monitored during hot functional

.

.

.

.

13

testing, and during the process of setting the spring

to its proper ' hot setting.'

This item will then be

followed as Inspector Followup Item 50-425/88-19-02,

"Potential Problems with Spring Can Travel."

b.

Design Program Verification

The Design Program Verification performed by the Readiness

Review Team focused on evaluation of the pipe stress

analysis activities and design of pipe supports.

Their

assessment in part was intended to evaluate the compliance

of design change activities with engineering procedure

controls.

The RR review emphasized the evaluation of

conformance of as-built data and conformance of instal-

lation and data collection activities with quality program

requirements.

The RR group intended for the assessment samples to be

selected from the same systems evaluated for Module 4,

however,

since

the

sequencing

of analytical

and

reconciliation work was controlled by the turnover

schedule, the assessment sample was altered and limited.

The NRC inspectors found that the RR sample covered all the

areas needed to evaluate the module topic, however, it was

difficult to do a complete vertical slice through their

assessment, in order to draw conclusions on the overall

program.

Therefore, the NRC inspectors were not able to

efficiently use the RR review groups sample in their

review, and chose a completely independent saniple for

review.

Documents included in the Readiness Review Team's review

and results of the review were divided intc the following

major categories-

o

Pipe Stress Analysis Packages,

o

Pipe Support Calculations,

o

Pipe Support Drawings,

o

Design Change and Nonconformance Documents,

The NRC inspectors examined all of the foregoing topics in

their review. The approach used by the inspectors in their

,

examination was directed toward evaluating the same

equipment, piping, and supports, from

? beginning of

design to the completion of construct an.

This was

accomplished by first selecting a set of thirteen piping

isometrics to form a basis for an assessment of both the

Design and Construction Program Verifications.

The piping

isometrics were chosen to obtain a diversity of pipe sizes,

..

_

.-.

'

.

.

14

pipe classes, locations, and systems. None of the thirteen-

piping isometrics selected were included in Readiness

Review's program.

The thirteen isometrics chosen had a

total of 56 associated pipe supports.

Included in this

upport sample were miscellaneous steel supports,. pipe

straps, snubbers, struts, and-spring supports. Of these 56

supports, only two pipe support drawings were within

Readiness Review's program. The piping isometrics and pipe

supports selected for evaluation are listed Table 1.

All

of the isometrics and pipe ' supports were evaluated in NRC

Region II's review -of the Construction Program . Veri fica-

tion, and a portion of the design documents associated with

these isometrics were examined in the review of the Design

Program Verification. The design documents examined by NRC

inspectors are indicated in Table 1.

The NRC assessment of

design documentation is reported as follows:

(1) Pipe Stress Analysis Packages

The following calculation packages were examined for

completeness,

inter-discipline

coordination,

conformance to design criteria and project require-

ments, consistency with drawings and installation, and

technical adequacy:

o

BJ-01-706, R/2

o

BG-01-717, R/1

o

BC-00-718, R/1

o

BC-00-725, R/0

Observations made relative to the stress analysis

review include:

'

o

The piping configuration, location of components

in the line and locations of supports, used in

the analysis was consistent with the isometric,

the installation and project tolerances, except

{

that pipe support V2-1204-063-H007, was installed

'

on

the

wrong

pipe.

See

discussion

in

Section 2.C.6).a.(6), of this report.

o

Stress limits used were in accordance with ASME

Section III Class 2 criteria for the Class 2

piping,

o

Damping values used were in accordance with

Regulatory Guide 1.61.

o

Load combinations used were in accordance with

Design Criteria DC-1017 and NUREG-0484.

.

'

.

.

15

i

o

. Stresses for the faul.ted condition were within

allowances specified in ASME Code Case 1606-1.

o

The valve weights and orientations used in the

enalysis were consistent with the drawings and

installation.

o

The design temperature and pressure, operating

temperature and pressure, and pipe material were

consistent with parameters given in the Line

Designation List.

o

The seismic response spectra used in the analysis

corresponded

to

the

proper

building

and

elevation,

o

The calculations for thermal anchor movements

were correct and the movements were incorporated

in the analysis. The inspectors found for

Isometric drawing 2K3-1204-014-01, calculation

BJ-01-706, a portion of Page 7 was missing in the

calculation,

indicating

the

thermal

anchor

1

movements used in the calculation.

>

o

The

calculated

stresses were within ASME

Section III Class 2 allowances and deflections at

support locations were less than the allowable

for both small and large bore piping.

(2) Pipe Suppcrt Calculations

,

The pipe support calculation p.ckages listed in

Table 1,

were examined for

c. ipleteness,

inter--

discipline

coordination,

confor.?ance

to design

criteria and project requirements, consistency with

drawings and installation, and technical adequacy,

All of these pipe supports are contained in the piping

isometrics reviewed in the Construction Verification

Review, discussed in Section 2.C.6).a.

CSservations made relative to these pipe support

,

calculations include:

o

Design loads and displacements were correctly

transferred from the pipe stress calculations to

the pipe support calculations.

o

A friction load was included whenever the thermal

movement at a support exceeded 1/16 inch.

o

The structural members used in the analyses

corresponded in size and material with the

drawings and installation.

.

'

.

.

.

16

o

That design assumptions were properly noted in

the calculation package.

The

inspector found

that for pipe support V2-1204-014-H006, that the

calculation for the'embeded plate, that it should

have been noted that.the assumptions the engineer

used, when the reduced faulted-loads, used in the

calculation, were indeed compared to the upset

loads.

o

The calculated stresses in miscellaneous steel

were within allowances of the American Institute

of Steel Construction, and stresses in ASME

Section III Subsection NF components were within

NF allowances.

(3) Pipe Support Drawings

The examination of pipe support drawings was performed

in conjunction with the review of pipe support

calculations and the evaluation of the Construction

Program Verification.

Therefore, all of the pipe

supports listed in Table I were included in the pipe

support drawing review.

The drawings were reviewed

for completeness, appropriate approvals, drafting

clarity, and consisten:y with project requirements.

The only deficiency identified in the drawing review

were those noted in the Construction Verification

Review Section 2.C 6).a of this report.

(4) Design Change and Nonconformance Documents

_

Based on the information presented in this report,

Mechanical Field Change Requests (MFCRs), DCN-Rs, and

Deviation Reports (DRs), were included in the many of

the 56 pipe support packages for the thirteen piping

isometrics evaluated by the NRC Region II inspectors.

These design change documents were examined by the NRC

Region II inspectors for the following attributes:

o

Proper disposition and approval,

o

Appropriate technical justification,

o

Correct incorporation into drawings.

The NRC inspectors identified no findings during the

examination of the sample design change documentation.

i

,:

.

.

.

17

c.

Findings

Subsection 6.5 of the Module 11 Report presents 8 findings disclosed

by the Readiness Review Team in the Design Program Verification.

Among these findings there were no Level I,

one Level II, . and

seven Level III findings. The NRC Region II inspectors performed an

evaluation on the or,e Level II finding (2RRF-001-002).

o

Finding 2RRF-001-002, Level II, was in reference to two PPP

procedures IX-50, and IX-65.

The concern was the lack of

clarity with respect to the appropriate responsibilities and

authority of PPP field engineers, QC inspectors, and QA

engineers.

The procedures have been revised and appropriate

training has been conducted.

The NRC inspectors identified no findings during the examination of

the Readiness Review Findings in the Construction and Design Program

Verification.

3

Exit Interview

The inspection scope and findings were summarized on July 14, 1988,

with those persons indicated in Paragraph 1.

The inspector described

the areas inspected and discussed in detail the inspection findings.

No dissenting comments were received from the licensee.

Violation 425/88-19-01, Failure to Follow Procedures, Resulting in

Errors in Pipe Support QC and Design Documentation. See Paragraph

2.C.6).a.

Inspector Followup Item, 50-425/88-19-02, Potential Problems with

l

Spring Can Travel.

See Paragraph 2.C.6).a.(7).

l

The licensee did identify as proprietary materials various documents

for review by the inspector during this inspection, but no

proprietary information is contained in this report.

4.

Acronyms and Initialisms

AISC

American Institute of Steel Construction

ANSI

American National Standards Institute

,

ASCE

American Society of Civil Engineers

ASME

American Society of Mechanical Engineers

ATCW

Authorization to Continue Work

AWS

American Welding Society

BWPC

Bechtel Western Power Company

CD

Civil Deviation Report

CMTR

Certified Materials Test Report

COC

Certificate of Compliance

DBE

Design Basis Earthquake

DC

Design Criteria (Bechtel)

DCN-R

Drawing Change Notice-Resident

.

.

.

18

DR

Deviation Report

FSAR

Final Safety Analysis Report

GDC

General Design Criteria

GPC

Georgia Power Company

IDR

Independent Design Review.

IE

Office of Inspection and Enforcement

IEB

Inspection and Enforcement Bulletin

INPO

Institute of Nuclear Power Operations

LDL

Line. Designation List

MFCR-

Mechanical Field Change Request

MWO

Maintenance Work Order

NDE

Non-Destructive Examination

NRC

Nuclear Regulatory Commission

NRR

Office of Nuclear Reactor Regulation

NSSS

Nuclear Steam Supply System

OBE

Operational Basis Earthquake

P&ID

Piping and Instrumentation Diagram

PPP

Pullman Power Products

PQR

Procedure Qualification Record

PWR

Pipe Whip Restraint

QA

Quality Assurance

QC

Quality Control

RRF

Readiness Review Finding

RRT

Readiness Review Team

SER

Safety Evaluation Report

SRP

Safety Review Plan

SSER

Supplement Safety Evaluation Report

VEGP

Vogtle Electric Generating Plant

V-SAMU

Vogtle Structural Analysis Mobile Unit

VWAC

Visual Weld Acceptance Criteria

WPS

Welding Procedure Specification

l

I

-

-

-

...

- . .

.

.

TABII 1

.

PIPING

STRESS

SUPPORTS

PPP

P&ID

IS0 METRICS

STRESS

ANALYSIS

LINE NUMBER

CALCUIATION

SUPPORTS

SUPPORT QC

DRAWING 1RBIBER

INSPECTED BY

ANALYSIS

REVIEWED BY AND SAFETY /

PIPE

REVIEWED

INSPECTED BY DOCUMENTATION

SYSTEM and BUIISING

PIPING IS0 METRICS

NRC RE

PROBIRf NUMBER NRC RRT PIPING CIASS

SUPPORTS

NRC RRT

NRC Rg REVIEWED BY NRC

_

2I4DB121. R/22

2K3-1204-028-01 R/4

YES NO

BJ-01-706,R/2 YES NO 2-1204-014-4" V2-1204-014-H007 R/2 YES NO

YES NO

YES

Safety Injection

Q212/GGO

V2-1204-014-H008 R/3 YES YES YES NO

YES

Auxilitry Buildlag

2K3-1204-014-01, R/5

YES NO

10-01-706, R/2 YES NO 2-1204-014-4" V2-1204-014-H004 R/2 YES NO

YES NO

YES

Q212/Gr.0

V2-1204-014-H005 R/2 YES NO

YES

N/)

YES

V2-1204-014-H006 R/2 YES NO

YES NO

YES

ZI4DRIIS, R/19

2K4-1208-055-02, R/6

YES NO

BG-02-905

NO

NO 2-1208-055-3" V2-1208-055-H044 R/2 NO

NO

YES NO

YES

Chemiccl and

Q212/HG0

V2-1208-055-H045 R/2 NO

NO

YES NO

YES

V41ume control

V2-1208-055-H046 R/2 NO

NO

YES NO

YES

AuxiIicry BuiIding

V2-1208-055-H048 R/4 NO

NO

YES NO

YES

V2-1208-055-H049 R/2 NO

NO

YES N0

(ES

V2-1208-055-H050 R/2 NO

NO

YES NO

YES

V2-1208-055-H051 R/2 NO

NO

YES NO

YES

V2-1208-055-H052 R/2 NO

NO

YES NO

YES

2K4-1208-215-01 R/5

YES NO

BG-02-905

NO

NO 2-1208-215-3" V2-1208-215-H001 R/3 NO

NO

YES NO

YES

Q212/HGO

V2-1208-215-H002 R/3 NO

NO

YES NO

YES

V2-1208-215-H003 R/2 NO

NO

YES NO

YES

V2-1208-215-H004 R/2 NO

NO

YES NO

YES

V2-1208-215-H005 R/5 NO

NO

YES NO

YES

$

2K4-1208-005-02,R/6

YES NO

BG-02-905

NO

NO 2-1208-255-3" V2-1208-255-H001 R/3 NO

NO

YES NO

YES

Q212/FGO

V2-1208-255-H002 R/2 NO

NO

YES NO

YES

V2-1208-055-H005 R/2 NO

No

YES NO

YES

V2-1208-005-H006 R/3 NO

NO

YES NO

YES

V2-1208-005-H007 R/2 NO

NO

YES NO

YES

2K4-1208-005-01,R/6

YES NO

BC-02-905

NO

NO 2-1208-005-3" V2-1208-005-H002 R/2 NO

NO

YES NO

YES

Q212/FGO

V2-1208-005-H001 R/2 N0

NO

YES NO

YES

\\

s.

2I4D5-119. R/15

2K3-1204-063-02, R/5

YES NO

BC-01-903

NO

NO 2-1204-057-4" V2-1204-063-H003 R/2 NO

NO

YES NO

YES

Saf;ty Injection

2-1204-063-4" V2-1204-063-H004 R/2 NO

NO

YES NO

YES

Auxilirry Building

2-1204-063-3" V2-1204-063-H005 R/4 NO

NO

YES NO

YES

Q212/FGO

V2-1204-063-H006 R/2 NO

NO

YES NO

YES

V2-1204-063-H007 R/3 NO

NO

YES NO

YES

V2-1204-063-H009 R/2 NO

NO

YES NO

YES

V2-1204-063-H010 R/2 NO

NO

YES NO

YES

V2-1204-063-H012 R/2 NO

NO

YES NO

YES

V2-1204-063-H013 R/2 NO

NO

YES NO

YES

V2-1204-063-H001 R/2 NO

NO

YES NO

YES

V2-1204-057-H039 R/2 NO

NO

YES NO

YES

- - .

-

-

-

- . -

- . -

- - -

.

. -

-

_

,

9

Page 2


.

.-

_--

..-

-

_....._-

PIPING

__.-

P&lD

STRESS

SUPPORTS

PPP

IS0 METRICS

STRESS

ANALYSIS

LINE NUMBER

CALCULATION

SUPPORTS

SUPPORT QC

DRAWINC 1RMBER

INSPECTED BY

ANALYSIS

REVIEW D BY AND SAFETY /

PIPE

REVIEWED

INSPECTED BY DOCUPENTATION

SYSTDI and BUILDING

PIPING IS0 METRICS

NRC _RRT

PROBIIM NUMBER NRC _RRT

PIPINC CIASS

SUPPORTS

EC RRT

NRC

RRT REVIE W D BY NRC

_

214DB115-2,R/16

2K3-1208-139-01,R/12

YES NO

BC-01-717, R/I IIS NO 2-1209-139-6" V2-1208-139-H016 R/3 YES NO

YES NO

YES

Chemical sad Volume

Contral,

Q212/FGO

V2-1208-139-H014 R/3 YES NO

YES NO

YES

Auxilirry Building

V2-1208-139-H003 R/4 YES NO

YES NO

YES

V2-1208-139-H007 R/5 YES NO

YES NO

YES

V2-1208-139-H008 R/3 YES NO

YES NO

YES

2K3-1208-146-01, R/15

YES NO

BC-Ol-903,R/I NO

NO 2-1208-145-4" V2-1208-145-H005 R/S NO

NO

YES NO

YES

2-1208-146-3" V2-1208-145-H006 R/7 NO

NO

YES N0

fES

2-1208-A20-l/2"V2-1208-145-H013 R/4 NO

NO

YES NO

YES

Q212/FGO

V2-1208-145-H014 R/l NO

NO

YES NO

YES

V2-1208-145-H015 R/I NO

NO

YES NO

YES

V2-1208-145-H016 R/I NO

NO

YES NO

YES

V2-1208-145-H017 R/R NO

NO

YES NO

YES

2X4D8122. R/20

2K3-1205-004-02,R/7

YES NO

BC-00-718. R/I YES NO 2-1205-0%-14" V2-1205-004-H015 R/4 YES NO

YES NO

YES

Residual Beat.

Q212/MGO

V2-1205-004-H010 R/3 YES NO

YES NO

YES

Removal Auxiliary

Building

2K3-1205-004-01,R/13

Y.'.S

NO

BC-00-718, R/l YES NO 2-1205-004-14" V2-1205-004-H016 R/3 YES NO

YES NO

YES

Q212/HGO

V2-1205-004-H019 R/4 YES NO

YES NO

YES

V2-1205-004-H001 R/2 YES NO

YES NO

YES

to

o

2K3-1205-006-01, R/12

YES NO

BC-00-725, R/0 YES NO 2-1205-006-8" V2-1205-006-H009 R/4 YES NO

YES NO

YES

Q212/HGO

v2-1205-006-H001 R/S

1.".S

NO

YES NO

YES

2K3-1205-006-02,R/12

YES No

BC-00-725 R/0 YES NO 2-1205-006-2" V2-1205-006-H014 R/6 YES YES YES NO

YES

Q212/KG0

'.

\\

u .

-

,_

A