Forwards QA Plan Re post-defueling Monitored Storage Condition
ML20153B716
Person / Time
Site: Crane Constellation icon.png
Issue date: 08/25/1988
From: Standerfer F
GENERAL PUBLIC UTILITIES CORP.
To:
NRC OFFICE OF ADMINISTRATION & RESOURCES MANAGEMENT (ARM)
Shared Package
ML20153B720 List:
References
4410-88-L-0133, 4410-88-L-133, NUDOCS 8808310065
Download: ML20153B716 (1)


Text

"

GPU Nuclear Corporation f

g gf Post Office Box 480 Route 441 South Middletown, Pennsylvania 17057 0191 717 944 7621 TELEX 84 2386 Writer's Direct Dial Number:

(717) 948-8461 August 25, 1988 4410-88-L-0133/0413P US Nuclear Regulatory Comission ATTN: Document Control Desk Washington, DC 20555

Dear Sirs:

ihree Mile Island Nuclear Station, Unit 2 (TMI-2)

Operating License No. DPR-73 Docket No. 50-320 Post-Defueling Monitored Storage Quality Assurance Plan GPU Nuclear letter 4410-88-L-0068, dated August 16, 1988, tranunitted the Safety Analysis Report (SAR) for the Post-Defueling Monitored Storage (PDMS) condition for THI-2.

Section 10.1 of the SAR, entitled, "Quality Assurance Plan," notes that the quality assurance requirements for TMI-2 during PDMS would be documented in a Quality Assurance Plan developed specifically for the PDMS plant condition. Attached is a copy of that plan.

Sincerely, In

' /g

. R. Standerfer Director, TMI-2 JJB/ emf Attachment cc: Senior Resident Inspector, TMI - R. J. Conte Regional Administrator, Region 1 - W. T. Russell Director, Plant Directorate IV - J. F. Stolz Systems Engineer, TMI Site - L. H. Thonus

  1. l l

8808310065 880825 DR ADOCK 050003 0 GPU Nucl6ar Corporation is a subsidiary of the General Public Utilities Corporation