Amend 95 to License DPR-20,revising Tech Specs for Primary Coolant Sys Leakage to Clarify Action When Leakage Exceeds Specified Limits & Deleting Spec Applicable to Cycle 2 Only
ML20151Y187
Person / Time
Site: Palisades Entergy icon.png
Issue date: 01/30/1986
From: Thadani A
Office of Nuclear Reactor Regulation
To:
Consumers Power Co
Shared Package
ML20151Y192 List:
References
DPR-20-A-095 NUDOCS 8602120613
Download: ML20151Y187 (5)


Text

ja aeroy zt,.

jo UNITED STATES g

3 NUCLEAR REGULATORY COMMISSION o

O E

WASHINGTON, D. C. 20555

%,...../

CONSUMERS POWER COMPANY PALISADES PLANT DOCKET NO. 50-255 AMENDMENT TO PROVISIONAL OPERATING LICENSE Amendment No.95 License No. DPR-20 1.

The Nuclear Regulatory Comission (the Comission) has found that:

A.

The application for amendment by Consumers Power Company (the licensee)datedApril 30, 1985, complies with the standards and requirements of the Atomic Energy Act of 1954, as amended (the Act),

and the Comission's rules and regulations set forth in 10 CFR Chapter I; B.

The facility will operate in conformity with the application, the provisions of the Act, and the rules and regulations of the Commission; C.

There is reasonable assurance (i) that the activities authorized by this amendment can be conducted without endangering the health and safety of the public; and (ii) that such activities will be conducted in compliance with the Comission's regulations; i

D.

The issuance of this amendment will not be inimical to the comon defense and security or to the health and safety of the public; and E.

The issuance of this amendment is in accordance with 10 CFR Part 51 of the Comission's regulations and all applicable requirements have been satisfied.

hgg2gDOS P

2.

Accordingly, the license is amended by changes to the Technical Specifications as indicated in the attachment to this license amendment and Paragraph 3.B. of Provisional Ope,ating License No. DPR-20 is hereby amended to read as follows:

B.

Technical Specifications The Technical Specifications contained in Appendices A and B, as revised through Amendment No. 95, are hereby incorporated in the license. The licensee shall operate the facility in accordance with the Technical Specifications.

3 This license amendment is effective as of the date of its issuance.

FOR THE NUCLEAR REGULATORY COMMISSION i

f Ashok C. Thadani, Director PWR roject Directorate #8 Division of PWR Licensing-B

Attachment:

Changes to the Technical Specifications Date of Issuance: January 30, 1986

)

)

ATTACHMENT TO LICENSE AMENDMENT NO. 95 PROVISIONAL OPERATING LICENSE NO. OPR-20 DOCKET NO. 50-255 Revise Appendix A Technical Specifications by removing the page identified below and insert the enclosed page. The revised page is identified by amendment number and contains marginal lines indicating the areas of change.

REMOVE INSERT 3-20 3-20 3-21 3-21 l

4 l

I

5 3.1 PRIMARY COOLANT SYSTEM (Cont) 3.1.5 Primary Coolant System Leakage Limits g

Specification a.

If the primary coolant system leakage exceeds 1 gpm and the source of the leakage is not identified, reduce unidentified primary coolant system leakage to less than 1 gpm within 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br />, or place the reactor in hot shutdown condition within the following 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> and in cold shutdown condition within the following 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />.

b.

If leakage from the primary coolant system exceeds 10 gpm, reduce primary coolant system leakage to less than 10 gpm within 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br />, or place the reactor in hot shutdown condition within the following 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> and in cold shutdown condition within the following 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />.

3-c.

If the specific activity of the secondary coolant in a steam generator exceeds 0.1 pCi/ gram dose equivalent I-131, the reactor shall be placed in hot shutdown within 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> and in cold shutdown within the following 30 hours3.472222e-4 days <br />0.00833 hours <br />4.960317e-5 weeks <br />1.1415e-5 months <br />.

d.

The primary to secondary leakage in a steam generator shall not exceed 0.3 gpm for any period of steady state operation greater than 24 consecutive hours.

During periods of start-up and major load changes, when the leakage measurement sensitivity is reduced, the calculated leakage shall not exceed 0.6 gpm for any period of greater than 24 consecutive hours.

Basis Industry experience has shown that while a limited amount of leakage is expected from the primary coolant system, the unidentified portion of this leakage can be reduced to a threshold value of less than 1 gpm. This threshold value is sufficiently low to ensure early detection of additional leakage. When the source of the leakage can be identified, the condition shall be evaluated to determine if operation can safely continue. Justifica-tion for continued operation with identified leakage in excess of 1 gpm shall be documented in writing and approved by the Plant General Manager or his representative.

A maximum allowable primary coolant system leak rate of 10 gpm has been established. This limitation does not include the primary coolant pump seal leak-off which is directed to the volume control tank. The 10 gpm limitation provides allowances for a limited amount of leakage from known sources whose presence will not interfere with the detection of unidentified leakage. A primary coolant system leak rate in excess of 10 gpm is indic-ative of a failure of sufficient magnitude to warrant shutdown for repair.

3-20 Amendment No. 28, 95

r 3.1 PRIMARY COOLANT SYSTEM (Contd)

The 10 gpm limitation is well within the 40 gpm capacity of one charging pump which would be available even under a loss of off-site power condition.

The initial 6 hour6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> period following indication of unidentified primary coolant system leakage in excess of 1 gpm, or total primary coolant system leakage in excess of 10 gpm, provides sufficient time to facilitate identi-fication and confirmation of the leakage source with the Plant being maintained in a stable condition. When the source of the leakage cannot be identified or reduced, the following 6 hour6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> period is sufficient to bring the Plant to hot shutdown condition in an orderly manner. The 24 hour2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> period which follows provides adequate time to bring the Plant to cold shut-down condition in an orderly manner and to correct minor deficiencies.

If major repairs are necessary, a cold shutdown condition would be in order.

The limitations on secondary system specific activity ensure that the resultant off-site radiation dose will be limited to a small fraction of 10 CFR Part 100 limits in the event of a steam line rupture. This dose also includes the effects of a coincident 1.0 gpm primary to secondary tube leak in the steam generator of the affected steam line and a concurrent loss of offsite electrical power.

9 i

l 3-21 Amendment No. 20,95

-