Notification of 980930 Meeting with Util in Rockville,Md to Discuss License Amend Request for Extending Sequoyah Emergency Diesel Generator Allowed Outage Time from 3 Days to 7 Days
ML20151X309
Person / Time
Site: Sequoyah  
Issue date: 09/11/1998
From: Hernan R
NRC (Affiliation Not Assigned)
To: Hebdon F
NRC (Affiliation Not Assigned)
References
NUDOCS 9809160375
Download: ML20151X309 (4)


Text

_

September 11, 1998 MEMORANDUM TO: Frederick J. Hebdon, Director Project Directorate ll-3 Division of Reactor Projects - 1/11 Office of Nuclear Reactor Regulation FROM:

Ronald W. Hernan, Senior Project Manager Original signed by:

Project Directorate 11-3 Division of Reactor Projects -l/II Office of Nuclear Reactor Regulation

SUBJECT:

FORTHCOMING MEETING WITH TENNESSEE VALLEY AUTHORITY (TVA)- SEQUOYAH NUCLEAR PLANT, UNITS 1 AND 2, REGARDING EXTENTION OF EMERGENCY DIESEL GENERATOR ALLOWED OUTAGE TIME DATE & TIME:

Wednesday, September 30,1998 9:00 a.m. - 11:30 a.m.

LOCATION:

U. S. Nuclear Regulatory Commission One White Flint North, Room O 4-B-6 11555 Rockville Pike Rockville, Maryland PURPOSE:

This meeting is being hold at TVA's request to discuss the li::ense amendment request for extending the Sequoyah emergency diesel generator allowed outage time from 3 days to 7 days.

PARTICIPANTS *:

NEC IVA R. Hernan, NRR P. Salas, et al.

F. Hebdon, NRR O. Chopra, NRR l

P. Gill, NRR I. Jung, NRR M. Reinhart, NRR Docket Nos. 50-327 and 50-328 cc: See next page CONTACT: Ronald W. Hernan, NRR g (( ((gg Qfy J

(301) 415-2010 i

  • Meetings between NRC technical staff and applicants or licensees are open for interested members of the public, petitioners, intervenors, or other parties to attend as observers pursuant to " Commission Policy Statement on Staff Meetings Open to the Public" 59 Federal Reaister 48340, 9/20/94.

DOCUMENT NAME: G:\\SQN\\MEETNOT3.30 f'Cl C)

TO GET a copy of this document, indicate in the box: "C" = Copy without attachment / enclosure "E" - Copy with attachment / enclosure "N' = No copy OFFICE PDil-3/PMA j l PDil-3/LA PDil-3/PD 4

)

NAME RHernan [//[F BClayton gAF FHebdon fd DATE 9/10/98

~

9//6/98 9/,0/98 4GOT160355 980911 PDR ADOCK 05000327 P

PDR

qSCEQy p

UNITED STATES

}

NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20565-0001

%..... p#

September 11, 1998 MEMORANDUM TO:

Frederick J. Hebdon, Director Project Directorate 11-3 Division of Reactor Projects - 1/II Office of Nuclear Reactor Regulation FROM:

Ronald W. Hernan, Senior Project Manager fg-Project Directorate 11-3 Division of Reactor Projects - 1/11 Office of Nuclear Reactor Regulation

SUBJECT:

FORTHCOMING MEETING WITH TENNESSEE VALLEY AUTHORITY (TVA)- SEQUOYAH NUCLEAR PLANT, UNITS 1 AND 2, i

REGARDING EXTENTION OF EMERGENCY DIESEL GENERATOR ALLOWED OUTAGE TIME DATE & TIME:

Wednesday, September 30,1998 9:00 ra.m. - 11:T,0 a.m.

LOCATION:

U. S. Nuclear Regulatory Commission One White Flint North, Room O 4-B-6 11555 Rockville Pike Rockville, Maryland PURPOSE:

This meeting is being held at TVA's request to discuss the license amendment request for extending the Sequoyah emergency diesel generator allowed outage time from 3 days to 7 days.

PARTICIPANTS *:

NRG 3YA R. Hernan, NRR P. Salas, et al.

F. Hebdon, NRR O. Chopra, NRR P. Gill, NRR

l. Jung, NRR M. Reinhart, NRR Docket Nos. 50-327 and 50-328 cc: See next page CONTACT: Ronald W. Hernan, NRR (301)415-2010
  • Meetings between NRC technical staff and applicants or licensees are open for interested l

members of the public, petitioners, intervenors, or other parties to attend as observers pursuant to " Commission Policy Statement on Staff Meetings Open to the Public" 59 Federal Reaister 48340, 9/20/94.

Mr. J. A. Scalice SEQUOYAH NUCLEAR PLANT Tennessee Valley Authority cc:

r Senior Vice President Mr. Pedro Salas, Manager Nuclear Operations Licensing and Industry Affairs Tennessee Valley Authority Sequoyah Nuclear Plant 6A Lookout Place Tennessee Valley Authority 1101 Market Street P.O. Box 2000 Chattanooga, TN 37402-2801 Soddy Daisy, TN 37379 Mr. Jack A. Bailey Mr. J. T. Herron, Plant Manager Vice President Sequoyah Nuclear Plant Engineering & Technical Services Tennessee Valley Authority

. Tennessee Valley Authority P.O. Box 2000 6A Lookout Place Soddy Daisy, TN 37379 1101 Market Street Chattanooga, TN 37402-2801 Regional Administrator U.S. Nuclear Regulatory Commission Mr. Masoud Bajestani Region ll Site Vice President -

61 Forsyth Street, SW.

Sequoyah Nuclear Plant Suite 23T85 Tennessee Valley Authority Atlanta, GA 30303-3415 P.O. Box 2000 Soddy Daisy, TN 37379 Mr. Melvin C. Shannon Senior Resident inspector General Counsel Sequoyah Nuclear Plant Tennessee Valley Authority U.S. Nuclear Regulatory Commission l

ET 10H 2600 Igou Ferry Road 400 West Summit Hill Drive Soddy Daisy, TN 37379 Knoxville,TN 37902 Mr. Michael H. Mobley, Director i

Mr. Raul R. Baron, General Manager TN Dept. of Environment & Conserv. don Nuclear Assurance Division of Radiological Health Tennessee Valley Authority 3rd Floor, L and C Annex SM Lookout Place 401 Church Street 1101 Market Street Nashville, TN 37243-1532 Chattanooga, TN 37402-2801 i

County Executive Mr. Mark J. Burzynski, Manager Hamilton County Courthouse Nuclear Licensing Chattanooga, TN 37402-2801 Tennessee Valley Authority 4X Blue Ridge 1101 Market Street Chattanooga, TN 37402-2801

l cc: Licensee & Service List 1

Meeting Notice Distribution E-Mail S. Collins /F. Miraglia (FJM)

B. Boger (BAB2)

' J. Zwolinski(JAZ)

F. Hebdon (FJH)

R. Hernan (RWH)

8. Clayton (BAC2)

T. Martin (e-mail to SLM3) l OPA (e-mail to OPA)

L. Plisco, Ril DRP (LRP)

M. Tsc' iltz (MDT) n K. Clark (KNC2)

PMNS (meeting announcement coordinator)

R. Barrett (RJB3)

A. El-Bassioni (AAE) i

1. Jung (IXJ)

J. Calvo (JAC3)

P. Gill (ASG)

O. Chopra (OPC)

W. Beckner (WDB)

M. Reinhart (FMR)