ML20151U715

From kanterella
Jump to navigation Jump to search
Supplemental Deficiency Rept CP-87-59 Re Improper Application of Const Aids.Initially Reported on 870921. Estimated Date for Completion of Corrective Actions for Unit 1 Rescheduled Until 890401.Unit 2 Schedule Unchanged
ML20151U715
Person / Time
Site: Comanche Peak  
Issue date: 08/10/1988
From: Counsil W, Walker R
TEXAS UTILITIES ELECTRIC CO. (TU ELECTRIC)
To:
NRC OFFICE OF ADMINISTRATION & RESOURCES MANAGEMENT (ARM)
References
CP-87-59, TXX-88610, NUDOCS 8808190223
Download: ML20151U715 (1)


Text

_

o M==

Log # TXX-88610

~

File # 10110 C

903.9 Ref. i 10CFR50.55(e)

TUELECTRIC August 10, 1988 William G.Counsil Esen:sta Vke hestdme V. S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, D.C.

20555

SUBJECT:

COMANCHE PEAK STEAM ELECTRIC STATION (CPSES)

DOCKET NOS. 50-445 Af!D 50-446 IMPROPER APPLICATION OF CONSTRUCTION AIDS SDAR: CP-87-59 (SUPPLEMENTAL REPORT)

Gentlemen:

On September 21, 1987, TV Electric letter logged TXX-6750 provided notification that the issue involving the improper application of construction aids was reportable under the provisions of 10CFR50.55(e).

TV Electric latest report on this issue, logged TXX-88266, was submitted "ar-b 1, 1988.

This su)plemental report is submitted to update the corrective action completion scledule.

In the last report on this issue (stated in TXX-88266), TV Electric indicated that the corrective actions (replacement of the T-1W and T-11W cable tray fittings) for Unit I would be completed by August 11, 1988.

The estimated completion date for implementation of Unit I corrective action has been rescheduled to April 1, 1989.

"le schedule for Unit 2 remains unchanged.

Very truly yours, MJf. St. M W. G. Counsil l

By: korei b.f/I o,

R. D. Walker Manager, Nuclear Licensing HAM /grr c-Mr. R. D. Martin, Pegion IV Residen Inspectors, CPSES (3)

)