Forwards Insp Rept 50-285/88-22 on 880629-0718.Enforcement Conference Scheduled for 880811 to Discuss Noted Violation. Agenda for Meeting Encl
ML20151R905
Person / Time
Site: Fort Calhoun Omaha Public Power District icon.png
Issue date: 07/29/1988
From: Callan L
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
To: Morris K
OMAHA PUBLIC POWER DISTRICT
Shared Package
ML20151R908 List:
References
EA-88-201, NUDOCS 8808120341
Download: ML20151R905 (2)


See also: IR 05000285/1988022

Text

3-

..- .

u, , -

ep

>

. , _

.

.

.

.

,q w,

-

,

'

Lj

Lj

e

3

,

,

,

,

.

,

i.:

. . -

.

a

' ;

,

,

,,

9

_(

g

k

I

,

F ,

' '

JIn; Reply Reir To:

-

.

.

.e

,

Docket
50-285/88-22-

-

7

LEA 88-201'

.

-

,

_ ,

n

v

i

4

,

'0maha Public Power District

J

ATTN:' Mr. skenneth J. Morris

. Division Manager-Nuclear' Operations-

1623 Harney Street

Omaha, Nebraska '68102

_

.-

,

,

Gentlemen:

This refers ta the inspectio'n conducted.by Messrs. P. H. Harrell and T.1Reis-of?

this office during the period June.29.through July'18, 1988, of activities

authorized by NRC Operating License DPR-40 for the Fort Calhoun Station, and to:

the discussion of our findings with Mr.' L. T; KJsek;(Acting Plant Manager)' and

.

other members of your staff at the conclusion of the inspection. .

'

The area examined during this inspection was 'a . followup ~on your staff's

l

.

finding that the limiting condition .for operation for-excore monitoring of

linear heat rate and the thermal margin / low pressure trip setting-of the reactor

protection system were in error. Within this area, the. inspection consisted of'

>

selective examination of the Technical Specifications ~, interviews with-

personnel, and observations made by the NRC. inspectors. The'inspecticn findin'gs

are documented in the enclosed inspection report.

.

-

m

As a result of this inspection, it was found that certain ofiyour, activit'tes;

L:

-

appeared to be in violation of NRC requirements. :As discussed.in the telephone.

conversation between Mr. T. F. Westerman and Mr. J. 'd._ Fisicaro of your staff..

a

we have scheduled an enforcement conference in our Region IV office:at 1 p.m. '

d

.

on August 11, 1988, to discuss your understanding of these: apparent violations,.

1

the reasons for occurrences, and your correcti.ve. actions

,We will also discuss.

the enforcement policy, if appropriate. An' agenda for this meeting'is: enclosed.

,

j

I

Should you have any questions concerning this inspection, we will be pleased to

discuss them witn you.

Sincerely,

hACb

L. J. Callan, Director

Division of Reactor Projects

u

F

Enclosures:

(seenextpage)

'

,

'

,

.

SRIk

PE

C:DRP/BI

0: R

'E

RIV:RI

TReis/nc

PHHarrell

RPMullikin

TFWesterman'

LJ aTlan -

G

..

n

,

g/3/88

/) /g.1/88

q/M/88

]//g/88

'l~Bf(/88'

.

g/44/88

9

'

g88 MBS S@hk?

.

,

$8DV

"

.

.

, o.

_ mm . ,g. _

m

-,,,

.

. .

_ . . . . . _ . . . _ . . _ . . _ , _ _ - . _ .

. , _ , _

_ . _ .

-

~. .

.

.

3

'

'

,

1,-

,

O

t

__r'.

?

.

.

,

Omaha Public Power District

-2-

.

Fnclosures:

.

%

1.

Appendix A - NRC Inspection Report _

,-

50-285/88-22

'

" ,

. Appendix B - Meeting Agenda

2.

cc w/ enclosures:

W. G. Gates, Manager

,

Fort Calhoun Station

P. O. Box 399

Fort Lalhoun, Nebraska 68023

Harry H. Voigt, Esq.

LeBoeuf, Lamb, Leiby & MacRae

1333 New Hampshire Avenue, NW

Washington, DC' 20036

Nebraska Radiation Control Program Director

bec to DMB (IE01)

bec distrib. by RIV:

R.D. Martin, RA

  • RPB-DRSS
  • Section Chief (DRP/B)
  • MIS System
  • .RIV File
  • DRP
  • RSTS Operator
  • ProjectEngineer,DRP/B

Lisa Shea, RM/ALF

  • T. Bournia, NRR. Project Manager
  • DRS

G. F. Sanborn, E0

  • RRI
  • w/766

.l

l

.l

,

.,

,

I

,

4