T) C l) x APR 181988 Docket No. 50-461 Illinois Power Company ATTN: Mr. W. C. Gerstner Executive Vice President 500 South 27th Street Decatur, IL 62525 Gentlemen:
This confirms our plans as discussed on April 15, 1988, to meet with Mr. Perry and others of your staff at 11:00 a.m. on April 21, 1988, at the NRC Region III office in Glen Ellyn, Illinois.
The purpose of the meeting is an enforcement conference to discuss a security event reviewed during an inspection on April 5-8, 1988, concerning inadequate security compensatory measures.
We will gladly discuss any questions you have concerning this meeting.
Sincerely,
'metgtnai sigr,cd by E.G. Ofeerm" Edward G. Greet.' nan, Director Division of Reac+.or Projects cc w/ enclosure:
DCD/DCB (RIDS)
Licensing Fee Management Branch Resident Inspector, RIII Roy Wight, Manager Nuclear Facility Safety Mark Jason, Assistant Attorney General, Environmental Control Division Richard Huboard i
J. W. McCaffrey, Chief, Public
]
Utilities Division j
H. S. Taylor, Quality Assurance i
Division 1
David Rosenblatt, Governor's Office of Consumer Services q
i nr nr b
RIII RIII RIII@y RIJi
$]Vh F%
/23$
Kn$l(
T/"
JMcCormick-Barger/pb Cooper op d
Grg$ man
/-
4//8/88 4////88 4/1b'/88
/88 4/)/88
'8804260206 880418
!(e 9
& ai s PDR ADOCK 05000461
%s-t j
Q DCD J
..e.
- g[>* Etio,'%,
UNITED STATES NUCLEAR REGULATORY COMMisslON
[
g REGION Hi 5
,4, GLEN ELLYN, lLLINOIS 60137 APR 181988 NOTICE OF SIGNIFICANT LICENSEE MEETING Name of Licensee:
Illinois Power Company Name of Facility:
Clinton Nuclear Power Station Docekt No. 50-461 Date and Time of Meeting:
Thursday, April 21, 1988 at 11:00 a.m.
Location of Meeting: Nuclear Regulatory Commicsion Region III 799 Roosevelt Road Conference Room C Glen Ellyn, IL Purpose of Meeting:
Enforcement conference to discuss inadequate security compensatory measures at the Clinton station.
RIII Attendees:
C. E. Norelius, Director, Division of Radiation Safety and Safeguards B. S. Mallett, Chief, Nuclear Materials Safety and Safeguards Branch
)
J. Creed, Chief, Safeguards Section i
R. Cooper, Chief, Reactor Projects Section 3B Licensee Attendees:
S. Perry, Manager, Nuclear Production F. Spangenberg, Director, Nuclear Licensing NOTE: Attendance at this meeting by NRC personnel should be made known by COB April 20, 1988, by telephone call to J. Creed, Region III (FTS338-5643).
Distribution:
J. M. Taylor, Deputy Executive Director for Regional Operations T. M. Murley, Director, Office of Nuclear Reactor Regulations i
T. T. Martin, Associate Director for Inspection and Technical Inspection F. Miraglia, Associate Director for Projects, NRR J. G. Partlow, Director. Division of Reactor Inspection and Safeguards i
D. M. Crutchfield, Director, Division of Reactor Projects III/IV/Y, NRR G. Holahan, Assistant Director for Region III and V, NRR M. Johnson, RIII Coordinator, EDO D. R. Muller, Director, Project Directorate III-2, NRR J. Stevens, Licensing Project Manager, NRR