C:mm:nw:alth Edisen Zion Generating Station 101 Shiloh Blvd.
Z:on, Illinois 60099 Telephone 312/746 2084 February 9, 1988 Mr. Bert Davis Acting Regional Administrator Directorate of Inspection and Enforcement, Region III U.
S.
Nuclear Regulatory Commission 799 Roosevelt Road Glen Ellyn, IL 60137
Subject:
Zion Nuclear Power Station Operating Report, NRC Dockets 50-295 and 50-304
Dear Mr. Davis:
Enclosed is Part 3 of the Zion Station Operating Report, reporting results of Environmental Radiological and Meteoro-logical monitoring.
Part 1, facility operating experience was submitted under separate cover in F.ebruary, and Part 2, radio-active effluents in February and AQgust.
Two copies of the report are provided for your use.
One copy each will be forwarded to Document Control and the NRC Resident Inspector.
Sinceret
- ours, 4
/7 kN G.
J.
Pliml Station Manager Zion Station GJP/jlc Enclosure 8804220159 880209 PDR ADOCK 05000295 R