ML20151D733

From kanterella
Jump to navigation Jump to search

Advises That SEP Topic VIII-2, Onsite Emergency Power Sys Complete Based on Mods Verified in 870519 Insp Rept 87-08. Trip Bypass Circuitry Installed for Generator Reverse Power & Generator Loss of Field Trips During 1984 Outage
ML20151D733
Person / Time
Site: Haddam Neck File:Connecticut Yankee Atomic Power Co icon.png
Issue date: 03/31/1988
From: Wang A
Office of Nuclear Reactor Regulation
To: Mroczka E
CONNECTICUT YANKEE ATOMIC POWER CO.
References
TASK-08-02, TASK-8-2, TASK-RR TAC-51934, NUDOCS 8804140412
Download: ML20151D733 (2)


Text

P

  • March 31,1988 Docket No. 50-213 DISTRIBUTION DicEK7DF Edordan NRC & Local DPRs JPartlow PDI-4 Rdg. OGC-WP Mr. Edward J. Mroczka SVarga ACRS(10)

Senior Vice President BBoger AWang Nuclear Engineering and Operations SNorris Connecticut Yankee Atomic Power Company P. O. Box 270 Hartford, Connecticut C6141-0270

Dear Mr. Mroczka:

SUBJECT:

HADDAM NECK PLANT - SEP TOPIC VIII-2, "0NSITE EMERGENCY POWER SYSTEMS (DIESEL GENERATORS) (TAC NO. 51934)

In a Safety Evaluation dated August 28, 1981, the staff noted that the diesel generator over current, reverse power, and loss of field protective trips are not bypassed during energency operation and that this was not in agreenent with current NRC guidelines. In the staff's "Integrated Plant Safety Assessrrent", dated June 1983, the staff agreed that Connecticut Yankee Atomic Power Company's (CYAPCO) prcposal to bypass or use coincident logic for all diesel generator protection trips other than the engine-overspeed and generator differential trips under accident conditions would resolve this SEP topic.

By letter dated Parch 17, 1988 CYAP" stated that during the 1984 cod 1986 refueling outages, CYAPCO con.pleted , te n.odifications necessary to resolve this SEP topic. Specifically, CYAPC0 installed trip bypass circuitry for the generator reverse power and generator loss of field trips during the 1984 refueling cutage. Because of the unavailability of qualified relays during the 1984 outage, the trip bypass circuitry for the generator overcurrent trip was corpleted during the 1986 refueling outage.

These nodifications were verified in Inspection Report 87-08 dated May 19, 1987.

Therefore, the staff considers SEP VIII-2, "Onsite Energency Power Systems -

Diesel Generator" to be cortplete.

Sincerely, original signed by Alan B. Wang, Project Manager Project Directorate I-4 Division of Reactor Projects I/II Office of Nuclear Reactor Regulation cc: See next page

^

LA:PDI-4 PM:PDI-4 D:P l Sh AWang:bdk JStol' ,

03/dl/88 03/Jl /88 0$/pj 8 )

Y 8804140412 880331 PDR ADOCK 05000213 0 PDR j

Mr. Edward J. Mroczka Connecticut Yankee Atomic Power Company Haddam Neck Plant ec:

Gerald Garfield, Esquire R. M. Kacich, Manager Pay, Berry and Howard Generation Facilities Licensing Counselors at Law Northeast Utilities Service Company City Place Post Office Box 270 Hartford, Connecticut 06103-3499 Hartford, Connecticut 06141-0270 K. D. Renberg, Vice President D. O. Nordquist Nuclear Operations Panager of Quality Assurance Northeast Utilities Service Company Northeast Nuclear Energy Company Post Office Box 270 Post Office Box 270 Hartford, Connecticut 06141-0270 Hartford, Connecticut 06141-0270 Kevin McCarthy, Director Regional Administrator Radiation Control Unit Region !

Cepartrent of Environmental Protection U. S. Nuclear Regulatory Commission State Office Building 475 Allendale Road Hartford, Connecticut 06106 King of Prussia, Penr.sylvania 19406 Bradford S. Chase, Under Secretary Board of Selectmen Energy Division Town Hall Office of Policy and Panagement Haddam, Connecticut 06103 80 Vashington Street Hartford, Connecticut 06106 J. T. Shedlosky, Pesident inspectcr Haddam Neck Plant D. B. Miller, Staticr. Superintendent c/o U. S. Nuclear Regulatory Conmissien Haddam Neck Plant Pcst Office Box 116 Connecticut Yankee Atomic Power Cenpany East Haddam Post Office RFD 1. Post Office Box 127E East Haddam, Connecticut C6423 East Hampton, Connecticut 06424

. G. H. Bouchard, Unit Superintendent Haddam Ncck Plant RFD fl Post Office Box 127E '

East Hampton, Connecticut 06424 e