ML20151D577
| ML20151D577 | |
| Person / Time | |
|---|---|
| Site: | Peach Bottom |
| Issue date: | 07/07/1988 |
| From: | Ronald Bellamy NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I) |
| To: | Corbin McNeil PECO ENERGY CO., (FORMERLY PHILADELPHIA ELECTRIC |
| References | |
| NUDOCS 8807250165 | |
| Download: ML20151D577 (3) | |
See also: IR 05000277/1988009
Text
,_
.
.
-
l
pL
K,
-
.
/
JUL 07 1989
Docket'Nos. 50-277
50-278
.
Philadelphia Electric Company
ATTN: Mr. C. A. McNeill
Executive Vice President-Nuclear
- 2301 Market Street
Philadelphia, Pennsylvania 19101
Gentlemen:
Subject:
Inspection 50-277/88-09 and 50-278/88-09
This refers to your letter dated May 16, 1988, in response to our Ictter dated
April-16, 1988.
Thank you for informing us of the corrective and preventive actions documented
in your letter. These actions will be examined during a-future inspection of
your -1icensed program.
Your cooperation with us is appreciated.
Sincerely,
Original Signed By:
Ronald R. Bellamy
Ronald R. Bellamy, Chief
Facilities Radiological Safety
and Safeguards Branch
Division of Radiation Safety
and Safeguards
0FFICIAL RECORD COPY
RL PB 88-09 - 0001.0.0
1l
06/24/88
\\
8807250165 080707
ADOCK 05000277
O
PNV
o
j'
I.
Philadelphia Electric Company-
2
JUL' 0 7 1988
.
cc w/ enc 1:
John S..Kemper, Sr., Senior Vice President-Nuclear
J. W.~ Gallagher, Vice_ President, Nuclear Services
E. C. . Kistner, Chairman, Nuclear Review Board
- Dickinson M. Smith, Vice President, Peach Bottom Atomic Power Station
Jack Urban, General Manager, Fuels Department, Delmarva Power & Light Co.
John F. Franz, Plant Manager, Peach Bottom Atomic Power Station
Troy B. Conner, Jr. , Esquire
W.-H. Hirst, Director, Joint Generation Projects Department,
-Atlantic Electric
Bryan W. Gorman, Manager, External Affairs
Eugene J. Bradley, Esquire, Assistant General Counsel (Without Report)
Raymond L. Hovis, Esquire
~ Thomas Magette, Power Plant Siting, Nuclear Evaluations
-
W.-.M. Alden, Director, Licensing Section
Doris Poulsen, Secretary of Harford County Council
-Dave Honan
Public Document Room (PDR)
Local Public Document Room (LPDR)
. Nuclear SafetyL information Center QSIC)
NRC Resident Inspector
Commonwealth of Pennsylvania
bec w/ encl:
Region I Docket Room (with concurrences)
Management Assistant, DRMA (w/o enc 1)
Section Chief, DRP
PA0 (2) SALP and All Inspection Reports
Robert J. Bores, DRSS
0$
M'* NN
RI:DRSS
RI:DRSS
RI:CRSS
Gordon/ejr
Lazaru
BEllamy
6/3Q88
g/ r/88
y/6/88
, )
0FFICIAL RECORD COPY
RL PB 88-09 - 0002.0.0
06/24/88
_
_
.
- .
se
'
. . . m
.
.
'
l
PHILADELPHI A ELECTRIC COM PANY
2301 M ARKET STREET
P.O. BOX 8699
PHILADELPHI A. PA 19101
(2:5) 848 soci
10 CPR 2.201
""I;OrN='00"'"
May 16, 1988
vC
,NUCLEAN SE R VIC E S
Docket Nos. 50-277
50-278
Mr. Ronald R.
Bellamy, Chief
Facilities Radiological Safety
and Safeguards Branch
U.S.
Nuclear Regulatory Commission
Region I
Attn: . Document Control Desk
20555
Subject:
Response to NRC Combined Inspection
Report 50-277/88-09 and 50-278/88-09 for
Peach Bottom Atomic Power Station
Dear Mr. Bellamy:
Your letter dated April 16, 1988 transmitted Combined
Inspection Report 50-277/88-09 and 50-278/88-09 for the routina
emergency preparedness inspection conducted February 29 through March
3,
1988.
Appendix A of your letter identified an item which does not
appear-to be in full compliance with NRC requirements.
Our response
to this violation is provided in an At tachment to this letter.
If you haVe any questions or require additional information,
please do not ht
tate to contact us.
Very truly yours,
Attachment
cc:
Addressee
W.
T., Russell,IAdmi'nistrator, Region I,
T.
P.' Johnson, USNRC Senior Resident Inspector
T.
Magette, State of Maryland
"
'
~[ kY
r-
T
C
.
.-?.
.
Attachment
"
Page 1 of 2
.'
Restatement of Violation:
r
'
10 CFR 50.54(t) requires an annual review of the emergency
preparedness program and that the results of the review, along with
recommendatione for improvements, be documented and repotted to the
licensee's corporate and plant management and retained for a period of
,e
five years.
Ccatrary to the above, the licensee did.not mainthin
documentation of the 1983 annual emergency preparedness audit, did not
perform an annual audit during 1985, and did not report the results of
,the 1986 annual audit to appropriate corporate and plant management.
This is a Severity Level IV Violation (Supplement VIII)
Response:
In the following-response, the term "review" refers to the
activities required by 10 CFR 50.54(t), and the term "audit" refers to
the activities required by PBAPS Technical Specification 6.5.2.8.e.
Admission or Denial of the Violation:
Philadelphia Electric Company acknowledges the violation as
stated.
Reason'for the Violation:
The reason for not maintaining documentation of the 1983 annual
emergency preparedness review, not performing an annual review during
1985, and not reporting the results of the 1986 annual review to
appropriate corporate and plant management is that no clear
assignments of responsibility for generation, distribution and
retention of an annual emergency preparedness review existed at the
time.
The 10 CPR 50.54(t) review in 1986 was performed by Enercon
Services under a contract administered by the Emergency Preparedness
Section.
It was felt by Emergency Preparedness after the review was
completed that Emergency Preparedness could not issue the results of
the review because they lacked the required independence.
This
l
situation was not resolved and consequently the distribution was not
completed.
i
l
L
-
. _ _ .
- _ - _ _ _ _ _ _ _ _ _ _ ,
,
,-
l%
hw
'
'
'
Attachment
Page 2 of 2
,
Significance of Violation:
From 1983 through today, PBAPS has demonstrated an adequate
emergency response capability through the effective conduct of drills
and exercises.
The results of the 10 CFR 50.54(t) review performed in
1986 did not identify any significant conditions adverse to the
quality of the Emergency Preparedness Program. -The review stated,.
'"The. Review Team determined, based on the information, facilities
equipment reviewed and the individuals interviewed, that the PBAPS
Emergency Preparedness Program is generally in a state of preparedness
to respond adequately to an emergency."
Further, although reviews
were not performed in accordance with 10 CFR 50.54(t), the annual
audit of the.PBAPS Emergency Preparedness Program as required by the
Technical Specifications has been performed each year.
Corrective Actions Taken and Results Ach}eved:
The failure to maintain documentation of the 10 CFR 50.54(t)
review performed in 1983 and the failure to perform a review in 1985
cannot be retroactively corrected.
The 1986 10 CFR 50.54(t) review
results have been reevaluated by the Emergency Preparedness Section,
and the open items have been distributed to appropriate corporate and
plant management for resolution.
Action plans have been developed for
the' tracking and closure of the items.
Corrective Action Taken to Avoid Future Non-Compliance:
Nuclear Quality Assurance (NQA), formerly the Nuclear
Operations Quality Assurance Division, did complete the 1987 10 CFR 50.54(t) review, and has been assigned the responsibility for the
performance of future reviews and the distribution and retention of
the results.
This group has had the responsibility for the
performance of the audits of the Emergency Preparedness Program as
required by the PBAPS Technical Specifications.
The results of the 10
CPR 50.54(t) reviews will be distributed to appropriate corporate and
plant management.
The findings and associated corrective actions and
recommendations will be dispositioned and tracked in accordance with
Emergency Preparedness Section procedures.
Date When Full Compliance Will Be Achieved:
l
l
The reevaluation of the results of the 10 CFR 50.54(t) review
!
performed in 1986 was completed in January 1988 and individual items
!
were entered into the Emergency Preparedness Action Item Tracking
System.
Completion dates for resolution of all items riot previously
closed were established as of March 31, 1988.
!
9
k