Notice of Issuance of Amend to License DPR-65.Amend Changes Tech Spec 3.9.20, Spent Fuel Pool, by Deleting Footnote Limiting Storage of Consolidated Spent Fuel to Five Consolidated Spent Fuel Storage Canisters
ML20151B943
Person / Time
Site: Millstone 
Issue date: 03/31/1988
From: Jaffe D
Office of Nuclear Reactor Regulation
To:
Shared Package
ML20151B730 List:
References
TAC-65274, NUDOCS 8804120047
Download: ML20151B943 (2)


Text

a e

7590-01 UNITED STATES NUCLEAR REGULATORY COMISSION j

NORTHEAST NUCLEAR ENERGY COMPANY, ET AL.

1 DOCKET NO. 50-336 NOTICE OF ISSUANCE OF AMENDMENT TO FACILITY OPERATING LICENSE The U. S. Nuclear Regulatory Comission (the Comission) has issued Amendment No.128 to Facility Operatino License No. DRP-65, to Northeast Nuclear Energy Company, The Connecticut Light and Power Company, and Western Massachusetts Electric Company, which revised the Technical Specifications for operation of the Millstone Nuclear Power Station, Unit 2, locsted in the Town of Waterford, Connecticut. The amendment was effective as of the date j

of its issuance.

The amendment changes Technical Specification 3.9.20. "Spent Fuel Pool",

which deletes a footnote which had li,nited the storage of consolidated spent fuel to five consolidated spent fuel storage canis,rs.

The application for the amendment complies with the standards and reouire-ments of the Atomic Energy Act of 1954, as amended (the Act), and the Comission's ruler and rcgulations. The Comission has made appropriate findings as required by the Act and the Conmission's rule; and regulations in 10 CFR Chapter 1, which are set forth in the license amendment.

Notice of Consideration of Issuance of Amendment and Opportunity for Prior j

Hearing in connection with this action was published in the FEDERAL REGISTER cn January 4,1988(53FR87).

No request for a hearing or petition for lean to I

intervene was fileo following this notice.

8804120047 800331]

ADOCK 050g3 6 DR

' The Comission has prepared an Environmental Assessment and Finding of No Significant Impact related to the action and has concluded that an environ-mental impact statement is not warranted because there will be no environmental impact attributed to the action beyond that which has been predicted and described in the Comission's Final Environmental Statement for the facility dated June 1973.

For further details with respect to the action, see (1) the application for amendment dated May 21, 1986, as supplemented by letter dated August 11, 1987, (2) Amendment No.128 to Facility Operating License No. DPR-65, and (3) the Environmental Assessment and Finding of No Significant Impact (53 FR 7065). All of these items are available for public inspection at the Comission's Public Document Room,1717 H Street, N.W., Washington, D.C., and at the Vaterford Public Library, 49 Rope Ferry Road, Waterford, Connecticut.

A copy of items (2) and (3) may be obtained upon request addrested to the U.S.

Nuclear Regulatory Comission, Washington, D.C. 20555, Attention:

Director, Division of Reactor Projects I/II.

Dated at Rockville, Maryland this 31 -

day of March

, 1988.

FOR THE ICLEAR REGULATORY COMMISSION ro\\ectManager David H.

e, 1

Project Directorate II-2 Division of Reactor Projects-I/II Office of Nuclear Reactor Reaulation

-