Requests Addl Info Re Emergency Plan Requirements for Fuel Storage.Lists Questions Requiring Licensee Response Needed for Evaluation of Emergency Action Levels in Emergency Plan.Rev of Site Emergency Plan Suggested
ML20150D890
Person / Time
Site: Dresden Constellation icon.png
Issue date: 07/07/1988
From: Erickson P
Office of Nuclear Reactor Regulation
To: Morgan W
COMMONWEALTH EDISON CO.
References
NUDOCS 8807140216
Download: ML20150D890 (3)


Text

- - -

e.  %

e no

  • uq'o UNITED STATES

' ~

8 n NUCLEAR REGULATORY COMMISSION

$ U WASHINGTON, D. C. 20666 k, j# July 7, 1988 Docket No. 50-10 Mr. W. E.' Morgan -

Nuclear Licensing Administrator Comonwealth Edison Company One First National Plaza Post Office Box 767 Chicago, ILL 60690-0767

Dear Mr. Morgan:

SUBJECT:

EMERGENCY PLAN REQUIREMENTS FOR DRESDEN UNIT 1 FUEL STORAGE-REQUEST FOR ADDITIONAL INFORMATION Our review of the Dresden Unit 1 Decomissioning Plan in conjunction with the Dresden Site Emergency Plan ieveals that the Emergency Plan does not fully adJress the spent fuel storage at Dresden 1. An analysis of the skin dose resulting from a worst case accident at Dresden 1 is needed for our evaluation of the Emergency Action Levels in the Emergency Plan.

Please respond to the following questions within 45 days of your receipt of this letter:

1. What are the worst case skin doses projected onsite, in areas that would be occupied, and at the site boundary for a fuel rod rupture accident at Dresden 17
2. What protective actions would be implemented onsite and offsite in the event of a worst case fuel rod rupture accident at Dresden 17
3. In the event of an emergency at Dresden 1, what licensee staff augmentation would '.>e implemented?
4. What are the Emergency Action Levels for a fuel handling accident at Dresden 1?
5. What are the Emergency Action Levels for a noble gas release at Dresden l?

0 8807140216 880707 PDR ADOCK 05000010 F PNU

.e n M'r. W. E. Morgan We have determined that the Site Emergency Plan should be revised to include emergency actions related to the storage of fuel at Dresden 1. Although the revision to the site Emergency Plan would be handled separately from the Dresden 1 Decommissioning Plan, the revision must be accepted by the NRC prior to approval of the Decommissioning Plan.

Sincerely, A &

Peter B. Erickson, Project Manager Standardization and Non-Power Reactor Project Directorate Division of Reactor Projects III, IV, Y and Special Projects Office of Nuclear Reactor Regulation l

l

. July 7, 1988 Mr. II. E. Morgan We have determined that the Site Emergency Plan should be revised to include emergent.y actions related to the storage of fuel at Dresden 1. Although the revision to the site Emergency Plan would be handled separately from the Dresden 1 Decommissioning Plan, the revision must be accepted by the NRC prior

'.a approval of the tecommissioning Plan.

Sincerely, original signed by Peter B. Erickson, Project Manager Standardization and Non-Power Reactor Project Directorate Division of Reactor Projects III, IV, Y and Special Projects Office of Nuclear Reactor Regulation Distribution:

Docket F14 6 OGC-Rockville RMeck hRC & Local PDRs EJordan LRubenstein l PDSNP Reading BGrires i DCrutchfied ACRS (10)

EHylton FWitt l

  • See Previous Concurrence PDSNP* PDSNP* ECEB* PEPB* a SNP l PErickson:1s EHylton FWitt RMeck u costein 07/06/88 07/06/88 07/06/88 07/06/88QR7/q/88 i