Forwards IE Inspec Rept 50-321/78-28 & 50-366/78-36 on 780815-18.No Items of Noncompliance Noted
ML20150D847
Person / Time
Site: Hatch  Southern Nuclear icon.png
Issue date: 11/20/1978
From: Long F
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To: John Miller
GEORGIA POWER CO.
Shared Package
ML20150D849 List:
References
781103, NUDOCS 7812070097
Download: ML20150D847 (2)


See also: IR 05000321/1978028

Text

l'

1e

e

UNITEo STATES

pm af oug'o

NUCLEAR REGULATORY COMMISSION

4

REGION il

,

g

101 MARIETTA STREET. N.W.

5

. f

ATL ANT A, GEORGI A 30303

g

MS

M

%.....#

In Reply Refer To:

RII:HLW

50-321/78-28

50-366/78-36

Georgia Power Company

Atta: Mr. J. H. Miller, Jr.

Executive Vice President

270 Peachtree Street, N. W.

Atlanta, Georgia

30303

Gentlemen:

This refers to the inspection conducted by Mr. H. L. Whitener of this

office on August 15-18, 1978, of activities authorized by NRC Operating

License Nos. DPR-57 and NPF-5 for the Hatch Units 1 and 2 facilities, and

to the discussion of our findings held with Mr. Nix at the conclusion of

the inspection.

Areas examined during the-inspection and our findings are discussed in the

enclosed inspection report. Within these areas, the inspection consisted

of selective examinations of procedures and representative records, inter-

views with personnel, and observations by the inspector.

Within the scope of this inspection, no items of. noncompliance were disclosed.

We have examined actions you have taken with regard to previously reported

un esolved items.

The status of these items is dis'

sed in the enclosed

report.

Based on discussions during this inspection, it is our understanding that

you will revise your surveillance procedure to incorporate specific acceptance

criteria and data requirements as delineated in the enclosed report and

will establish written guidelines for the selection of a representative

sample of suppressors for functional testing.

In accordance with Section 2.790 of the NRC's " Rules of Practice", Part 2,

Title 10, Code of Federal Regulations, a copy of this letter and the enclosed

If

inspection report vill be placed in the NRC's Public Document Room.

this report contains any information that you (or your contractor) believe

to be proprietary, it is necessary that you make a written application

within 20 days to this office to withhold such information from public

disclosure.

Any such application must include a full statement of the

reasons on the basis of vbich it is claimed that the information is

proprietary, and should be prepared so that proprietary information

7812070og7

o

-

. _ - - _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ - _ _ _ _ _ - _ _ _ - _ _ _ _ _

_

_

_.

__

_ _ _ _

_

-

.

4

Georgia Power Company

-2-

ggy 3

g

identified in the application. is contained in a separate part of the

document.

If we do not hear from you in this regard within the specified

period, the report will be placed in the Public Document Room.

Should you have any questions concerning this letter, we will be glad to

discuss them with you.

Since al -

U %~

F. J. Long, Chief

Reactor Operations and Nuclear

Support Branch

Enclosure:

Inspection Report Nos. 50-321/78-28

and 50-366/78-36

cc w/enci:

Mr. C. E. Belflower

Site QA Supervisor

Plant E. I. Hatch

P. O. Box 442

Baxley, Georgia

31513

Mr. M. Manry, Plant Manager

Plant E. I . Hatch

P. O. Box 442

Baxley, Georgia

315i3

<

. _ .

- - - - - - - ~ _ _ _ _ . . _ _ _ _ _ _ _ _ _ _ _ , _ . ___ _ _ _ _ _ _ _ _ _ _

_