Forwards IE Inspec Rept 50-315/78-29 & 50-316/78-27 on 780925-29 & Notice of Violation.Notice of Violation W/Held Per 10CFR2.790(d)
ML20150D748
Person / Time
Site: Cook  American Electric Power icon.png
Issue date: 10/29/1978
From: Hind J
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To: Dolan J
INDIANA MICHIGAN POWER CO.
Shared Package
ML20150D751 List:
References
781024, NUDOCS 7812060388
Download: ML20150D748 (2)


See also: IR 05000315/1978029

Text

q_

'

IPDR

t# *W

UNITED STATES

4

/

NUCLEAR REGULATORY COMMISSION

'

.

,

y 'l pl

j

REGloN iil

5 .' h

W-

799 ROOSEVELT ROAD

g

'k. .?

8

GLEN ELLYN BL LINCIS 60137

.....

OCT 2~4 f978'

Docket No. 50-315

Docket No. 50-316

<

o

American Electric Power Service

Corporation

Indiana and Michigan Power Company

ATTN:

Mr. John E. Dolan, Senior

Executive Vice President

Engineering

2 Broadway

New York, NY

10004

Gentlemen:

This refers to the.inepection conducted by Messrs. J. R. Creed and

T. J. Madeda of this office on September 25-29, 1978, of activities

at Donald C. Cook Nuclear Power Plant, Units 1 cnd 2 authorized by

NRC Operating Licenses No. DPR-58 and No. DPR-74 and to the dis-

cussion of our findings with Messrs. D. Shaller, L. Matthias,

F. Arsenault and other members of your staff at the conclusion of

the inspection.

The enclosed copy of our inspection report identifies areas

examined during the inspection. Within these areas, the

inspection consisted of a selective examination of procedures

and representative records, observations, and interviews with

personnel.

During this inspection, certain of your activities appeared

to be in noncompliance with NRC requirements, as described

in the enclosed Appendix A.

This notice is sent to you pursuant to the provisions of

Section 2.201 of the NRC's " Rules of Practice," Part 2, Tit.le

10, Code of Federal Regulations.

Section 2.201 requires you

to submit to this office within twenty days of your receipt

of this notice a written statement or explanation in reply,

including for each item of noncompliance: (1) corrective

action taken and the results achieved; (2) corrective action

to be taken to avoid further noncompliance; and (3) the date

when full compliance will be achieved.

5

7 812 0 C 0 388

Af MCW.RNi 00idAINS

'

10 CiR 2.793 (d) INf 0RMAliON

k

1

l

-)

r

7

l

..

..

American Electric Power

-2-

Service Corporation

Indiana and Michigan.

Power Company

!

Areas examined during this inspection concern a subject

matter which is exempt from disclosure according to Section

2.790 of the NRC's " Rules of Praqtice," Part 2 Title 10,

Code of Federal Regulations. Consequently, the enclosure

to this letter, our report of this inspection, and your

response to the noncompliance identified in the enclosure

to this letter will not be placed in the Public Document

Room. Therefore, your statement of corrective action

regarding the noncompliance' identified in the enclosure

should be submitted as a separate enclosure to your trans-

mittal letter.

We will gladly discuss any questions you have concerning this

inspection.

Sincerely,

J. Y

J. A. Hind, Chief

Safeguards Branch

Enclosures:

1.

Appendix A, Notice

of Violation-

2.

IE Inspection Rpts

No. 50-315/78-29

and No. 50-316/78-27

(Part 2.790(d) Information)

cc'w/ encls:

D. V. Shaller, Plant Manager

Central Files

Reproduction Unit NRC 20b

Ac w/o encls:

/ PDR

Local PDR

Lit!C"c::i C0r:1 AINS

10 CF : 2.*/D (d) 1:;f 0Rf4ATIO:1

. . .

. - . - . . . . - - . - . - - .