i March 22, 1988 a
=
Docket Nos.
50-277/278 Pr. William Alden Philadelphia Electric Company 2301 Market Street Philadelphia, Pennsylvania 19101
Dear Mr. Alden:
l
SUBJECT:
STATUS UPDATE ON COMPLETED ACTIONS We are requesting your assistance in updating the status of 'your implementation of certain issues for which the staff's review has been completed.
You have provided previous similar updating information in letters dated May 29, 1986 and September 23,'1987.
Some of the previous dates were projected dates and in some cases you indicated that the informatior: provided to you was insufficient to permit identification of the issue and its completion date.
Using the information in the enclosure, please provide an I
update on when the Philadelphia Electric Company completed or will complete all actions (construction, procedures, operational testing and training) necessary l
to resolve the issue.
Sincerely,
/s/
Robert E. Martin, Project Manager t
Pro,iect Directorate I-2 Division of Reactor Projects I/II i
Enclosure:
As stated
.DISTDIBUTION
! Docket File ]
NRC PDR/LPDR~
PDI-2 Reading SVarga/B80ger 1
WButler 8803240475 880322 M0'Brien PDR ADOCK 05 27 RMartin/RClark P
i OGC 4
EJordan/JPartlow ACRS (10) kIf/PO PDI-2/D Mardin:mr WButler
$n A
$ ltOy
'o UNITED STATES t
NUCLEAR REGULATORY COMMISSION j
WASHINGTON, D. C. 20565
?g
,/
March 22, 1988 Docket Nos.
50-?77/278 Mr. William Alden Philadelphia Electric Company 2301 Market Street Philadelphia, Pennsylvania 19101
Dear Mr. Alden:
SUBJECT:
STATUS UPDATE ON COMPLETED ACTIONS We are requesting your assistance in updating the stetus of your implementation of certain issues for which the staff's review has been completed. You have provided previous similar updating information in letters dated May 29, 1986 and September ?3, 1987.
Some of the previous dates were projected dates and in some cases you indicated that the infornation provided to you was insufficient to permit identification of the issue _ar.d its completion date.
Using the information in the enclosure, plecse provide an update on when the Philadelphia Electric Company completed or will complete all actions (construction, procedures, operational testing and training) necessary to resolve the issue.
Sincerely, EckKM&
/ Robert E. Martin, Project Manager Project Directorate I-2 Division of Reactor Projects I/II
Enclosure:
As stated i
I I
J
a i
er i
NRC TAC NO.
Date of Principal Correspnndence (Unit 2/ Unit 3)
Relevant to Status of the issue i
(NRC unless otherwise indicated) j 07945/46 PEco:
03/18/87 l
08225/6 PEco:
1?/20/77 08500/1 07/02/84 43931/2 08/19/81 45157/8 0?/11/85 47375/6 06/10/85 48404/5 04/11/84 48469/70 02/10/84 A8507 03/14/83 48874/5 03/21/84 49194/5 12/05/83 i
51019/20 03/21/84 i
4 51267/8 PECo:
08/24/87 51354/5 03/28/84 l
l 51404 02/24/84 52377/8 05/04/84 52681/2 02/27/85 i
I 53273/4 02/07/85 53331 01/20/84 53351 PEco:
12/22/83 53485 06/01/84 53617/8 and 60227/8 01/15/88
e o
i 2
NRC TAC NO.
Date of Principal Correspondence (Unit 2/ Unit 3)
Relevant to Status of the Issue i
(NRC unless otherwise indicated) 54291/2 03/14/86 54367/8 11/19/85 54488/9 06/20/84 54617/8 10/03/84 54766/7 02/20/85 54793/4 11/09/84 54830/1 PEco:
04/19/84 55157/8 11/?2/85 55174/5 06/20/84 55807 03/19/85 55944/5 03/19/85 i
55946/7 03/05/85
$6940/1 06/18/85 56949/50 12/10/85 56953/4 07/30/86 57807/8 09/1?/86 59012/3 02/19/86 60222/3 07/0?/P.6 60555/6 08/11/86 61973 01/08/87 j
64442 09/11/87 64539/41 09/24/87 64540/42 0?/22/88 64543/4 06/02/87 6492/3 09/22/87 j
64809/10 03/03/88
..