Amend 114 to License DPR-59,adding Requirement That Capacity Test for Main Control Room Emergency Ventilation Air Supply Sys Be Performed Every 18 Months
ML20149L458
Person / Time
Site: FitzPatrick 
(DPR-59-A-114)
Issue date: 02/17/1988
From: Capra R
Office of Nuclear Reactor Regulation
To:
Shared Package
ML20149L461 List:
References
NUDOCS 8802240241
Download: ML20149L458 (5)


Text

-

  1. pn
  • tog $o, UNITED sTATI i

[3,e (i NUCLEAR REGULAVOF f COMMISSION

(

l WASHINGTOh 9.C.20555 yf POWER AUTHORITY OF THE STATE OF NEW YORK DOCKET N0. 50-333 JAMES A. FITZPATRICK NUCLEAR POWER PLANT AMENDifENT TO FACILITY OPERATING LICENSE Amndment No.

114 License No. OPR-59 1.

The Nuclear Regulatory Comission (the Commission) has found that:

A.

The application for amendment by Power Authority of the State of New York (the licensee) dated April 15, 1986, complies with the standards and reouirements of the Atomic Energy Act of 1954, as amended (the Act) and the Comission's rules and regulations set forth in 10 CFR Chapter I; B.

The facility will operate in conformity with the application, the provisions of the Act, and the rules and regulations of the Comission; C.

There is reasonable assurance (i) that the activities authorized by this amendment can be conducted without endangering the health and safety of the public, and (ii) that such activities will be conducted in compliance with the Comission's regulations; D.

The issuance of this amendment will not be inimical to the comor, defense and security or to the health and safety of the public; and E.

The issuance of this amendment is in accordance with 10 CFR Part 51 of the Comission's regulations and all applicable requirements have been sattsfied.

2.

Accordingly, the license is amended by changes to the Technical Specifications as indicated in the attachment to this license amendment, and paragraph 2.C.(2) of Facility Operating License No. DPR-59 is hereby amended to read as follows:

e802240241QO2{33 g0 PDR ADOCK PDR P

2-(2) Technical Specifications The Technical Specifications contained in Appendices A and B, as revised through Amendment No.114, are hereby incorporated in the license.

The licensee shall operate the facility in accordance with the Technical Specifications.

3.

This license amendment is effective as of the date of its issuance.

FOR THE NUCLEAR REGULATORY COMMISSION a ad CL. Cw -J Robert A. Capra, Director Project Directorate I-l Division of Reactor Projects, I/II

Attachment:

Changes to the Technical Specifications Date of Issuance: February 17, 1988 1

,8 naaro,

u

/

UNITED STATES

[ ',,'c. c [\\

t

^

q NUCLEAR REGULATORY COMMISSION llT,.* '. ' " }/ - lE W ASHINGTON. D, C. 20555

%,,Y..,,

ATTACHMENT TO LICENSE AMENDMENT NO.114 FACILITY OPERATING LICENSE NO. DPR-59 DOCKET N0, 50-333 Revise Appendix A as follows:

Remove Pages Insert Pages 238 238 243 243 I

e 1

JAFNPP I

3.11 (cont'd) 4.11 (cont'd) ventilation a'.c supply fan and/or filter may be

b. Di-octylphtalats (DOP) test for particulate out of service for 1 month.

filter efficiency greater than 99% for particulate greater then 0.3 micron size.

2. The main control room air radiation monitor shall be operable whenever the control room
c. Freon-112 test for charcoal filter bypass as emergency ventilation air supply fans and a measure of filter efficiency of at least filter trains are required % be operable by 99.5% for halogen removal.

3.11.A.1 or filtration of the control room ventilation intake air must be initiated.

d. A sample of charcoal filter shall be analyzed once a year to assure halogen
3. The control room emergency ventilation system removal efficiency of at least 99.5%.

l shall not be out of service for a period exceeding 7

days during normal reactor

2. Operability of the main control room air intake operation or cofueling operations.

In the radiation monitor shall be tested once/3 months.

event that the system is not returned to service within 7 days the reactor will be

3. Temperature transmitters and differential shutdown in an orderly manner and in the Cold pressure switches shall be calibrated once/

Shutdown Condition within 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> or if operating cycle.

refueling operations are in progress, such operations will be terminated in an orderly

4. Main control room emergency ventilation air manner.

supply system capacity shall be tested once every 18 months to assure that it is 110 % of the design value of 1000 efs.

Amendment No.

114 238

3 JAFNPP 3.11 & 4.11 BASES A. Main Control Room 7ent11stion System One main control room emergency ventilation air conducted in accordance with manufacturers' supply fan provides adequate ventilation flow reconunendations.

under accident conditions. Should one emergency ventilation air supply fan and/or fresh air The purpose of the emergency ventilation air filter train be out of service during reactor supply system capacity test is to assure that

)

operation, the allowable repair time of 1 month sufficient air is supplied to the main control is justified, based on the 3 month test inter-room so that a slight positive pressure can be val.

maintained, thereby minimizing in-leakage.

The 3 month test interval for the main control B. Crescent Area Ventilation room emergency ventilat.on air supply fan and dampers is sufficient since two redundant Engineering analyses indicate that the temper-trains are provided and neither is normally in ature rise in safeguards compartments without operation.

adequate ventilation flow or cooling is such that continued operation of the safeguards A pressure drop test across each filter and equipment or associated auxiliary equipment across the filter system is a measure of filter cannot be assured.

system condition.

DOP injection measures particulate removal efficiency of the high C. Battery Room Ventilation efficiency particulate filters. A Freon-112 test of charcoal filters is essentially a Engineering analyses indicate that the temper-leakage test.

Since the filters have charcoal ature rise and hydrogen buildup in the battery, of known efficiency and holding capacity for and battery charger cowartments without elemental lodine and/or methyl iodine, the test adequate ventilation is such that continuous also gives an indication of the relative operation of equipment in these compartments efficiency of the installed system.

cannot be assured.

Laboratory analysis of a sample of the charcoal filters positively demonstrates halogen removal D. Emergency Service Water System officiency. These tests ars The ESWS has two 100 percent cooling capacity i

pumps, each powered from a separate standby power supply.

The ESWS utilizes lake water to the cooling system of the emergency diesel generators.

The system will also supply water to those components of the RSCLCS which are required for emergency conditions during a loss of power condition.

These include ECCS pumps and area unit coolers.

Amendment No.

114 243

-