ENCLOSURE 1
Virginia Electric and Power Company
Docket Nos. 50-338, 50-339
North Anna Units 1 and 2
During the Nuclear Regulatory Commission (NRC) inspection conducted on
November 20 - December 18,198'/ , violations of NRC requirements were identi-
fied.
The violations involved a failure to follow the . requirements of a
radiation work permit and failure to properly implement post maintenance
testing.
In accordance with the "General Statement of Policy and Procedure
for NRC Enforcement Actions," 10 CFR Part 2, Appendix C (1987), the violations
are 1isted below:
~
I
Technical Specification (T.S.) 6.11 requires that procedures for personnel
radiation protection shall be prepared consistent with the requirements
,
of 10 CFR Part 20 and shall be approved, maintained, and adhered to for
.
all operations involving personnel radiation exposure.
Health Physics
'
procedure 5.3.20 "Initiating, Using, Extending and Terminating a Radiation
Work Permit (RWP)" requires a radiation worker to comply with the require-
,
ments, instructions, and precautions of the RWP.
Contrary to the above, on November 24, 1987, several operations personnel
failed to follow the requirements of RWP 87-3156, which required a whole
body frisk after leaving the area, in that they failed to perform a whole
body frisk at the designated frisking station.
This is a Severity Level IV violation (Supplement V).
(Unit 1 only)
Pursuant to the provisions of 10 CFR 2.201, Virginia Electric and Power Company
is hereby required to submit a written statement or explanation to the Nuclear
Regulatory Commission, ATTN:
Document Control Desk, Washington, DC 20555,
with a copy to the Regional Administrator, Region II, and a copy to the NRC
Resident Inspector, North Anna, within 30 days of the date of the letter
transmitting this Notice. This reply should be clearly marked as a "Reply to a
Notice of Violation" and should include [for each violation]:
(1) admission or
'
denial of the violation, (2) the reason for the violation if admitted, (3) the
corrective steps which have been taken and the results achieved, (4) the
'
corrective steps which will be taken to avoid further violations, and (5) the
date when full compliance will be achieved. Where good cause is shown, con-
sideration will be given to extending the response time. If an adequate reply
jgk2110171 880119
"
o
ADOCK 05000330
.
?.
--
..
,;...
(
.
!
'
Virginia Electric and Power Company
2
Docket Nos. 50-338,'50-339
- North Anna Units 1 and 2-
- is not received within the time specified in this Notice, an order may be
issued to show cause why the license should not be modified, suspended, or
l-
revoked or why such other action as may be proper should not be taken.
FOR THE NUCLEAR REGULATORY COMMISSION
.
p J. Nelson Grace
Regional Administrator
Dated at Atlanta, Georgia
this 15tMay of
Jan.
1988