Forwards Status Rept on Std Plant Design Technical Reviews for Jan 1988.Problems W/Meeting Listed Input Dates Requested within 1 Wk of Memo Receipt
ML20148C913
Person / Time
Site: 05000601
Issue date: 01/19/1988
From: Rubenstein L
Office of Nuclear Reactor Regulation
To: Congel F, Houston R, Partlow J, Rowe J, Shao L
Office of Nuclear Reactor Regulation, NRC OFFICE OF NUCLEAR REGULATORY RESEARCH (RES)
References
PROJECT-669R, PROJECT-671R, PROJECT-675R, PROJECT-676R NUDOCS 8801250289
Download: ML20148C913 (14)


Text

(og UNITED STATES

/ NUCLEAR REGULATORY COMMISSION y 'g p, ,

g '0-E W ASHINGTON, D. C. 20555 I

% y / January 19, 1988

....+

Docket No. 50-601 >

Project Nos. 669, 671, 675, and 676  !

I l

l MEMORANDUM FOR: L. Shao, Director I Division of Engineering and System Technology, NRR J. Partlow, Director Division of Reactor Inspection l and Safeguards, NRR l l

F. Congel, Director Division of Radiation Protection and Emergency Preparedness, NRR J. Rowe, Director Division of Licensee Performance and Quality Evaluation, NRR '

R. W. Houston, Acting Director ,

Division of Reactor Accident Analysis, RES l l

FROM: Lester S. Rubenstein, Director Standardization and Non-Power Reactor Project Directorate Division of Reactor Projects III, IV, V and Special Projects, NRR

SUBJECT:

STATUS REPORT ON STANDARD PLANT DESIGN TECHNICAL REVIEWS  !

l Attached is the January status report concerning the current review milestones for each of the standard plant projects (EPRI, ABWR, RESAR SP/90, and CE System 80+).

  • Note the column, "Expected Input Date" reflect dates established in the June 25, i 1987 "Program Plan For Standard Plant Review" or dates for which modification I CONTACT:

T. Kenyon NRR/PDSNP Ext. 28206 8801250289 880119 PDR ADOCK 050 i R

l r

was agreed to by PDSNP and the review branch. Category 1 items have been discussed with the appropriate Assistant Directors. I request any problems in l meeting these input dates be identified to me by the appropriate Assistant j Director within a week of receipt of this memo. '

,S Lltw Lester S.'Rubenstein, Director Standardization and Non-Power Reactor Project Directorate Division of Reactor Projects III, IV, Y and Special Projects, NRR

Enclosure:

As stated cc: T. Murley J. Sniezek F. Miraglia J. Richardson C. Y. Cheng L. B. Marsh C. McCracken A. Thadani J. Joyce  !

J. Mauk i F. Rosa J. Craig M. W. Hodges B. Grimes l R. Erickson '

D. Matthews R. Barrett l L. Cunningham H. Miller -

A. Beach W. Regan, Jr.

J. Murphy G. Bagchi

e Date: January 22, 1988 i

REVIEW STATUS REPORT ON WESTINGHOUSE RESAR SP/90 l PDA REVIEW Expected Division / Due Input Branch Reviewer Modules Subject

  • Milestone Date Date Cat.** Comments DEST /EMTB Johnson 1, 4, 5, 5&8, 7, Materials Engineering Draft SER 3/31/88 3/31/88 3 Awaiting 10 to P.M. Input DEST /EMB Hou/Brammer*** 1,4,5,7, Mechanical Engineering Draft SER 3/31/88 3/31/88 3 Awaiting to P.M. Input DEST /ESGB Staley 3 Hydrology Draft SER 3/31/88 3/31/88 3 Input Rec'd to P.M. 10/26/87 Giese-Koch 3 Geology & Seismology Draft SER 3/31/88 3/31/88 3 Awaiting to P.M. Input Chan 7 Civil Engineering Draft SER 3/31/88 3/31/88 3 Awaiting to P.M. Input
  • See September 29, 1987 meno for complete listing of review assignments
    • Category definitions:
1. AD or above attention requested
2. Branch Chief attention requested
3. On schedule
4. Complete
      • Brammer Providing Assistance

a Date: January 22, 1988 REV?EW STATUS REPORT ON WE5TINGHOUSE RESAR SP/90 PDA REVIEW (Cont.)

Expected Division / Due Input Branch Reviewer Modules Subject

  • Milestone Date Date Cat.** Comments DEST /ECEB Wing 1, 6&8, 10, 13 C.._-.ical Engineering Draft SER 3/31/88 3/31/88 3 Input Rec'd to P.M. 11/23/87 Notley 13 Fire Protection RAI's to 7/31/87 1/15/88 2 -

P.M.

DEST /SICB Burrows 9, 13, 15 Instrumentation & Draft SER 3/31/88 3/31/88 3 -

Controls to P.M.

DEST /SELB Trehan 9, 13 Electrical Engineering Draft SER 3/31/88 3/31/88 3 Input Rec'd to P.M. 12/17/87 DEST /SPLB Shum ('.ead) 1, 10, 13 Containment Systems Draft SER 3/31/88 3/31/88 3 Awaiting to P.M. Input Wagne.' 688, 7 Plant Systems Draft SER 3/31/88 3/31/88 3 Awaiting to P.M. Input Walker 7 Equipment Qualification Draft SER 3/31/88 3/31/88 3 Awaiting to P.M. Input

  • See September 29, 1987 memo for complete listing of review assignments
    • Category definitions:
1. AD or above attention requested
2. Branch Chief attention requested
3. On schedule
4. Complete

Date: January 22, 1988 REVIEW STATUS REPORT ON HESTINGHOUSE RESAR SP/90 PDA REVIEW (Cont.)

Expected Division / Due Input Branch Reviewer Modules Subject

  • Milestone Date Date Cat.** Comments DEST /SPLB Gill a Plant Systems Draft SER 3/31/88 3/31/88 3 Awaiting (cont.) to P.M. Input Fell 1, 6&8, 10, HVAC Systems, Waste Draft SER 3/31/88 3/31/88 3 Awaiting 12, 13 Management, Steam & to P.M. Input Power Conversion Raval 13 Plant Systems Draft SER 3/31/88 3/31/88 3 Awaiting to P.M. Input DEST /SRXB Liang 1, 4, 5, 6&8, Reactor Systems RAIs to 7/31/87 1/29/88 1 -

9, 10, ll, 12 P.M.

DRIS/RSGB Mendelsohn 2 Physical Security Draft SER 3/31/88 3/31/88 3 Awaiting to P.M. Input DLPQ/LQAB Spraul 13 Quality Assurance Draft SER 3/31/88 3/31/88 3 Awaiting to P.M. Input O See September 29, 1987 nemo for complete listing of review assignments 00 Category definitions:

1. AD or above attention requested
2. Branch Chief attention requested
3. On schedule
4. Complete -

Date: January 22, 1988 REVIEW STATUS REPORT ON WESTINGHOUSE RESAR SP/9D PDA REVIEW (Cont.)

Expected Division / Due Input Branch Reviewer Modules Subject

  • Milestone Date Date Cat.** Comments DLPQ/LHFB Lapinski 15 Control Room / Human Draft SER 3/31/88 3/31/88 3 -

Factors Engineering to P.M.

DREP/PRAB Spickler 1,3,4,5, Radiological Accident Draft SER 3/31/88 3/31/88 3 -

6&8, 9, 10 Analysis to P.M.

Willis 12 Process & Effluent RAIs to 7/31/87 TBD 2 Reviewer Radiological to P.M. assigned Monitoring & Supply System 1/88 RES/PRA Chelliah/BNL 16 Probabilistic Safety Final 11/30/87 1/29/88 2 Under review Study TER to RES o See September 29, 1987 memo for complete listing of review assignments 00 Category definitions:

1. AD or above attention requested
2. Branch Chief attention requested
3. On schedule
4. Complete

/ ..

e Date: December 10, 1987 REVIEW STATUS REPORT ON GE ABWR FDA/DC REVIEW Expected Division / SRP Due Input Branch Reviewer Chapter Subject Milestone Date Date Cat.* Comments DEST /EMEB Li 5 Mechanical Engineering RAIs to 12/31/87 12/31/87 4 P.M.

DEST /EMTB Tsao 4,5,6 Materials Engineering RAIs to 12/31/87 12/31/87 4 P.M.

DEST /ECEB Witt 5, 6 Chemical Engineering RAIs to 12/31/87 12/31/87 4 P.M.

DEST /SPLB Chandrasekaran 5, 6, 15 Plant Systems RAIs to 12/31/87 TBD 1 Date missed -

P.M. SPLB estimate of completion

- 4/15/88 DEST /SRXB Thomas 4, 5, 5, 15 Reactor Systems RAIs to 12/31/87 TBD 1 Date missed -

P.M. SRXB estimate of completion

- 5/30/88 DLPQ/PRAB Pedersen 15 Radiological Consequences RAIs to 12/31/87 12/31/87 4 P.M.

O Category definitions:

1. AD or above attention requested
2. Branch Chief attention requested -
3. On schedule
4. Complete ,

I Date: January 22, 1988 l

REVIEW STATUS REPORT ON CE SYSTEM 80+

CESSAR-DC REVIEW Expected Division / Due Input Branch Reviewer Chapter Subject Milestone Date Date Cat.* Comments DEST /EMEB Horace Shaw Chapter 1 Introduction and Gen. RAIs to 12/15/87 02/02/88 3 Under review Description P.M.

DEST /ETFB Martin Hum Chapter 1 Introduction and Gen. RAIs to 12/15/87 12/15/87 2 Under review Description P.M.

DEST /ECEB Frank Witt Chapter 1 Introduction and Gen RAIs to 12/15/87 12/15/87 4 Under review Description P.M.

DEST /EGSB Norman Romney Chapter 1 Introduction and Gen. RAIs to 12/15/87 12/15/87 2 Under review Description P.M.

DEST /SIGB James Stewart Chapter 1 Introduction and Gen. RAIs to 12/15/87 12/15/87 2 Under review Description P.M.

DEST /SELB 0. Chopra Chapter 1 Introduction and Gen. RAIs to 12/15/87 12/15/87 2 Under review Description P.M.

DEST /EMEB J. Rajan Chapter 1 Introduction and Gen. RAIs to 12/15/87 02/02/88 3 Under review Description P.M.

O Category definition:

1. AD or above attention requested
2. Branch Chief attention requested 4
3. On schedule 4o Complete .

e Date: January 22, 1988 REVIEW STATUS REPORT ON CE SYSTEM 80+

CESSAR-DC Review (Cont.)

Expected Division / Due Input Branch Reviewer Chapter Subject Milestone Date Date Cat.* Comments DEST /SPLB J. Raval Chapter 1 Introduction and Gen. RAIs to 12/15/87 12/15/87 2 Under review Description P.M.

DEST /SRXB L. Kopp Chapter 1 Introduction and Gen. RAIs to 12/15/87 12/15/87 4 Under review Description P.M.

DREP/PEPB R. Van Niel Chapter 1 Introduction and Gen. RAIs to 12/15/87 12/15/87 2 Under review Description P.M.

DREP/PRAB G. Kelly Chapter 1 Introduction and Gen. RAIs to 12/15/87 12/15/87 4 Under review Description P.M.

DREP/PRPB Tom Essig Chapter 1 Introduction and Gen. RAIs to 12/15/87 12/15/87 4 Under review Description P.M.

DRIS/RSGB B. Mendelsohn Chapter 1 Introduction and Gen RAIs to 12/15/87 12/15/87 4 Under review Description P.M.

DOAE/0TSB B. Giardina Chapter 1 Introduction and Gen. RAIs to 12/15/87 12/15/87 2 Under review Description P.M.

DLPQ/LHFB G. Lapinski Chapter 1 Introduction and Gen. RAIs to 12/15/87 12/15/87 2 Under review Description P.M.

DRAA/PRAB E. Chelliah Chapter 1 Introduction and Gen RAIs to 12/15/87 12/15/87 2 Under review Description P.M.

O Category definition:

1. AD or above attention requested .
2. Branch Chief attention requested
3. On schedule
4. Complete

e Date: January 22, 1988 REVIEW STATUS REPORT ON SYSTEM 80 CESSAR-F REVIEW i Expected Division / Due Input Branch Reviewer Chapter Subject Milestone Date Date Cat.* Coments DEST /SRXB C. Liang TAC 66400, ASPSS ISSUE Final SER 2/28/88 2/28/88** 3 -

to P.M.

DEST /EMEB J. Rajan TAC 66401, Steam Gen. Tube Vibration RAIs to open open 3 Awaiting input P.M. frcm applicant DEST /EMTB W Wickman TAC 66401, Steam Gen. Tube Vibration RAIs to open open 3 Awaiting input P.M. from applicant DEST /SIGB R. Kendall System 80 ATWS RAIs to 1/15/88 1/15/88 A Under review P.M.

  • Category definition:
1. AD or above attention requested
2. Branch Chief attention requested
3. On schedule
4. Complete
    • Close cut issue

e Date: January 22, 1988 REVIEW STATUS REPORT ON EPRI'S ALWR REQUIREMENTS DOCUMENT Expected Division / Due Input Branch Reviewer Chapter Subject

P.M.

3 Reactor Coolant Systems DSER to 03/1/88** 03/1/88 3 P.M.

4 Reactor Systems RAI to 09/1/87 12/3/87 4 P.M.

4 Reactor Systems DSER to 03/1/88** 03/1/S8 3 P.M.

5 Eng. Safety Systems RAI to 02/22/88 02/22/88 3 P.M.

DEST /EMTB Tsao 2 Power Generation Systems DSER to 11/1/87 12/4/87 4 P.M.

3 Reactor Coolant Systems RAI to 09/1/87 12/4/87 4 P.M.

3 Reactor Coolant Systems DSER to 03/1/88** 03/1/88 3 P.M.

4 Reactor Systems RAI to 09/0/87 12/4/87 4 P.M.

4 Reactor Systems DSER to 03/1/88** 03/1/88 3 P.M.

5 Eng. Safety Systems RAI to 02/22/88 02/22/88 3 P.M.

O Category Definition:

1. AD or above attention requested
2. BC attention requested
3. On schedule
4. Complete
    • Due date extended from 2/1/88 to 3/1/88 because of delays in RAIs -

e Date: January 22, 1988 REVIEW STATUS REPORT ON EPRI'5 ALWR REQUIREMENTS DOCUMENT (Cont.)

Division / Expected Branch Reviewer Chapter Due Input Subject

  • Milestone Data Date Ca t .
  • Comments Stewart 4

DEST /SICB 3 Reactor Coolant Systems DSER to 03/1/88** 03/1/88 3 P.M.

4 Reactor Systems DSER to 03/1/88** 03/1/88 3 P.M.

S Eng. Safety Systems RAI to 02/22/88 02/22/88 3 P.M.

DEST /SELB Lazevnick 3 Reactor Coolant Systems DSER to 03/1/88** 03/1/88 3 P.M.

4 Reactor Systems DSER to 03/1/88** 03/1/88 P.M.

S Eng. Safety Systems RAI to 02/22/P"- 02/22/88 3 P.M.

DEST /SPLB Ridgely 2 Power Generation Systems DSER to 11/1/87 12/8/87 4 P.M.

Ridgely 3 Reactor Coolant Systems RAI to 09/1/87 10/16/87 4 P.M.

Shum 3 Reactor Coolant Systems DSER to 03/1/88** 03/1/88 3 New Reviewer P.M.

O Categcry Definition:

1. AD or above attention requested
2. BC attention requested
3. On schedule
4. Complete -

00 Due date extended from 2/1/88 to 3/1/88 because of delays in RAIs

e Date: January 22, 1988 REVIEW STATUS REPORT ON EP2I'S ALWR REQUIREMENTS DOCPMENT (Cont.)

Expected Div*sion/ Due Input Branch Reviewer Chapter Subject

  • __ Milestone Date Date Cat.* Comments DEF'/SPLB Ridgely 4 Reactor Systems RAI to 09/1/87 10/16/87 4 (cont.) P.M.

Shum 4 Reactor Systems DSER to 03/8/88** 03/1/88 3 New Reviewer P.M.

Shum 5 Eng. Safety Systems RAI to 02/22/83 02/22/88 3 P.M.

DEST /SRXB Schwenk 3 Reactor Coolant' Systems RAI to 09/1/87 10/7/87 4 Oral comr.ents &L P.M. respoases 3 Reactor Coolant Systems DSER to 03/1/88** 02/15/88 3 P.M.

4 Reactor Systems RAI to 09/1/87 10/7/87 4 Oral comments 8.

P.M. responses 4 Reactor Systems DSER to 03/1/80** 02/15/88 3 P.M.

5 Eng. Safety Syste.ns RAI to 02/22/88 02/22/88 3 P.M.

t OREP/RPB Branagan 5 Eng. Safety Systems RAI to 02/22/88 02/22/88 3 P.M.

4

  • Category Definit an:
1. AD or above attention requested
2. BC attention requested
3. On schedule
4. Complete .
    • Due date extended from 2/1/88 to 3/1/88 because of delays in RAIs

January 19, 1988 2-was agreed to by PDSNP and the review branch. Category 1 items have been discussed with the appr0priate Assistar;t Directors. I request any problems in meeting these input dates ~be identified to me by the appropriate Assistant Director within a week of receipt of this memo, original signed by Lester S. Rubenstein, Director Standardization and Non-Power Reactor Project Directorate Division of Reactor Projects III, IV, V and Speciel Projects, NRR

Enclosure:

As stated cc: T. Murley J. Sniezek F. Miraglia J. Richardson C. Y. Cheng L. B. Marsh C. McCracken A. Thadani J. Joyce J. flauk F. Rosa J. Craig M. W. Hodges S. Grimes R. Erickson D. Matthews R. Barrett L. Cunningham H. Miller A. Beach W. Regan, Jr. {

J. Murphy G. Bagchi DISTRIBUTION:

5DocketJ11ea EHylton ADR4 NRC PDR Pleech FD.5flP Reading DScaletti GVissing DCrutchfield LRubenstein TXeny n, PDS

~~

PDS $/!

LRubent.tei,n ERf1)on:cw '

Ol/p/88 01/ ff/38 *