ML20148A307
| ML20148A307 | |
| Person / Time | |
|---|---|
| Site: | Perry |
| Issue date: | 12/15/1978 |
| From: | James Keppler NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III) |
| To: | Davidson D CLEVELAND ELECTRIC ILLUMINATING CO. |
| Shared Package | |
| ML20148A310 | List: |
| References | |
| NUDOCS 7812280307 | |
| Download: ML20148A307 (2) | |
See also: IR 05000440/1978014
Text
T
a
- "*%,1
UNITED STATES
NUCLEAR REGULATORY COMMISSION
'
.v . -
EI M,y
( $ y(g ) e
R E GION ill
g
7ti9' noose VE LT RoAo
g
v
oLEN E LLv N. iLLiwois sois7
j
a...*
EE C 1.
178
Docket No. 50-440
Docket No. 50-441
The Cleveland Electric Illuminating
Company
ATTN:
Mr. D. R. Davidson
Vice President - Engineering
Post Office Box 5000
Cleveland, OH 44101
Gentlemen:
This refers to the inspection conducted by Messrs. J. E. Ronklin,
J. H. Neisler, and P. C. Hawkins of this office on October 25-27,
1978, of activities at the Perry Nuclear Plant Project, Units 1
and 2, authorized by NRC Construction Permits No. CPPR-148 and
No. CPPR-149 and to the discussion of our findinge with Messrs.
M. R.
Edelman and G. W. Groscup and others of your staff at the
conclusion of the inspection.
The enclosed copy of our inspection report identifies areas
examined during the inspection. Within these areas, the
inspection consisted of a selective examination of procedures
and representative records, observations, and interviews with
personnel.
During this inspection, certain of your activities appeared
to be in noncompliance with NRC requirements, as described
in the enclosed Appendix A.
Item No. 2 shown in the Notice
of Violation enclosed with this letter is a recurrent item.
In your response please give this matter particular attention.
This notice is sent to you pursuant to the provisions of Section
2.201 of the NRC's " Rules of Practice," Part 2, Title 10, Code
of Federal Regulations.
Section 2.201 requires you to submit to
this office within thirty days of your receipt of this notice a
written statement or explanation in reply, including for each
item of noncompliance: (1) corrective action taken and the results
achieved; (2) corrective action to be taken to avoid f urther non-
compliance; and (3) the date when full compliance will be achieved.
781228 COO 7
s i.
o
h.h
bEC1-
TI
The Cleveland Electric
-2-
Illuminating Company
In accordance with Section 2.790 of the NRC's " Rules of Practice,"
Part 2, Title 10, Code of Federal Regulations, a. copy of this
letter, the enclosures, and your response to this letter will be
placed in the NRC's Public Document Room, except as follows.
If
the enclosures contain information that you or your contractors
believe to be proprietary, you must apply in writing to this office,
within twenty days of your receipt of this letter, to withhold such
information from public disclosure.
The application must include a
full statement of the reasons for which the information is considered
proprietary, and should be prepared so that proprietary information
identified in the application is contained in an enclosure to the
application.
'
We will gladly discuss any questions you have concerning this
inspection.
Sincerely,
~ .$9
ames G. Ke
r
Director
Enclosures:
1.
Appendix A, Notice
of Violation
2.
IE Inspection Reports
No. 50-440/78-14
and No. 50-441/78-13
cc w/encls:
Central Files
Reproduction Unit NRC 20b
Local PDR
U. Young Park, Power
Siting Commission
Mr. Daniel D. Wilt,
Attorney
1
1
1
-
--.
-
.
.
.
, _ . .
. . .