ML20147E693

From kanterella
Jump to navigation Jump to search
IE Inspec Repts 50-460/78-07 & 50-513/78-07 on 781010-13 During Which 03 Items of Noncompliance Were Noted:Equip Maint & Storage,Safety Related Steel Structures & Safety Related Structures Welding
ML20147E693
Person / Time
Site: Washington Public Power Supply System
Issue date: 11/08/1978
From: Albert W, Haynes R, Kirch D
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION V)
To:
Shared Package
ML20147E638 List:
References
50-460-78-07, 50-460-78-7, 50-513-78-07, 50-513-78-7, NUDOCS 7812210153
Download: ML20147E693 (12)


See also: IR 05000460/1978007

Text

r

,

,,

.

.

V. S. NUCLEAR REGULATORY COMMISSION

-.

OFFICE OF INSPECTION AND ENFORCEMErlT

s

REGION V

50-460/73-07-

Repo'rt No. 50-513/78-07

Docket flo. 50-460 & 50-513 License No. CPPR 134 & 174;afeguards Group

Licensee: Washington Public Power Supply Systems

P. O. Box 968

Richland, Washington 99352

Facility Name:

WNP 1 and 4

Inspection at:

WNP 1 and 4 Site, Richland Washington

Octo,eg,J0-13f 1978

b

InspectionConducjtd:

Inspector

[/

// 7/ /[

E

G~. Albebti'Keac~ tor Irispector

/ Dat Signed

Aftado

ir/p/

~F. I rs

R

rI

p ctor

' / Dpfe Sign d

h

  • ~7

//

7

7$

J."H.'Eckhar E Re

r

'n

ect

D

/ ate igne

Y7

WVitu(son, Reactor Inspec[or '

D6te Signed

kl 0;%n _

// /v/ 76

Ap;

j.

R. C. Haynes;/ Chief, Projects Section,

frate Signed

Reactor Genftruction and Engineeri ig Support Branch

Inspection on October 10-13,1978 (Report Nos. 50-460/78-07 and

50-513/78-07)

Areas Inspected:

Routine, announced inspection by regional based in-

spectors of construction activities including: open items from previous

inspections, equipment maintenance and storage, safety-related steel

structures, safety-related structures welding, containment liner and

welding, structural concrete, drawing control, contractor audits, and

i

contractor QA programs. The inspection it.volved 107 inspector hours

,

onsite by four NRC inspectors.

)

1

Resul t_s :

Of the nine areas inspected, no items of noncompliance or

_

deviations were identified in six areas.

One item of noncompliance was -

identified in each area of equipment maintenance and storage, safety-

related steel structures and safety-related structures welding.

7E122io\\f3

et

. . - .

-

.

, ,

.

.

.

.

DETAILS

.

1.

Persons Contacted

.

Washington Public Power Supply System (WPPSS)

  • M. W. Hultgren, Division Manager, WNP-1/4
  • J. P. Thomas, Project Manager, WNP-1/4
  • T. J. Houchins, QA Manager,.WNP-1/4

_

  • M. C. Carrigan, Construction Manager, WNP-1/4
  • G. K. Dyekman, Project Engineering Manager
  • C. R. Edwards, Principal QA Engineer
  • J. W. Shannon, Acting Assistant Director - Technology

J. R. Nichdaus, QA Engineer

  • W. M. Lazear, QA Engineer
  • R. D.' Crisp, QA Engineer

J. Carson, QA Engineer

R. C. Mertens, QA Engineer

P. Magbod, QA Engineer

R. O. Romine, Supervisor of Engineering Administration

A. Bright, Administrative Engineer

,A. G.-Hosler, Project Licensing Engineer

State of Washington

  • G. Hansen, Manager QA Division, Washington State Energy Facility

Site Evaluation Council

  • Denotes those attending exit inter'13w.

United Engineers and Constructors (UE&C)

R. L. Peters, Mechanical Superintendent

R. H. Bryans, Field Project Engineer

R. Goldstein, Field Engineer

i

C. J.,Rammel, Preventive Maintenance Coordinator

'

B. Lentz, QA Engineer

D. House, Drawing Control Clerk.

U. E. Cickocki, Manager, Construction QA and Interface

P. Bily, Lead Contractor Drawing Auditor

R. N. Devers, Documentation Supervisor

W. J. Norton, QA Engineer

Shurtleff and Andrews

D. Fitzgerald, QA Manager

J. D. Jackman, QC Inspector

_

-

K. B. Engstrom, QC Inspector

M. Freize, Foreman

,

d-

-2

.

..

.

.

.

i

1.

Persons Contacted (Continued)

.

Boecon Construction Co. (Boecon)

M. Rothwell, Document Control Clerk

L. Keane, QA Engineer

L. McGrath, QC Engineer

G. F. Atkinson/ Wright /Schuckert/ Harbor (AWSH)

W. G. Anberg, Engineering Drawing Supervisor

P. Burns Document Control Supervisor

M. D. Latch, QA Manager

J. A. Jones (Jones)

W. S. Roe, QA Manager

P. Schonecke, QA Engineer

Capital Development Corporation (CDC)

W. Young, Boilermaker Foreman

D. Willis, Boilermaker

BabcockandWilcox(B&W)

L. Rafferty, Field Representative

Pittsburg Des-Moines (PDM)

D. Wilson, QA Documentation Supervisor

C. L. Baner, Siting QA Manager

Pacific Testing Laboratory (PTL)

M. Paige, Level I Inspector

2.

Project Status

At the time of this inspection, construction on Unit 1 was 16%

complete and construction of Unit 4 was 7% complete.

Operating license application is currently scheduled for December,

1979 and fuel loading for June,1982.

3.

Licensee Action on Previously Identified Open Items

a.

Closed (50-460/77-03):

Engineering review of contractor

generated nonconformance reports.

Since Revison 5 to QAP-15

has been issued, all individual contracts have been revised by

PCR 5628 requiring all contractors to implement QAP-15.

.

.

.

'

-3

Oyen - Unresolved item (50-460/78-06): Missing preventive

b.

e

.

,

mcintenance checks for various valves and safety-related

vessels.

Discussions with the licensee disclosed that a

search of the records indicated that PM records for June and

July for the two steam generators and pressurizer were re-

covered but the records for valves 1-DH-V7A,1-DHR-FCV-3A and

1-DHR-FCV-3B could not be found.

Nonconformance reports

1 NCR-CM-21 and 22 document the above items.

This, together

with further findings on the subject noted in Paragraph 6

below, indicate that the unresolved item represents a defi-

ciency for failure to proper'" complete documentation as

required.

4.

IE bulletins and Circulars /PSAP Changes

The handling of I&E bulletins and circulars was examined against

WPPSS QAP-27.

It was found that QAP-27 was now being used by the

Engineering Administrative section although the procedure was

originally written for implementation by the QA department.

Engineering Administration had assumed the function of bulletin and

circular control in August 1978. A revised procedure is scheduled

for issue by October 31, 1978.

Except for defined responsibilities

and authority, the procedure was being followed.

However, it did

appear that in many cases, greater emphasis was being placed on

tracking responses to bulletins than on tracking circulars.

The

inspector emphasized that the NRC does not necessarily place

greater importance on bulletins than on circulars, but rather

classifies items as bulletins when it is desirable to obtain

replies for an evaluation of the generic aspects of a problem.

The

bulletins on environmental qualification of electrical equipment,

which eventually gave rise to a general circular on the subject

were cited as an example.

This item will be examined further

during a future inspection.

The control of deviations from the PSAR was examined for conform-

ance to the licensee's procedure EDP-8.4.

No deviations or items

of concern were noted.

5.

Document Control

The licensee's document control system, including the implemen .

tation by UE&C, Boecon, and AWSH was examined for compliance with

PSAR commitments, licensee and contractor procedures, and licensee

response to NRC enforcement action.

The licensee was in the process of effecting document control

system modifications required to implement their response to NRC

enforcement action.

The area of document control is considered

open and will be further examined during a future inspection.

.

'

4

9

a.

Review of Quality Assurance Implementing Procedures

'

The following procedures were examined:

(1) AWSH:

QCCP-8, " Document Control"

(2) WPPSS: QAP-6, " Document Control"

(3) UE&C:

FGCP-38, " Document Control of Contractor /

Vendor Information"

(4) UE&C:

FGCP-39, " Design Document Control"

b.

Observation of Drawing Control Activities

The inspector examined the revision status of 282 field-

located design and contractor drawings.

It was noted that

three AWSH drawings (CWZ112416, CWZ119709A and CWZ1197098 at

location 22C) were not the most recent approved revisions.

Action was taken 'to remove and replace the drawings identified.

c.

Audits and Surveillances

Quality assurance personnel had performed numerous surveil-

lances in the area of drawing control, as committed by the

licensee's response to NRC enforcement action.

The drawing

control surveillance reports for the months of August and

September,1978, were sampled and reviewed.

The surveillances

appeared to be adequate with regard to scope, depth, and

finding resolution.

Licensee representatives noted that

internal procedures were being revised to establish schedules

and minimum frequencies for performance of QA surveillance

over document control activities.

UE&C had established a drawing control audit group which

audits field-located drawings on a daily basis.

The inspector

sampled and examined nine of the drawing control audit reports

for the period September 28, 1978 through October 5,1978.

Eight discrepancies had been identified during a review of

2627 field-located drawings.

Corrective actions taken appeared

adequate.

d.

Automated Drawing Index

An Automated Drawing Index (ADI) has been developed by UESC.

This index is to include all design drawings and contractor

issued drawings.

The ADI was utilized by the inspector to

determine the most recent revision of field-locatea drawings.

The validity of the ADI was examined by comparing the ADI

listed revision of certain sampled drawings against those in

,

-5-

..

.

the master drawing files of UE&C, Boecon and AWSH.

It was

.found that the ADI did not include all UE&C design drawings,

.

since seven design drawings marked as issued to Boecon for

construction were not listed on the ADI.

Also, eighteen

design drawings issued to AWSH were not listed on the ADI and

in one case, the ADI listed the wrong revision. The licensee

indicated that the ADI was still in the process of development

and was being updated on a daily basis so that all design and

contractor drawings applicable to individual contractor

organizations would eventrally be included.

e.

Document Revision Transmittal and Control

The UESC procedures require that contractors acknowledge

receipt and incorporation of transmittals revising contract

documents.

UE&C had identified about 54 transmittals to

Boecon and AWSH for which no completed contractor acknowl-

edgements were on file and had taken action to assure prompt

acknowledgement and return.

The inspector sampled various

specification revisions and noted that the contractors had

apparently received all revisions.

The inspector examined

Specification No. 9779-206 at the Boecon Field Engineering

office and observed that revisions had been filed in a binder

separate from the binder containing the specification and that

numerous revisions had not been entered into the specification

body.

In addition, Specification No. 9779-253 was examined at

the AWSH document control office.

It was noted that Page 14V

was that of Revision 17 and not the effective Revision 25 for

Page 14V.

Licensee representatives noted that the drawing

control audit group only audits drawings and that the advis-

ability of including other documents in the audit scope would

be evaluated. . Action was taken to correct the discrepancies

identified.

It was identified that the UE&C document control center listed

Revision 25 as the latest revision to Specification 9779-253.

Examination of the specification at AWSH showed Revision 26

had been received and entered.

Licensee representatives ex-

plained that Revision 26 which listed changed drawings, had

been issued by the drawing control office and Revision 25 had

been issued by the document control organization. The licensee

stated that measures would be implemented to assure that all

specification revisions would be brought to the attention of

the document control center.

6.

Equipment Maintenance and Storage

a.

Examination of Stored Equipment

Storage conditions for the reactor pressure vessel, the two

steam generators and the emergency generator were examined.

i

_

.

.

.

..

.

-6-

.

.

.

In accordance with UE&C procedure FGCP-16-2 and B&W.Specifi-

cation FS III-la-23, the. interval between successive' inspections

of.the reactor vessel was not to exceed 30 days.

However, the

inspector found that the last surveillance was recorded 139

days previously.

In addition, it was found that an inspector

(recently assigned) was unaware of the. requirement for in-

spection of the secondary side of the steam generator although

he had performed major component inspections.

Also,~it was

found'that the rotor for the diesel generator was not maintained

with the'same heat controls as those for the stator even

though the manufacturer did not distinguish between the two

components.

The inspector found that site B&W personnel were cognizant of

vessel and steam generator conditions.. The rotor and stator

of the diesel generator were not stored assembled as the

manufacturer 'apparently intended; thus the stator heaters did

not take care of both components.

However, ambient temperature

was well above dewpoint which was all the manufacture required.

The absence of adequate and prompt documentation of inspections,

together with the unresolved item noted from the previous

inspection in this area (see Paragraph 3.b above), appears to

constitute an ite[n of noncompliance,

b.

Storage and Maintenance Requirements

The inspector examined provisions for obtaining storage and

maintenance requirements.

While many manufacturer's manuals

were available at the site, the basic method of providing the

site with requirements was the completion of a form by the

design office of UE&C.

The form is entitled " Equipment /

Material Storage and Preventative Maintenance Requirements."

One section of the form was entitled "Special Storage and

Preventative Maintenance Instructions."

It was found from an

examination of over 200 such forms that only a small percentage

(less than 10%) had this section completed.

The instruction

controlling the preparation and use of this form, which was

labeled " Attachment 1", -could not be made available to the-

NRC inspector at the time of this site visit.

Compliance with the requirements of 10 CFR 50, Appendix 13,

Criterion V and XIII could not be readily determined and the

item is considered to be an unresolved item.

-

.

-7-

-

7.

Structural' Steel Installation

'

'

a.

Review of Quality Records

The inspector reviewed the following quality records associated

with the beams listed below in the Unit 1 and Unit 4 General

Services Building (GSB).

Unit 1, Area A, El 438

Unit 4, Area B El 454

Beam Mark

Beam Mark

5-1170E

7-18048

5-1166A

7-1800H

5-1192D

7-1807A-

5-11678

7-1810G

5-1165H

7-1814A

5-1184A

7-2680E

5-11648

7-24578

The records reviewed included, certified Material Test Reports,

Certificates of Conformance, Receiving Inspection Reports,

Bolting Inspection Reports 28-42 for Unit 1 and 23-34 and 48

for Unit 4, and selected Nonconformance Reports including

open, dispositioned or closed NCR's. All records reviewed

accurately reflected the ' status of the work except that the

Certified Material Test Report for beam 7-1810G could not be

reviewed as the mill item number for the beam could not be

found in the cross reference catalog.

The CMTR for beam 7-

1810G will be reviewed during a future inspection.- No items

of noncompliance or deviations were noted.

8.

Structural Steel Welding

a.

Obser'vation of Work

The inspector observed the welding of " Nelson" studs to floor

beams through "Q" decking in the Unit 1 GSB at elevation 441

feet between lines A and B and lines 6 and 9.

Contrary to the

i

requirements of Shurtieff and Andrews Quality Assurance Pro-

'

cedure 2E, Revision 2 " Stud Welding and Inspection," the

inspector noted the following items:

(1) studs with surface

rust were being welded, (2) the first two' studs on each member

were not in all cases t,,'ng bent 30 degrees and (3) the first

two studs ~ welded on each Jember per set of equipment were not

being bent when two operators were welding on one member with-

L

different guns and controllers.

The inspection of Nelson

studs.by the assigned QC inspector was also observed.

The QC

inspector was using the proper criteria'as contained in QAP-2E

and was familiar with the visual inspection criteria of AWS

D1.1-1972 as implemented by QAP-2E.

The failure to follow

the stud welding procedure appears to be an item of noncompliance,

,

I

l

ll

,

'

.

.

-8-

.

..

One welder'was observed welding beam clips to embed plates in

the Unit 4 GSB at elevation 420 feet on line 1, 2. feet west of

.line T.

One beam clip weld was in process and the other had

been fitted.up but not tacked.

The welder was observed using

'

the proper procedure and filler metal. A check of the records

-indicated that he was qualified for the' process and position

being used in accordance with AWS Dl.1-1972.

Fit up conformed

to the requirement of AWS Dl.1-1972.

Two additional welders

were observed putting 5/16 inch ' fillets around studs requiring

repair with E7018 electrodes. All requirements of QAP-2E were

being met. ~No items of noncompliance or deviations were

noted.

b' .

Review of Quality Records

The inspector reviewed selected quality records associated

with structural steel welding. The qualification records of

six QC inspectors were reviewed for compliance with Shurtleff

and= Andrews QAP-13 " Qualifications of' Quality Assurance

,

Personnel . " One QC Inspector's Certification stated that the

inspector was certified as a Level II' inspector.

This certifi-

cation statement allows the particular inspector to perform

activities such as structural steel placement and inspection,

inspection of bolted and welded joints 'and inspection of

repairs.

The inspector's resume documented approximately 14

months experience and only one training session on stud welding

inspection.

QAP-13 requires that such inspectors be a high

school graduate and have four years experience or other docu-

mentation showing demonstrated capability or completion of

proficiency testing. These records could not be found in the

inspector's certification file.

The QA Manager was designated as a Level III inspector and his

resume listed his education as an MS degree in Electrical

Engineering from John Quincy Adams College.

No high school or

undergraduate education was listed.

Following the site in-

l

spection, the Eleventh Edition of American Universities and

l

Colleges and the Ninth Edition of the Yearbook of Higher

Education were reviewed which disclosed that John Quincy Adams

College was not contained in the listings of accredited colleges

and universities.

This finding is contrary to the requirements

of QAP-13, " Qualification of Quality Assurance Personnel"

which requires that the Level III inspector be a graduate of

an accredited college or a high-school graduate with ten years

experience.-

All stud welders were listed on the qualified stud welder

roster and the three welders observed doing SMAW welding were

qualified for the process and position being used.

The failure of QA/QC personnel to meet QAP-13 qualification

requirements appears to be an item of noncompliance.

t

j

.

.

-9-

.

'

9.

Containment Structural Steel Installation and Welding (Unit 4)

a.

Observation of Work and Work Activities

,

i

The NRC inspector examined the Unit 4 containment liner plate

installation and welding to ascertain compliance with the

ASME Boiler and Pressure Vessel Code (B&PV Codc)Section III,

Division 2.

The following installed panels and weld seams

were examined:

(1) Panels

28E44 (ring 7)

213El

(ring 10)

214E1

(ring 10)

28E74 (ring 10)

(2) Weld Seams

7V-15, 6H-12, 6H-13, 7V-16, 6H-14, 7V-17, 6H-15,

10V-16, 9H-16, 9H-15,10V-17, 9H-17,10V-2, 9H-2,

10V-3, 9H-2

In addition, installation of ring #13 liner panels (including

fit up and tack welding) and vacuum box testing of vertical

and horizontal welds on ring #11 were observed.

No deviations

or items of noncompliance were noted.

b.

Review of Quality Records

The following quality records of containment liner plate

installation and welding were reviewed to ascertain compliance

with ASME B&PV Code,Section III, Division 2:

(1) Material certification for the panels listed in Paragraph

9.a(1),above.

(2) Fabrication checklist (weld records) for the welds listed

in Paragraph 9.a(2), above.

(3) Welder operator qualification records for the processes

used on the welds listed in Paragraph 9.a(2), above.

(4) Radiographs for welds 9H-16, 9H-15, 9H-107, and 10V-2.

(5) Local panel tolerance deviation report for ring 1.

No deviations or items of noncompliance were noted.

.

_10

-

.

.

10.

Structural. concrete

-

a.

General Service Building (Units 1 and 4)

The NRC inspectors observed and examined concrete placement

1290 in the Unit 1 General Service Building (GSB) and place-

ment G-201 in the Unit 4 GSB for compliance with the require-

ments of ACI-318-71. Also, batch tickets and records of tests

performed at the placements were reviewed.

No deviations or

items of noncompliance were noted.

b.

Containment (Unit 1)

Curing records of lift 1-C103 (placed on October 5,1978) and

the preplacement inspection records for lift 1-C104 were

reviewed to ascertain compliance with ASME B&PV Code, Division

III, Section 2 and ACI-318-71.

No deviations or items of

noncompliance were noted.

The reactor primary shield wall reinforcing steel and forms

were examined, and the importance and difficulty of adequate

concrete consolidation for this lift was discussed with the

licensee.

Problems with such placements at other facilities

were noted.

11.

Contractor Audits

The audit program and the completed audits covering QAP-2A,B,D&E,

QAP-3, and QAP-9A were reviewed. The audit checklists are being

revised as required to perform an upcoming audit.

The audits show

that the audit checklists are being used and the depth and scope of

the audits appear commensurate with the status of the work. All

findings were assigned to a responsible person for completion and

reaudits of the deficient areas show that corrective action had

been taken.

No items of noncompliance or deviations were noted.

12.

C'ontractor QA Programs

An initial review of the QA program for the J. A. Jones Company was

made. Jones will have the principal piping contracts for the

installation of primary system components and other class I piping,

and will perform its own NDE.

Program elements meeting 10 CFR 50,

Appendix B, Criterion I, II, III and XVIII were examined, licensee

approval of the program was verified, and an initial tour of the

uncompleted small bore pipe shop and records storage facilities was

made.

No deviations or items of noncompliance were identified.

1

- -

- - - -

. - -

- ._.

'~

-11-

.

.

,

.

'13.

Unresolved Items

,

Unresolved items are matters about which more information is re-

[

quired in order to ascertain whether they are acceptable items,

items of noncompliance, or deviations.

Unresolved items discicted

during the inspection are discussed in Paragraph 6.b.

14.

Exit Interview

,

At the conclusion of the site inspection, the inspector met with

those individuals designated in Paragraph 1.

In reviewing the

resul'i of the structural steel welding inspection, the inspector

emphasized that the' reject rate from welding of Nelson studs

through "Q" decking was such that the process, as presently practiced

at WNP 1 and 4, was unacceptable.

Licensee personnel noted that

the process was a conventional " state of the art" process and that

a 10-15% reject could be tolerated. The inspector disagreed and

stated that he intended to solicit an NRC position regarding the

practice.

With regard to the inspectors' concerns about preventive maintenance-

systems, the licensee stated that they shared these same concerns

and had initiated certain corrective-actions following the previous

NRC inspection.

However, full resolution and implementation would

take some time.

'

.

I

-