7 Tclephone (017) 872-810')
TWY 710 380-7619 YANKEE ATOMIC ELECTRIC COMPANY h
1671 Worcester Road, Framingham, Massachusetts 01701 1
February 18, 1988 FYR 88-24 United States Nuclear Regulatory Commission i
Document Control Desk Washington, DC 20555 Attention:
Morton B. Fairtile, Project Manager Project Directorate I-3 Division of Reactor Projects I-II
References:
(a) License No. DPR-3 (Docket No. 50-29)
(b) Letter, USNRC to YAEC, dated January 20, 1988
Subject:
Response to USNRC Generic Letter 88-02
Dear Sir:
In Euference (b), the USNRC requested that Yankee indicate its interest in participating in the ISAP II Program. Attached is our response to the questions contained in Generic Letter 83-02.
We trust that you will find this information satisfactory; however, if you have any questions please contact us.
Very truly yours, YANKEE ATOMIC ELECTRIC COMPANY Georg
- apanic, r.
Senior Project Engineer Licensing GP/25.423 Attachment cc: USNRC Region I USNRC Resident Inspector YNPS OY 8803010402 880218 DR ADOCK 05000029 p
6 PDR
e ATTACHMENT Response to Generic Letter 88-02 Facility - Yankee Nuclear Power Station Rowe,-Massachusetts Utility - Yankee Atomic Electric Company Framingham, Massachusetts Individual-Contact -- George Papanic, Jr.
Senior Project Engineer - Licensing 617-872-8100, Extension 2214 Question 1 -
Would you be interested in participating in ISAP II? If so, in what time frame?
Yankee Response - Yankee is not interested in participating in the ISAP II Program, at this time. However, we will closely monitor -
the experiences of utilities participating in the program and will reassess'our position after we gain a practical demonstration of how the program will be implemented.
Question 2 -
Do you believe that an industry /NRC seminar consisting of a brief discussion by NRC followed by a question and answer period would be beneficial prior to making a decision?
l Yankee Response - Yankee would be interested in participating in an industry /NRC seminar.
Question 3 -
Would you be interested in a one-on-one meeting with the NRC to discuss your particular facility?
Yankee Response - Yankee is not interested in participating in a one-on-one meeting at this time; however, we would request such a meeting prior to participating in the ISAP II Program.
Question 4 -
If you remain undecided regarding participation, what additional information do you need in order to make a decision?
Yankee Response - Yankee believes that we will gain sufficient information through an industry /NRC seminar and monitoring the experiences of utilities in the ISAP II Program to make our decisions.
i
)
l
\\
! ATTACHMENT (Continued)
- Question 5 -
Do you have any potential concerns about participating:in
.ISAP II?-
Yankee Response - ' Yankee does have several concerns about participating.in the ISAP II Program. 'The most important one:at this time-is the need expressed by the NRC that the operating license be amended to include ISAP II.
Our recent experience with' a' ten year Systematic Evaluation Program (SEP) raises questions about the practically and efficiency of involving the ISAP II Program in a formal licensing process.
- Question 6 -
Do you have any suggestions for progrr.m improvements or-changes?
Yankee Response - -Yankee, at this time, does not have any suggestions for program improvements or changes.
I 1 i
i t--
=
yrw